The road is completed after 2 years of waiting
Cai Chuoi Street, Thanh Duc Ward, completed on December 3, helps people travel conveniently, reduces the situation of agricultural products being forced to price, improves income and life.
Mr. Pham Van Bay in Thanh Duc Ward said that when Lao Dong Newspaper reported that the slow construction affected the economy, the construction unit was directed to speed up the progress. "People are more excited because now there is more convenience in traveling, and agricultural products are easier and more efficient to do business with than before," said Mr. Bay.
Mr. Bay added that the completion of the road helps transport agricultural products from the garden to the market more quickly, reduces transportation costs, and people feel secure in producing and doing business more effectively.

Accelerating progress also helps stabilize income, reduce damage to people growing agricultural products, and at the same time create favorable conditions for trade of goods in the region, improve the lives and joy of residents of Thanh Duc ward.
Mr. Tran Minh Quang, also in Thanh Duc ward, who owns about 3,000m of coconut trees, said that the unfinished road makes trading difficult, goods are transported slowly, and prices have dropped sharply.
"For example, I sell coconuts for 100,000 VND/tester, while other places sell for 120,000 VND/tester. Now the new road, wide and spacious, is at the same price as another place, much more convenient, Mr. Quang shared.
Mr. Quang shared that since the road was opened, the harvesting and transportation of coconuts are no longer delayed, goods arrive at the market on time, ensuring stable prices, increasing income for people.
Cai Chuoi route opens on December 3
Speaking with Lao Dong, Mr. Nguyen Thanh Vinh - Acting Head of Project Management Department 1, Vinh Long Agricultural Project Management Board said that the Thanh Duc - Long My Irrigation System project was approved by the Provincial People's Committee in Decision No. 1911/QD-UBND dated September 15, 2022, implementing the period 2022-2026.
Cai Chuoi route in Thanh Duc ward is 3,038m long, 5m wide, 3.5m wide, handed over the construction site in October 2023.
During the implementation process, site clearance encountered many difficulties, and the resettlement site arrangement will not be completed until February 2025.
"Receiving voters' opinions and later Lao Dong Newspaper recorded the inconvenience of traveling and difficulties in economic development of the investor and directed the construction unit to speed up the progress," Mr. Vinh added.

Mr. Pham Hoang Dao, representative of the construction unit, said that after receiving the site, the unit has worked overtime continuously, regardless of sunny days, rainy days and Saturdays and Sundays, to ensure progress.
This helps the project progress quickly, while facilitating people's travel and transportation of agricultural products, promptly avoiding damage to selling prices and income.
"The project was completed on December 3, the road is smooth, making it convenient for people to travel and transport agricultural products, while improving the lives and stabilizing income for residents of Thanh Duc ward," Mr. Dao added.