What is the solution for the North-South expressway through Quang Binh?

CÔNG SÁNG |

Quang Binh Province will enforce cases that do not agree with the compensation and site clearance policy according to the provisions of law at the North-South Expressway .

There are 610m of space remaining

The Eastern North-South Expressway construction project for the period 2021 - 2025, section through Quang Binh province, has 3 component projects, with a length of 126.43km, passing through 6 districts, towns and cities. streets and 35 communes and wards.

To date, the length handed over to the Project Management Board is 126.82km, reaching 99.51%, currently the remaining 610m is obstructed by land. Accounts for 0.49% passing through 4 districts and towns.

Accordingly, Quang Trach district has handed over 25.29km/25.3km, the remaining 10m. Ba Don town has handed over 9.32km/9.35km; 35m remaining. Bo Trach district has handed over 28.96km/29.04km, the remaining 80m. In particular, Le Thuy district has handed over 31.46 km/31.95 km; The remaining length is 490m.

The ground level of the North-South expressway through Quang Binh in Le Thuy district is still problematic. Photo: Cong Sang
The ground level of the North-South expressway through Quang Binh in Le Thuy district is still problematic. Photo: Cong Sang

A representative of the Ho Chi Minh Project Management Board, the investor of the Van Ninh - Cam Lo component project, said that in Le Thuy district there are still nearly 500m of ground problems, these points affect the progress of the project.

“From September, the Central region begins the rainy season. This leads to many difficulties in construction, especially the soil embankment part. We hope to have clean ground to carry out land filling this August" - this representative said.

Implement enforcement

Mr. Dang Dai Tinh - Chairman of Le Thuy District People's Committee - said that there are still about 20 households with nearly 500 square meters of land that have not been cleared. The district is focusing its total efforts on implementing specific plans.

“For some households that are paying and receiving money, we are waiting for the Government's money to be allocated. As soon as it is available, we will make payments to households. In the case of these households, they occupy about 90 square meters of space" - Mr. Tinh said.

Ground problems have prevented some sections of the North-South expressway through Quang Binh province from being constructed. Photo: Cong Sang
Ground problems have prevented some sections of the North-South expressway through Quang Binh province from being constructed. Photo: Cong Sang

Le Thuy District People's Committee will continue propaganda and advocacy work both centrally and individually for households to receive money. For households that have campaigned three times and do not agree, after fully implementing the plans and policies, the district is planning to enforce it. The number of households in this case has 249 square meters of space.

Recently, the district decided to enforce 3 cases, but then people agreed to receive the remaining money. So for the remaining households, the district continues to make enforcement plans to ensure the fastest handover progress.

Local authorities will carry out enforcement against households who do not agree to compensate according to regulations. Photo: Cong Sang
Local authorities will carry out enforcement against households who do not agree to the compensation policy according to regulations. Photo: Cong Sang

Site clearance work in Le Thuy district is more difficult because the area is the longest in the province and the project passes through the most densely populated terrain with nearly 1,000 households. Along with that, the land history left behind is complicated, with land transferred from agricultural and forestry farms, encroached land, disputes, no origin at the time of land use... so it takes a lot of time to handle. Along with that, the district also has solar power problems and nearly 700 graves.

"We will try our best to focus on carrying out the work so that we can hand over the site to the project as soon as possible" - Mr. Tinh said.

Le Thuy district still has nearly 500m of land that has not been cleared. Photo: Cong Sang
Le Thuy district still has nearly 500m of land that has not been cleared. Photo: Cong Sang

Vice Chairman of Quang Binh Provincial People's Committee Doan Ngoc Lam said that basically, affected people in the project area are very positive and unanimous in creating conditions for site clearance and handover of implementation sites. However, some households are reluctant and do not agree, affecting the progress of handing over the site to the investor.

Mr. Lam requested localities to issue enforcement decisions and develop construction protection plans for cases that do not agree with the compensation and site clearance policy according to the provisions of law.

CÔNG SÁNG
TIN LIÊN QUAN

Đường cao tốc sẽ về đến Đất Mũi, Cà Mau

NHẬT HỒ |

Cục Đường bộ đã trình bổ sung quy hoạch mới tuyến cao tốc Cà Mau - Đất Mũi, chiều dài khoảng 90 km, quy mô 4 làn xe, đầu tư sau 2030.

Loay hoay giải phóng mặt bằng, cao tốc Biên Hòa - Vũng Tàu lo “lỡ hẹn”

MINH CHÂU - TRÍ ĐỘ |

Trong khi dự án thành phần 3 cao tốc Biên Hòa - Vũng Tàu đoạn qua tỉnh Bà Rịa - Vũng Tàu đang thi công nhanh chóng thì dự án thành phần 1 và 2 đoạn qua tỉnh Đồng Nai vẫn đang loay hoay giải phóng mặt bằng (GPMB).

Dự án cao tốc Bắc - Nam qua Quảng Bình còn vướng mặt bằng

CÔNG SÁNG |

Công tác giải phóng mặt bằng Dự án xây dựng công trình đường bộ cao tốc Bắc - Nam phía Đông đoạn qua địa phận tỉnh Quảng Bình đến này vẫn còn hơn 500m.

Thăng hàm 2 phó giám đốc công an tỉnh, điều động 3 sĩ quan

Quang Việt |

Trong tuần qua, ngoài 2 phó giám đốc công an tỉnh được thăng hàm, ngành công an còn ghi nhận có 3 thượng tá được điều động, bổ nhiệm.

Chủ tịch Tổng LĐLĐVN thăm, tặng quà người dân bị thiên tai tại Hà Giang

Nguyễn Tùng |

Ngày 14.9, ông Nguyễn Đình Khang, Ủy viên Trung ương Đảng, Chủ tịch Tổng Liên đoàn Lao động Việt Nam (Tổng LĐLĐVN) cùng đoàn công tác tới thăm, tặng quà đoàn viên, công nhân viên chức lao động và người dân bị thiệt hại do lũ lụt tại Hà Giang.

Học trò vùng cao Quảng Nam khát khao cái chữ

Hoàng Bin |

Ở vùng cao Quảng Nam, nơi cái ăn, cái mặc còn thiếu thốn, mỗi ngày đến lớp với học sinh dân tộc thiểu số là cả hành trình vượt khó để chinh phục con chữ.

57 người dân Làng Nủ an toàn, còn 33 nạn nhân mất tích

Đinh Đại |

Lào Cai - Đến 16h chiều 14.9, lực lượng chức năng ghi nhận 57 người an toàn; còn 33 nạn nhân mất tích trong vụ lũ quét tàn khốc ở Làng Nủ.

Người dân TPHCM thích thú khi tận mắt thấy hàng trăm siêu xe

Anh Tú - Thanh Vũ |

TPHCM - Ngày 14.9, Hành trình Gumball 3000 đã diễn ra ở đường Lê Lợi, Quận 1 thu hút hàng ngàn người đến chiêm ngưỡng 120 siêu xe từ nhiều nước trên thế giới.

The highway will return to Dat Mui, Ca Mau

NHẬT HỒ |

The Department of Roads has submitted additional planning for the Ca Mau - Dat Mui expressway , about 90 km long, 4 lanes, for investment after 2030.

Struggling to clear the land, Bien Hoa - Vung Tau Expressway worries about "missing the appointment"

MINH CHÂU - TRÍ ĐỘ |

While component project 3 of the Bien Hoa - Vung Tau expressway passing through Ba Ria - Vung Tau province is being rapidly constructed, component projects 1 and 2 passing through Dong Nai province are still struggling with site clearance (GPMB). ).

The North-South Expressway project through Quang Binh still has land problems

CÔNG SÁNG |

Site clearance work for the North-South Expressway Construction Project in the East, section passing through Quang Binh province , still has more than 500m left.