Building fences to protect 5,000 hectares of land at Long Thanh airport reaches over 32%

HÀ ANH CHIẾN |

Dong Nai - The fence protecting the entire area of 5,000 hectares under the Long Thanh airport project has been implemented by more than 32%.

On June 18, according to information from Airports Corporation of Vietnam (ACV), package 2.10, fence border of Long Thanh International Airport (abbreviated as Long Thanh airport) outside the scope of 1,810 ha is being implemented by the contractor consortium to excavate the foundation of the project, construct M200 concrete foundation, construct reinforcement concrete, construct brick walls, with a realized value of more than 25 billion VND, reaching more than 32%.

Bidding package 2.10, Long Thanh airport border fence outside the scope of 1.810 ha started in October 2024 has a contract value of more than 78 billion VND.

Previously, package 2.4, fence within the scope of 1,810 hectares of Long Thanh airport had completed 100% construction with a length of 7,856 m.

Dong Nai Provincial People's Committee once proposed to soon complete the construction of a protective fence for the entire area of 5,000 hectares belonging to the Long Thanh airport project, with a length of about 30 km.

The solution is to build a closed fence around the Long Thanh airport project to prevent re-encroachment after clearing clean land.

The entire component project 3 of Long Thanh airport has 15 main construction packages (currently 3 packages have been completed and 12 packages are under construction). According to ACV's report, the actual value of the entire project to date has reached over 76%. Contractors are simultaneously accelerating, organizing "3 shifts, 4 teams" day and night, and at the same time responding to the "180 days to accelerate to the finish line" emulation period.

According to the schedule, the Long Thanh airport project will be put into commercial operation at the end of 2026.

HÀ ANH CHIẾN
RELATED NEWS

Dong Nai recovers more than 2,465 hectares of land in 4 wards and communes near Long Thanh airport

|

Dong Nai - 6 compensation and site clearance projects in wards and communes of Long Thanh, Nhon Trach, Long Phuoc, Phuoc An have a total area of more than 2,465 ha.

Long Thanh airport passenger terminal technical operation in September

|

Dong Nai - Long Thanh airport passenger terminal will be technically operational in September 2026, moving towards commercial operation at the end of the year.

Long Thanh Airport extends labor recruitment for aviation fuel branch

|

Dong Nai - Long Thanh Airport (Long Thanh ward) extends labor recruitment for Long Thanh Aviation Fuel Services Branch.

The 2nd runway of Long Thanh airport will be completed on September 30

|

Dong Nai - Package 4. The 2nd runway of Long Thanh airport will be completed on September 30, 2026.

Ms. Le Thi Thuy re-elected as Chairwoman of the 14th Vietnam Women's Union

|

On June 18, the results of the first Conference of the 14th Central Executive Committee of the Vietnam Women's Union, term 2026 - 2031 were announced.

Students of Ho Chi Minh City University of Law bring law to workers through comedy

|

At the Legal Consulting program co-organized by Lao Dong Newspaper, workers accessed legal knowledge through comedy performances by students.

World Cup 2026 schedule today 18. 6

|

Update World Cup 2026 schedule today (June 18) and early tomorrow morning (June 19), Vietnam time.

Dong Nai recovers more than 2,465 hectares of land in 4 wards and communes near Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - 6 compensation and site clearance projects in wards and communes of Long Thanh, Nhon Trach, Long Phuoc, Phuoc An have a total area of more than 2,465 ha.

Long Thanh airport passenger terminal technical operation in September

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport passenger terminal will be technically operational in September 2026, moving towards commercial operation at the end of the year.

Long Thanh Airport extends labor recruitment for aviation fuel branch

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport (Long Thanh ward) extends labor recruitment for Long Thanh Aviation Fuel Services Branch.

The 2nd runway of Long Thanh airport will be completed on September 30

HÀ ANH CHIẾN |

Dong Nai - Package 4. The 2nd runway of Long Thanh airport will be completed on September 30, 2026.