On key projects in the West during the rainy and stormy season

PHƯƠNG ANH |

To complete the progress of key projects, investors, contractors and workers still stay at the construction site despite heavy rain.

On the afternoon of September 12, a heavy rain lasting more than 30 minutes interrupted the work of workers constructing Dai Ngai 2 Bridge, part of the Dai Ngai Bridge project connecting Tra Vinh and Soc Trang provinces.

Mr. Nguyen Tien Dung - Commander of Dat Phuong Group Joint Stock Company, a member of the joint venture contractor for the Dai Ngai Bridge Project - regularly reminds workers to check the cables and steel piles where the barges are moored because the construction takes place on the river, so all machinery and equipment are placed on the barges.

“The bridge construction site is near the river mouth, so the water flows rapidly and the wind is strong. Ensuring labor safety and traffic safety on the river is more difficult than on road projects due to the ebb and flow of water. Especially during the rainy season, construction is also affected,” said Mr. Dung.

Mr. Dung said that in the past, the unit has always maintained 3 shifts and 4 teams. In addition, they have also made roofs for concrete items (cantilever), built camps right at the construction site so that when it rains, workers can take shelter without having to move to the inland area.

De day nhanh tien do, dap ung ke hoach de ra, nhung ngay qua, nguoi lao dong nganh dien lien tuc bam tru tren cong truong de thi cong, du cho thoi tiet co bat loi
To speed up the progress, engineers and workers constructing Dai Ngai 2 Bridge stayed at the construction site despite the unpredictable weather. Photo: Phuong Anh

Mr. Tran Duc Hieu - construction engineer of Dai Ngai 2 bridge said: "We work with the spirit of overcoming the sun and rain. Only when the rain is too heavy and unsafe will we stop. When it is light rain and safe, everyone will wear raincoats and work as usual."

According to Project Management Board 85 (Ministry of Transport) - the investor of Dai Ngai Bridge Project - currently, the construction contractors have mobilized 275 personnel, 97 machines and equipment of various types, and deployed 18 construction teams. The construction output value reached over 41%. Particularly, Dai Ngai 2 Bridge has a construction output of over 50%. It is expected that in November 2024, the girder installation will be carried out, the bridge will be assembled at the end of April 2025, and the entire bridge will be completed in 2025.

Similarly, at the Chau Doc - Can Tho - Soc Trang Expressway Component 4 Project through Soc Trang province, contractors also flexibly constructed during rainy and sunny times.

According to the Project Management Board of 2 Soc Trang provinces - the Investor of the Chau Doc - Can Tho - Soc Trang Expressway Component 4 Project has so far achieved 5.02% of the contract value.

Cac cong nhan thi cong thanh phan 4 cao toc Chau Doc - Can Tho - Soc Trang voi tinh than “lam ngay khong du tranh thu lam dem“. Anh: Phuong Anh
Workers constructing the Chau Doc - Can Tho - Soc Trang Expressway Component 4 Project with the spirit of "working during the day is not enough, so take advantage of working at night". Photo: Phuong Anh

Mr. Hoang Ngoc Cuong - Project Executive Director, Dat Phuong Group Joint Stock Company, Commander of Bridge No. 22 of Package No. 10 said - when entering the rainy season, construction work is difficult, affecting progress. Therefore, depending on the work, construction will be organized in 3 shifts, 4 shifts, including day, night and holidays.

"When heavy rain makes construction impossible, the contractor will flexibly arrange for workers to rest and will make up for the time after the rain to ensure the volume is completed according to plan," said Mr. Cuong.

PHƯƠNG ANH
TIN LIÊN QUAN

“Vượt nắng thắng mưa” đưa đường dây 500kV mạch 3 về đích

Nhóm PV |

Lời tòa soạn: Dự án đường dây 500KV mạch 3 dần về đích. Phóng viên Báo Lao Động đã có những ngày đồng hành trên công trường cùng người lao động, để ghi lại những nhịp lao động hăng say, hối hả; những nụ cười, giọt mồ hôi và cả giọt nước mắt. Dù khó khăn, vất vả, áp lực lớn, nhưng tất cả đều chung sức, đồng lòng để cùng viết nên kỳ tích, quyết tâm đưa công trình hoàn thành với thời gian ngắn nhất, góp phần đảm bảo an ninh năng lượng quốc gia.

Vượt nắng thắng mưa trên công trình cầu gần 8.000 tỉ đồng

PHƯƠNG ANH |

Ghi nhận của Lao Động tại công trình cầu Đại Ngãi 2 nối Quốc lộ Nam Sông Hậu với huyện Cù Lao Dung (tỉnh Sóc Trăng) các công nhân đang khẩn trương thi công mặc dù thời tiết tương đối phức tạp lúc nắng lúc mưa.

Phát huy tinh thần vượt nắng thắng mưa, thi đua lao động trên công trường đường dây 500kV mạch 3

Xuân Hùng - Quách Du |

Chiều 22.4, đoàn công tác của Tổng Liên đoàn Lao động (LĐLĐ) Việt Nam do ông Nguyễn Đình Khang - Ủy viên Trung ương Đảng, Chủ tịch Tổng LĐLĐ - đã đến thăm hỏi, động viên, tặng quà khích lệ công nhân, người lao động đang làm việc trên công trường dự án đường dây 500kV mạch 3 qua địa bàn tỉnh Thanh Hóa.

Phê chuẩn ông Lê Ngọc Châu làm Chủ tịch UBND tỉnh Hải Dương

PHẠM ĐÔNG |

Thủ tướng Chính phủ đã phê chuẩn kết quả bầu chức vụ Chủ tịch UBND tỉnh Hải Dương đối với ông Lê Ngọc Châu.

Tháo gỡ cho dự án, đất đai trong kết luận thanh tra, bản án

PHẠM ĐÔNG |

Phó Thủ tướng Chính phủ nhấn mạnh, quan trọng nhất là xác định đúng người, rõ việc trong tổ chức tháo gỡ cho dự án, đất đai trong kết luận thanh tra, bản án.

Dân phố cổ Hội An chưa mặn mà đón khách thuê homestay

Hoàng Bin |

Sau hơn 4 tháng thí điểm mô hình đón khách lưu trú trải nghiệm cùng cư dân phố cổ Hội An, chỉ có 1 hộ dân đăng ký loại hình này.

Thi thể trôi sông được xác định là nạn nhân sập cầu Phong Châu

Tô Công |

Phú Thọ - Thi thể nam giới phát hiện trưa 16.9 trên sông Hồng được xác định là nạn nhân mất tích trong vụ sập cầu Phong Châu.

Lào Cai thông tin về nhu cầu, đầu mối hỗ trợ bà con vùng lũ

Bảo Nguyên |

Tỉnh Lào Cai vừa thông tin cụ thể về nhu cầu hỗ trợ người dân vùng lũ và đầu mối tiếp nhận cứu trợ của các huyện, thị xã trên địa bàn.

Vượt nắng thắng mưa trên công trình cầu gần 8.000 tỉ đồng

PHƯƠNG ANH |

Ghi nhận của Lao Động tại công trình cầu Đại Ngãi 2 nối Quốc lộ Nam Sông Hậu với huyện Cù Lao Dung (tỉnh Sóc Trăng) các công nhân đang khẩn trương thi công mặc dù thời tiết tương đối phức tạp lúc nắng lúc mưa.

Phát huy tinh thần vượt nắng thắng mưa, thi đua lao động trên công trường đường dây 500kV mạch 3

Xuân Hùng - Quách Du |

Chiều 22.4, đoàn công tác của Tổng Liên đoàn Lao động (LĐLĐ) Việt Nam do ông Nguyễn Đình Khang - Ủy viên Trung ương Đảng, Chủ tịch Tổng LĐLĐ - đã đến thăm hỏi, động viên, tặng quà khích lệ công nhân, người lao động đang làm việc trên công trường dự án đường dây 500kV mạch 3 qua địa bàn tỉnh Thanh Hóa.