Ceremony on the North-South Expressway construction site through Quang Binh

CÔNG SÁNG |

During the holidays, the construction site of the North-South Expressway through Quang Binh is still bustling with machinery and workers to speed up the project's progress.

Speed ​​up construction

During the holidays of September 2nd this year, the construction site of the North-South Expressway through Quang Binh province was still bustling with machinery. Taking advantage of the dry summer days to prepare for the rainy season, contractors constructing the North-South Expressway through Quang Binh province have simultaneously deployed construction to speed up progress.

The North-South Eastern Expressway Project for the 2021-2025 period passing through Quang Binh includes 3 component projects: Vung Ang - Bung, Bung - Van Ninh and Van Ninh - Cam Lo with a total length of more than 126km.

Machinery is working loudly at the North-South Expressway construction site. Photo: Cong Sang
Machinery is working loudly at the North-South Expressway construction site. Photo: Cong Sang

The Ministry of Transport requires investors of North-South Expressway component projects to speed up construction and proactively prepare plans to respond to storms and floods in the upcoming rainy season.

Workers here work in 3 shifts, day and night, to complete the items on schedule by the end of September this year.

Regardless of rain or shine, holidays, workers still work on the North-South Expressway. Photo: Cong Sang
Regardless of rain or shine, holidays, workers still work on the North-South Expressway. Photo: Cong Sang

At the construction site of the Van Ninh – Cam Lo highway through Le Thuy district – Quang Binh province, machinery and workers are rolling the road, and in some places are spreading the roadbed.

The Ho Chi Minh Road Project Management Board (Ministry of Transport) is the investor of the Van Ninh - Cam Lo Expressway Component Project. Mr. Chu Van Long - Deputy Head of Project Management Department 4, Ho Chi Minh Road Project Management Board said that this is a favorable time to accelerate the implementation of the completion of the stages, to avoid heavy rain affecting the construction.

Taking advantage of the dry weather to speed up construction progress. Photo: Cong Sang
Taking advantage of the dry weather to speed up construction progress. Photo: Cong Sang

“We are currently carrying out stages such as roadbed construction, asphalt construction, etc. at full capacity while the weather is still sunny and dry,” said Mr. Long.

Construction road adhesion

Worker Nguyen The Gian, who is constructing a hollow asphalt concrete section on the North-South expressway through Phu Thuy commune (Le Thuy district), said that the weather is sunny so the unit is speeding up the construction of the sections on the route.

Every day, the unit works 3 shifts from morning to night. At noon, workers take a break to eat and rest, then continue their work on the road.

Workers find solutions to avoid the heat on the highway. Photo: Cong Sang
Workers find solutions to avoid the heat on the highway. Photo: Cong Sang

"The workers also understood the assigned tasks, took advantage of every moment to speed up the progress, everyone was happy to help the project achieve the results as assigned by the Prime Minister" - Mr. Gian said.

In the XL-02 package, the Bung - Van Ninh component project (through Quang Binh province), the construction unit is mobilizing over 400 engineers, workers and over 250 vehicles and construction equipment on the route. Many sections have been paved by the construction unit, and the work is being carried out vigorously on every meter of road.

From above, the intersection on the Bung - Van Ninh route is gradually taking shape, part of which is paved.

The intersection on the Bung - Van Ninh route is gradually taking shape. Photo: Cong Sang
The intersection on the Bung - Van Ninh route is gradually taking shape. Photo: Cong Sang

The contractor representative said that the construction work at the site was arranged scientifically and methodically, and was completed as it progressed, in order to meet the contract schedule.

Up to now, the North-South Eastern Expressway project in the 2021-2025 period passing through Quang Binh has handed over 105.99km/126.43km of land; 419m remaining.

Local authorities are continuing to implement plans to hand over the site to the contractor to ensure the project is on schedule.

CÔNG SÁNG
TIN LIÊN QUAN

Giải pháp nào cho mặt bằng cao tốc Bắc - Nam qua Quảng Bình?

CÔNG SÁNG |

Tỉnh Quảng Bình sẽ cưỡng chế những trường hợp không đồng ý với chính sách bồi thường, giải phóng mặt bằng theo quy định của pháp luật tại cao tốc Bắc - Nam.

Dự án cao tốc Bắc - Nam qua Quảng Bình còn vướng mặt bằng

CÔNG SÁNG |

Công tác giải phóng mặt bằng Dự án xây dựng công trình đường bộ cao tốc Bắc - Nam phía Đông đoạn qua địa phận tỉnh Quảng Bình đến này vẫn còn hơn 500m.

Hợp long cầu bắc qua sông Gianh tuyến cao tốc Bắc - Nam

CÔNG SÁNG |

Cầu sông Gianh bắc từ xã Quảng Thanh (huyện Quảng Trạch) qua xã Quảng Hải và Quảng Lộc (thị xã Ba Đồn, tỉnh Quảng Bình) vừa được hợp long ngày 14.8.

Tuyển Indonesia thua trận đầu tiên tại vòng loại 3 World Cup 2026

NHÓM PV |

Tối 15.10, đội tuyển Indonesia nhận thất bại 1-2 trên sân tuyển Trung Quốc tại vòng loại thứ 3 World Cup 2026.

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Phá đường dây cờ bạc nghìn tỉ qua mạng, tạm giam 12 người

Thành Nhân |

Bến Tre - Lực lượng Công an vừa triệt xóa đường dây cờ bạc trên không gian mạng với tổng số tiền giao dịch hơn 1.800 tỉ đồng.

Nổ nồi hấp tinh dầu, 1 bé gái bị thương, 5 căn nhà ảnh hưởng

LÝ LINH |

TPHCM - Ngày 15.10, Công an huyện Bình Chánh đang điều tra vụ nổ nồi hấp tại một cơ sở sản xuất tinh dầu trên địa bàn xã Vĩnh Lộc A khiến một bé gái bị thương.

Nguyên chủ tịch xã ở Thái Bình bị tố lạm quyền để trục lợi

TRUNG DU |

Thái Bình - Nguyên Chủ tịch UBND xã Quỳnh Hải, huyện Quỳnh Phụ bị tố lợi dụng chức vụ quyền hạn để tư lợi, trục lợi cho bản thân, gia đình.

Giải pháp nào cho mặt bằng cao tốc Bắc - Nam qua Quảng Bình?

CÔNG SÁNG |

Tỉnh Quảng Bình sẽ cưỡng chế những trường hợp không đồng ý với chính sách bồi thường, giải phóng mặt bằng theo quy định của pháp luật tại cao tốc Bắc - Nam.

Dự án cao tốc Bắc - Nam qua Quảng Bình còn vướng mặt bằng

CÔNG SÁNG |

Công tác giải phóng mặt bằng Dự án xây dựng công trình đường bộ cao tốc Bắc - Nam phía Đông đoạn qua địa phận tỉnh Quảng Bình đến này vẫn còn hơn 500m.

Hợp long cầu bắc qua sông Gianh tuyến cao tốc Bắc - Nam

CÔNG SÁNG |

Cầu sông Gianh bắc từ xã Quảng Thanh (huyện Quảng Trạch) qua xã Quảng Hải và Quảng Lộc (thị xã Ba Đồn, tỉnh Quảng Bình) vừa được hợp long ngày 14.8.