Ceremony on the North-South Expressway construction site through Quang Binh

CÔNG SÁNG |

During the holidays, the construction site of the North-South Expressway through Quang Binh is still bustling with machinery and workers to speed up the project's progress.

Speed ​​up construction

During the holidays of September 2nd this year, the construction site of the North-South Expressway through Quang Binh province was still bustling with machinery. Taking advantage of the dry summer days to prepare for the rainy season, contractors constructing the North-South Expressway through Quang Binh province have simultaneously deployed construction to speed up progress.

The North-South Eastern Expressway Project for the 2021-2025 period passing through Quang Binh includes 3 component projects: Vung Ang - Bung, Bung - Van Ninh and Van Ninh - Cam Lo with a total length of more than 126km.

Machinery is working loudly at the North-South Expressway construction site. Photo: Cong Sang
Machinery is working loudly at the North-South Expressway construction site. Photo: Cong Sang

The Ministry of Transport requires investors of North-South Expressway component projects to speed up construction and proactively prepare plans to respond to storms and floods in the upcoming rainy season.

Workers here work in 3 shifts, day and night, to complete the items on schedule by the end of September this year.

Regardless of rain or shine, holidays, workers still work on the North-South Expressway. Photo: Cong Sang
Regardless of rain or shine, holidays, workers still work on the North-South Expressway. Photo: Cong Sang

At the construction site of the Van Ninh – Cam Lo highway through Le Thuy district – Quang Binh province, machinery and workers are rolling the road, and in some places are spreading the roadbed.

The Ho Chi Minh Road Project Management Board (Ministry of Transport) is the investor of the Van Ninh - Cam Lo Expressway Component Project. Mr. Chu Van Long - Deputy Head of Project Management Department 4, Ho Chi Minh Road Project Management Board said that this is a favorable time to accelerate the implementation of the completion of the stages, to avoid heavy rain affecting the construction.

Taking advantage of the dry weather to speed up construction progress. Photo: Cong Sang
Taking advantage of the dry weather to speed up construction progress. Photo: Cong Sang

“We are currently carrying out stages such as roadbed construction, asphalt construction, etc. at full capacity while the weather is still sunny and dry,” said Mr. Long.

Construction road adhesion

Worker Nguyen The Gian, who is constructing a hollow asphalt concrete section on the North-South expressway through Phu Thuy commune (Le Thuy district), said that the weather is sunny so the unit is speeding up the construction of the sections on the route.

Every day, the unit works 3 shifts from morning to night. At noon, workers take a break to eat and rest, then continue their work on the road.

Workers find solutions to avoid the heat on the highway. Photo: Cong Sang
Workers find solutions to avoid the heat on the highway. Photo: Cong Sang

"The workers also understood the assigned tasks, took advantage of every moment to speed up the progress, everyone was happy to help the project achieve the results as assigned by the Prime Minister" - Mr. Gian said.

In the XL-02 package, the Bung - Van Ninh component project (through Quang Binh province), the construction unit is mobilizing over 400 engineers, workers and over 250 vehicles and construction equipment on the route. Many sections have been paved by the construction unit, and the work is being carried out vigorously on every meter of road.

From above, the intersection on the Bung - Van Ninh route is gradually taking shape, part of which is paved.

The intersection on the Bung - Van Ninh route is gradually taking shape. Photo: Cong Sang
The intersection on the Bung - Van Ninh route is gradually taking shape. Photo: Cong Sang

The contractor representative said that the construction work at the site was arranged scientifically and methodically, and was completed as it progressed, in order to meet the contract schedule.

Up to now, the North-South Eastern Expressway project in the 2021-2025 period passing through Quang Binh has handed over 105.99km/126.43km of land; 419m remaining.

Local authorities are continuing to implement plans to hand over the site to the contractor to ensure the project is on schedule.

CÔNG SÁNG
TIN LIÊN QUAN

Giải pháp nào cho mặt bằng cao tốc Bắc - Nam qua Quảng Bình?

CÔNG SÁNG |

Tỉnh Quảng Bình sẽ cưỡng chế những trường hợp không đồng ý với chính sách bồi thường, giải phóng mặt bằng theo quy định của pháp luật tại cao tốc Bắc - Nam.

Dự án cao tốc Bắc - Nam qua Quảng Bình còn vướng mặt bằng

CÔNG SÁNG |

Công tác giải phóng mặt bằng Dự án xây dựng công trình đường bộ cao tốc Bắc - Nam phía Đông đoạn qua địa phận tỉnh Quảng Bình đến này vẫn còn hơn 500m.

Hợp long cầu bắc qua sông Gianh tuyến cao tốc Bắc - Nam

CÔNG SÁNG |

Cầu sông Gianh bắc từ xã Quảng Thanh (huyện Quảng Trạch) qua xã Quảng Hải và Quảng Lộc (thị xã Ba Đồn, tỉnh Quảng Bình) vừa được hợp long ngày 14.8.

Người dân TPHCM thích thú khi tận mắt thấy hàng trăm siêu xe

Anh Tú - Thanh Vũ |

TPHCM - Ngày 14.9, Hành trình Gumball 3000 đã diễn ra ở đường Lê Lợi, Quận 1 thu hút hàng ngàn người đến chiêm ngưỡng 120 siêu xe từ nhiều nước trên thế giới.

Ngôi làng quanh năm tô vẽ, tạo tiếng trống dịp Tết Trung thu

Thanh Bình - Khánh Linh |

Làng nghề ông Hảo (xã Liêu Xá, huyện Yên Mỹ, tỉnh Hưng Yên) là nơi khai sinh của nhiều món đồ chơi Trung thu cổ truyền.

Làm từ thiện không trung thực là vi phạm đạo đức, pháp luật

NHÓM PV |

PGS.TS Phạm Ngọc Trung đã có những chia sẻ xung quanh câu chuyện về tình người và vấn đề làm từ thiện sau cơn bão số 3.

Chưa đóng cửa mỏ vàng cũ, đã giao đất để làm mỏ vàng mới

HƯNG THƠ |

Công ty trây ỳ trả lại đất ở mỏ vàng A Pey A được tỉnh Quảng Trị cho thuê đất để thực hiện dự án mỏ vàng A Vao.

Đình chỉ 2 chủ tịch xã ở Lào Cai do lơ là phòng chống bão lũ

Bảo Nguyên |

UBND huyện Bát Xát, tỉnh Lào Cai vừa ra quyết định đình chỉ công tác đối Chủ tịch UBND xã Trung Lèng Hồ và Pa Cheo do vi phạm quy định phòng, chống bão lũ.

What is the solution for the North-South expressway through Quang Binh?

CÔNG SÁNG |

Quang Binh Province will enforce cases that do not agree with the compensation and site clearance policy according to the provisions of law at the North-South Expressway .

The North-South Expressway project through Quang Binh still has land problems

CÔNG SÁNG |

Site clearance work for the North-South Expressway Construction Project in the East, section passing through Quang Binh province , still has more than 500m left.

Hop Long Bridge spans the Gianh River on the North-South Expressway

CÔNG SÁNG |

The Gianh River bridge spanning from Quang Thanh commune (Quang Trach district) through Quang Hai and Quang Loc communes (Ba Don town, Quang Binh province ) was just completed on August 14.