Da Nang removes obstacles to site clearance for more than 400 projects in 2026

An Thượng |

The entire Da Nang City has more than 400 projects to be implemented, with nearly 47,000 dossiers not yet handed over.

In 2026, Da Nang city faces great pressure in site clearance work. This continues to be a "bottleneck" directly affecting the progress of key projects. At the City Party Committee conference just held on March 27, the Standing Committee identified three key tasks: removing investment bottlenecks; creating new growth momentum; tightening discipline, improving public service efficiency. This is the basis for Da Nang to move towards sustainable and comprehensive development.

Statistics show that the number of backlog dossiers includes more than 10,000 cases of residential land, nearly 24,000 dossiers of agricultural land and nearly 3,000 other land dossiers. In addition, there are more than 18,000 graves that have not been relocated. The volume of work is large, spreading across many areas, putting significant pressure on the grassroots government system.

The Ngu Hanh Son area is the place with the most projects, with 21 projects needing site clearance. Many key projects such as FPT Technology Urban Area, Hoa Quy Urban Area, and expanded Ba Tung Resettlement Area are identified as having to be thoroughly handled to create momentum for development.

The city plans to allocate more than 5,000 billion VND for this work. The City People's Committee clearly assigns responsibilities to each level and sector. Communes and wards must develop detailed plans weekly and monthly; assign officials to monitor each dossier. Specialized agencies are assigned to take the lead in reviewing and summarizing difficulties and proposing timely handling solutions.

Investors are required to closely coordinate with compensation agencies, strengthen citizen reception, and mobilize land handover. The Fatherland Front and mass organizations participate in monitoring and reflecting people's opinions, contributing to creating consensus.

Reality shows that after implementing the two-level government model, the workload concentrated at the commune level has increased sharply. However, some localities have not fully implemented their responsibilities, leading to bottlenecks in handling dossiers. Delays at the grassroots level have led to stagnation in many large projects.

Leaders of the city's finance sector emphasized the requirement to strengthen direction and guidance for commune-level officials. The goal is to coordinate synchronously between levels, accelerate the progress of processing procedures, and soon hand over land for projects.

An Thượng
RELATED NEWS

Da Nang completes shared infrastructure to launch Lien Chieu container terminal

|

Da Nang - Da Nang announced the completion of shared infrastructure and launched the Lien Chieu container port project with a scale of over 45.2 trillion VND.

Da Nang establishes grassroots trade union of An Duc Phat Windows Joint Stock Company

|

Da Nang - Thang An Commune Trade Union, Da Nang City established the grassroots Trade Union of An Duc Phat Windows Joint Stock Company.

Grassroots trade union of Ngu Hanh Son ward, Da Nang organizes conference for civil servants and workers

|

Da Nang - Grassroots trade unions of Ngu Hanh Son ward organize conferences for civil servants and workers in 2026.

Large fire at a confectionery warehouse in Hanoi, 12 fire trucks mobilized

|

Hanoi - In the early morning of March 31, a confectionery warehouse in Huong Son commune caught fire fiercely.

Inspectors point out many businesses exploiting exceeding capacity to serve expressways in Khanh Hoa

|

Khanh Hoa - Many mineral exploitation enterprises exceeding capacity to serve the construction of expressway projects have been pointed out by the inspection agency.

Quang Tri Inspectorate intervenes, identifying households building houses encroaching on neighbors' land

|

Quang Tri - After the reflection of Lao Dong Newspaper, the Provincial Inspectorate determined that the family of Ms. M.T. T. H (Dong Ha ward) built a house encroaching on adjacent land.

US bombers attacking Iran banned in Spain

|

Spain banned US bombers from operating in its airspace and bases after criticizing the operation in Iran as illegal.

Football prediction Vietnam vs Malaysia

|

The Vietnamese team aims for important goals in the rematch against Malaysia in the 2027 Asian Cup qualifiers.

Da Nang completes shared infrastructure to launch Lien Chieu container terminal

Nguyễn Linh |

Da Nang - Da Nang announced the completion of shared infrastructure and launched the Lien Chieu container port project with a scale of over 45.2 trillion VND.

Da Nang establishes grassroots trade union of An Duc Phat Windows Joint Stock Company

Tường Minh |

Da Nang - Thang An Commune Trade Union, Da Nang City established the grassroots Trade Union of An Duc Phat Windows Joint Stock Company.

Grassroots trade union of Ngu Hanh Son ward, Da Nang organizes conference for civil servants and workers

Tường Minh |

Da Nang - Grassroots trade unions of Ngu Hanh Son ward organize conferences for civil servants and workers in 2026.