Hanoi Ring Road 2.5 accelerates construction of many sections

Minh Hạnh |

Hanoi - Ring Road 2.5 project is being accelerated for site clearance and construction. Many sections of the route have been handed over land, and some basic items have been completed.

In early June, many sections of the Hanoi Ring Road 2.5 project are being accelerated with the expectation of putting the road into operation soon, reducing inner-city traffic pressure and creating motivation for socio-economic development.

After many years of implementation facing difficulties in capital and site clearance, the project is entering an acceleration phase. The road plays a role in connecting Ring Road 2 with Ring Road 3, contributing to completing the capital's framework traffic network.

According to the plan, Ring Road 2.5 is about 19.64km long, starting from Ciputra urban area and ending at Ring Road 3 intersection near Thanh Tri bridge, passing through many wards such as Xuan Dinh, Cau Giay, Thanh Xuan, Dinh Cong, Hoang Mai and Linh Nam. The entire route is divided into 13 investment sections.

Nút thắt mặt bằng trên Vành đai 2,5 dần được tháo gỡ. Ảnh: Hải Lê
The site clearance bottleneck on Ring Road 2.5 is gradually being removed. Photo: Hai Le

In Xuan Dinh ward, site clearance is being promoted. According to the Ward Infrastructure Investment Project Management Board, the locality has completed investigation, measurement, inventory and developed a compensation and resettlement support plan for all 54 affected cases.

In the western area of ​​the city, the sections Dich Vong - Duong Dinh Nghe, Vu Pham Ham - Tran Duy Hung and Nguy Nhu Kon Tum - Nguyen Trai are gradually taking shape after the groundbreaking ceremony on March 20, 2026.

In which, the Vu Pham Ham - Tran Duy Hung section 600m long passing through Trung Kinh Ha residential area (Yen Hoa ward) is being focused on site clearance. The project recovers more than 30,600m2 of land, affecting 369 households and organizations. Local authorities are speeding up procedures to soon hand over clean ground to the construction unit.

At the Nguy Nhu Kon Tum - Nguyen Trai section, about 950m long, site clearance is basically completed. More than 39,000m2 of land has been handed over to the investor to implement technical infrastructure items.

After the works on the route were dismantled, the appearance of the area has changed significantly. Many locations have gathered machinery and materials; workers are constructing drainage systems, underground technical infrastructure and auxiliary items.

Vành đai 2,5 Hà Nội tăng tốc sau nhiều năm chậm tiến độ. Ảnh: Hải Lê
Hanoi Ring Road 2.5 accelerates after many years of slow progress. Photo: Hai Le

The Nguyen Trai - Dam Hong section in Khuong Dinh ward is considered one of the land clearance hotspots of the entire project. The project has a cross-section of 50m, with a total investment of more than 2,432 billion VND. To implement the project, the locality must recover more than 60,900m2 of land from 736 cases, including 16 organizations and 720 households and individuals.

Despite the large workload, many areas have been handed over to contractors for construction. People expect the project to be completed and contribute to reducing congestion on Nguyen Trai, Khuong Dinh, Khuong Ha and Dam Hong areas.

Meanwhile, the Dam Hong - National Highway 1A section, about 2km long, after being technically opened in early 2026, is now basically completed. The road has a cross-section of 40m, a scale of 6 lanes, sidewalks, green trees, lighting and drainage are being synchronously completed. When put into operation, this section will contribute to reducing the load on the Giai Phong, Kim Giang, Nguyen Xien axes and the southern gateway of the city.

However, the National Highway 1A - Linh Nam section, especially the Linh Nam - Ring Road 3 section, still faces many difficulties due to site clearance problems. Many existing civil works and technical infrastructure have not been relocated, affecting the construction progress.

This is the final section of Ring Road 2.5 before connecting with Ring Road 3 and Thanh Tri bridge area. Therefore, removing obstacles in Linh Nam area is considered a key factor to close the entire route, promoting the traffic connection efficiency of the project in the coming time.

Minh Hạnh
RELATED NEWS

Hanoi has not yet finalized the time to ban gasoline vehicles in Ring Road 1

|

Hanoi - The city continues to study and absorb opinions to complete the draft resolution on low-emission zones in Ring Road 1.

New look of the ring road project worth more than 7,210 billion VND in Hanoi

|

Hanoi - The Ring Road 1 project, Hoang Cau - Voi Phuc section, is being urgently implemented, in which some sections have been asphalted.

Hanoi considers shortening the progress of Ring Road 4 to be completed 6 months ahead of schedule

|

Hanoi is considering shortening the progress of component project 3 of Ring Road 4 - Capital Region, setting a target to technically open traffic about 6 months ahead of schedule.

Trade unions must become pioneers in promoting science and technology

|

Faced with the wave of artificial intelligence, the Vietnam Trade Union needs to help workers access new knowledge, improve skills and adapt to development requirements.

Deeper understanding of the role of grassroots trade union officials

|

Thanh Hoa - Attending and following the opening session of the 14th Vietnam Trade Union Congress, union members and trade union officials are more deeply aware of the role of the grassroots level.

Solutions to promote labor safety culture in the face of new requirements

|

Hanoi - Participating in the Workshop Center No. 1 of the 14th Vietnam Trade Union Congress, Mr. Nguyen Manh Kha - Chairman of Petrovietnam Trade Union, presented on Solutions to promote occupational safety culture in the face of new requirements.

The strength of the trade union starts from the workers' belief

|

Strongly innovating trade union organizations, improving representative capacity, and protecting workers' rights are requirements set in the new period.

Proposing 2 more days off on National Day

|

Union members, workers and trade union organizations proposed considering and adding 2 more holidays on National Day.

Hanoi has not yet finalized the time to ban gasoline vehicles in Ring Road 1

HOÀI ANH |

Hanoi - The city continues to study and absorb opinions to complete the draft resolution on low-emission zones in Ring Road 1.

New look of the ring road project worth more than 7,210 billion VND in Hanoi

SÓNG HỮU |

Hanoi - The Ring Road 1 project, Hoang Cau - Voi Phuc section, is being urgently implemented, in which some sections have been asphalted.

Hanoi considers shortening the progress of Ring Road 4 to be completed 6 months ahead of schedule

Minh Hạnh |

Hanoi is considering shortening the progress of component project 3 of Ring Road 4 - Capital Region, setting a target to technically open traffic about 6 months ahead of schedule.