Recorded by Labor on the morning of August 28, at bridge No. 22, package No. 10 of Chau Doc - Can Tho - Soc Trang expressway, section passing through Soc Trang province, about 100 engineers and workers are urgently constructing with the spirit of overcoming Sun beats rain, 3 shifts, 4 crews.
Mr. Hoang Ngoc Cuong - Project Executive Director, Dat Phuong Group Joint Stock Company - informed that to date, 67/82 piles have been constructed, 34/84 beams have been cast, 4 pier bases and 1 abutment have been installed and 6 have been installed. beam span, reaching 50% of output value. It is expected that by December 31, 2024, it will reach 80% of output value.
Also according to Mr. Cuong, implementing the 15-day rush to speed up the construction progress of Project Component 4 and celebrate the National Day of September 2, the contractor has increased 2 teams and 1 shift (from 6:30 p.m. to 11 p.m.) to speed up registration progress with investors. The peak period has not yet ended but progress has reached 100% of the registration value.
According to Project Management Board 2 - Investor of Project Component 4, the project has a total investment capital of 11,961 billion VND, to date reaching 3.94% of the contract value. In 2024 alone, capital of 2,463 billion VND was allocated, over 390 billion VND has been disbursed, reaching 15.8% of the plan. The project has 4 bidding packages, currently reaching from 1.51 - 7.96%.
Regarding backfilling materials, there are currently 2 sand mines for the project: MS03 and MS01. As of August 27, about 10,000m3 has been supplied. Relevant industries are also carrying out procedures to transfer saline sand from B1.1 and B1.2 mines and speeding up licensing procedures for the remaining river sand mine to supply sand for the Project.
Currently, contractors are focusing on completing the internal service road, and simultaneously implementing construction of the remaining bridges on the route. Additional construction tips speed up progress for ongoing bridges. Carrying out construction in 3 shifts, 4 crews, overcoming sun and rain, speeding up the construction progress of bridges to compensate for the slow volume. Prepare materials, labor, and equipment to speed up the progress of the road right after sand arrives at the construction site.
Previously, the leaders of the People's Committee of Soc Trang province launched a 15-day and night rush competition to speed up the construction progress of the 4-part project of Chau Doc - Can Tho - Soc Trang expressway, phase 1.
Chairman of the People's Committee of Soc Trang province requested construction contractors to re-establish detailed construction progress, urgently gather personnel, equipment, and materials as soon as sand for the foundation is available to speed up progress and organize construction. "3 shifts, 4 crews" to compensate for slow progress in recent times, ensuring project progress.