The Quang Binh Provincial Health Education and Communication Center project was approved on October 30, 2015 by the People's Committee of Quang Binh province. The project is built in Dong Phu ward, Dong Hoi city.
The scale and construction capacity of the 5-storey main building block, providing enough working and professional space for the center's officials and employees and supporting items. Construction started in 2017 but has not yet been completed and put into use.
The Department of Health is the investor, Hung Dung Construction and Trading Company Limited advises on project planning. Quang Binh province's civil and industrial construction investment project management board is the project management unit.
Total investment is 49.3 billion VND from the central budget and provincial budget. The implementation period is from 2016-2020, then extended until 2022. And from 2022 until now, the above project is still "under construction", unable to go into operation.
As noted by Lao Dong Newspaper on July 28, the project has completed the rough construction, parts such as floor tiles, exterior tiles, and glass are basically complete. Weeds grow luxuriantly inside and outside the project area. There are no workers involved in construction.
According to the latest report on the implementation status of the above project, the Management Board of Civil and Industrial Construction Investment Projects of Quang Binh province clearly stated that in the bidding package for the construction and installation of the main building block and sub-items, Supported by Hanoi Real Estate Investment and Trading Joint Stock Company (contractor), construction started on June 1, 2017, completed on December 31, 2022. The project has basically completed the rough and finishing parts such as floor tiles and Inax tiles on the outside of the house.
From the date of July 1, 2022, signing the contract addendum to adjust the time for implementing the bidding package until December 31, 2022, the contractor implemented the work items of the bidding package very slowly, at some times not at all. construction on site; There are no drastic solutions, no concentration of human resources, machinery and equipment to speed up the construction progress to complete the package as planned.
By December 31, 2022, the implementation volume of the new bidding package will reach about 79% of the contract value; The investor, project management unit, and supervision consultant have worked, checked and confirmed the volume of the bidding package's site, and have made a record of the delay in construction progress of the main building block and other items. auxiliary project under the Health Education and Communication Center Project in Quang Binh province, because the contractor did not complete the schedule according to the signed contract.
On July 29, the Management Board of Civil and Industrial Construction Investment Projects of Quang Binh province informed that the construction progress of the construction package was prolonged, so the price of materials and fuel fluctuated a lot. On the other hand, During the implementation process, it is necessary to adjust and supplement a number of work items to ensure quality and aesthetics, resulting in costs, so the reserve of the bidding package and the project has been used up.
The contractor carrying out the construction and installation package of the main house and auxiliary items was sluggish, did not have drastic solutions, did not focus on human resources, machinery and equipment, so it did not complete according to the contract schedule.
The completion of the adjusted design documents by the design consulting unit is still slow and does not follow the agreed contents between the investor and relevant units. The total disbursed value is more than 39.4 billion VND.
Some images recorded by Lao Dong on July 28: