Overcoming sun and rain on highway construction projects

PHƯƠNG ANH |

Construction contractors are accelerating the progress of implementing the Chau Doc - Can Tho - Soc Trang component 4 expressway project.

Recorded by Labor on the morning of August 28, at bridge No. 22, package No. 10 of Chau Doc - Can Tho - Soc Trang expressway, section passing through Soc Trang province, about 100 engineers and workers are urgently constructing with the spirit of overcoming Sun beats rain, 3 shifts, 4 crews.

Construction workers of bridge No. 22 - Project component 4 Chau Doc - Can Tho - Soc Trang. Photo: Phuong Anh
Construction workers of bridge No. 22 - Project component 4 Chau Doc - Can Tho - Soc Trang. Photo: Phuong Anh

Mr. Hoang Ngoc Cuong - Project Executive Director, Dat Phuong Group Joint Stock Company - informed that to date, 67/82 piles have been constructed, 34/84 beams have been cast, 4 pier bases and 1 abutment have been installed and 6 have been installed. beam span, reaching 50% of output value. It is expected that by December 31, 2024, it will reach 80% of output value.

Also according to Mr. Cuong, implementing the 15-day rush to speed up the construction progress of Project Component 4 and celebrate the National Day of September 2, the contractor has increased 2 teams and 1 shift (from 6:30 p.m. to 11 p.m.) to speed up registration progress with investors. The peak period has not yet ended but progress has reached 100% of the registration value.

Mr. Lam Van Man - Member of the Party Central Committee, Secretary of the Soc Trang Provincial Party Committee (left) inspected the construction progress of the expressway project at package number 10 on the morning of August 28. Photo: Phuong Anh
Mr. Lam Van Man - Member of the Party Central Committee, Secretary of the Soc Trang Provincial Party Committee (left) - inspected the construction progress of the expressway project at package number 10 on the morning of August 28. Photo: Phuong Anh

According to Project Management Board 2 - Investor of Project Component 4, the project has a total investment capital of 11,961 billion VND, to date reaching 3.94% of the contract value. In 2024 alone, capital of 2,463 billion VND was allocated, over 390 billion VND has been disbursed, reaching 15.8% of the plan. The project has 4 bidding packages, currently reaching from 1.51 - 7.96%.

Regarding backfilling materials, there are currently 2 sand mines for the project: MS03 and MS01. As of August 27, about 10,000m3 has been supplied. Relevant industries are also carrying out procedures to transfer saline sand from B1.1 and B1.2 mines and speeding up licensing procedures for the remaining river sand mine to supply sand for the Project.

Ms. Ho Thi Cam Dao - Permanent Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council and Mr. Tran Van Lau (2nd from left) - Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of Soc Trang province presented gifts to encourage the contractor, highway construction workers. Photo: Phuong Anh
Ms. Ho Thi Cam Dao - Permanent Deputy Secretary of the Provincial Party Committee, Chairman of the People's Council of Soc Trang province and Mr. Tran Van Lau (2nd from left) - Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of Soc Trang province - presented encouragement gifts contractors, highway construction workers. Photo: Phuong Anh

Currently, contractors are focusing on completing the internal service road, and simultaneously implementing construction of the remaining bridges on the route. Additional construction tips speed up progress for ongoing bridges. Carrying out construction in 3 shifts, 4 crews, overcoming sun and rain, speeding up the construction progress of bridges to compensate for the slow volume. Prepare materials, labor, and equipment to speed up the progress of the road right after sand arrives at the construction site.

Previously, the leaders of the People's Committee of Soc Trang province launched a 15-day and night rush competition to speed up the construction progress of the 4-part project of Chau Doc - Can Tho - Soc Trang expressway, phase 1.

Chairman of the People's Committee of Soc Trang province requested construction contractors to re-establish detailed construction progress, urgently gather personnel, equipment, and materials as soon as sand for the foundation is available to speed up progress and organize construction. "3 shifts, 4 crews" to compensate for slow progress in recent times, ensuring project progress.

PHƯƠNG ANH
TIN LIÊN QUAN

Chỉ mới 80.000m3 cát biển về cao tốc Cần Thơ - Cà Mau

PHƯƠNG ANH |

Do ảnh hưởng điều kiện khai thác nên đến thời điểm hiện tại chỉ khoảng 80.000m3 cát biển đưa về cao tốc Cần Thơ - Cà Mau.

Lượng cát biển đưa về cao tốc chưa đạt được như kỳ vọng

PHƯƠNG ANH |

Biển động, gió lớn, đường vận chuyển xa... dẫn đến lượng cát biển đưa về cao tốc Cần Thơ - Cà Mau chưa đạt được như kỳ vọng.

Gần 1 triệu m3 cát đã về cao tốc trục ngang đoạn Cần Thơ

Tạ Quang |

Cao tốc Châu Đốc - Cần Thơ - Sóc Trăng (cao tốc trục ngang) đoạn đi qua Cần Thơ, cát đã về trên công trường trên 850.000m3.

Áp thấp mạnh lên thành bão, mưa lớn ở Bắc Bộ, Trung Bộ

Khương Duy |

Cục Quản lý đê điều và Phòng, chống thiên tai vừa phát đi tin áp thấp nhiệt đới gần Biển Đông và cảnh báo mưa lớn ở nhiều nơi.

Mệt mỏi vì bơm xong lại ngập trong biệt thự chục tỉ ở Hà Nội

Đền Phú - Vân Trường |

Hà Nội - Sau khi được bơm nước, dọn dẹp sau bão số 3, nhiều biệt thự tại KĐT Nam An Khánh lại ngập sau cơn mưa lớn.

Đại diện quán cơm bị tẩy chay ở Hạ Long xin lỗi khách hàng

Nguyễn Hùng |

Quảng Ninh - Thông tin từ UBND TP Hạ Long sáng 17.9, tại buổi làm việc giữa các bên hôm qua, đại diện quán Cơm sạch bà Liên đã lên tiếng xin lỗi khách hàng.

Kỳ thủ Lê Quang Liêm thắng đương kim vô địch thế giới

tam nguyên |

Chiến thắng của Lê Quang Liêm giúp tuyển Việt Nam hòa tuyển Trung Quốc tại Olympiad Cờ vua 2024.

Còn bao nhiêu hồ thủy điện mở cửa xả lũ?

ANH TUẤN |

Đến nay, các hồ thủy điện đang thực hiện xả điều tiết gồm Tuyên Quang (1 cửa), Thác Bà (2 cửa), Trung Sơn (3 cửa), Bản Vẽ (3 cửa).

Only 80,000m3 of sea sand has reached the Can Tho - Ca Mau highway

PHƯƠNG ANH |

Due to the impact of mining conditions, up to now only about 80,000m3 of sea sand has been brought to Can Tho - Ca Mau highway .

The amount of sea sand brought to the highway has not reached expectations

PHƯƠNG ANH |

Rough seas, high winds, long transport routes... lead to the amount of sea sand brought to the Can Tho - Ca Mau highway not reaching expectations.

Nearly 1 million m3 of sand has returned to the horizontal highway section of Can Tho

Tạ Quang |

Chau Doc - Can Tho - Soc Trang Expressway (horizontal highway) passing through Can Tho, sand has returned to the construction site over 850,000m3.