Resort project worth more than 400 billion VND on golden land built but still not completed

NGUYỄN LUÂN |

Quang Tri - Expected to become a high-class coastal resort with a 5-star hotel, but the Saigon - Bao Ninh Eco-tourism Area project has not been completed yet.

Sleeping" by the sea

The Saigon - Bao Ninh Eco-tourism Area project (Dong Hoi ward, Quang Tri province) includes a 19-story hotel with 229 5-star standard rooms, 64 resort villas, a restaurant area, a beach club, a swimming pool, and many synchronous service and technical infrastructure items.

However, after a long period of slow implementation, the project was only started in March 2019. According to the plan, the project must be completed and put into operation from September 2020.

Khối khách sạn 19 tầng đã cất nóc nhưng chỉ hoàn thiện phần thô, nhiều năm qua không có dấu hiệu tiếp tục thi công. Ảnh: Nguyễn Luân
The 19-story hotel block has been topped up but only completed the rough part, and for many years there has been no sign of continuing construction. Photo: Nguyen Luan

According to reporters of Lao Dong Newspaper, after building the rough structure of the 19-story hotel, some bungalows, restaurants, swimming pools and technical infrastructure, the entire construction site is almost "frozen".

The hotel block has been roofed since the end of 2020, but it is still just a gray concrete frame. Many walls have not been plastered, steel reinforcement protrudes from the construction, and many items are still unfinished.

Cánh cổng trở nên hoen rỉ, xuống cấp sau nhiều năm dự án dừng thi công. Ảnh: Nguyễn Luân
The gate becomes rusty and degraded after many years of project suspension. Photo: Nguyen Luan

Besides, the row of stilt houses was built and then abandoned for a long time, causing many items to degrade. The project grounds are covered with weeds, many green trees planted from the early days of implementation are now withered due to lack of care. Currently, there are no records of workers or machinery constructing the project.

According to the dossier, the total realized investment value to date is about 184 billion VND, equivalent to 43.39% of the total investment after adjustment. Despite spending a large amount of money, the project has been suspended from construction from 2020 to now, creating a messy scene right in the coastal area considered one of the locations with potential for tourism development in the locality.

Debt of more than 39.5 billion VND in land rent

Through thematic inspection of prolonged delayed projects, the Quang Tri Provincial Inspectorate pointed out many reasons why the project fell into a state of stagnation.

According to a recent inspection conclusion, the investor has not fully ensured financial resources as committed, has not completed the project on schedule even though it has been extended, and is also slow to carry out investment adjustment procedures when the investment registration certificate expires.

Một căn bungalow tại dự án Khu du lịch sinh thái Sài Gòn - Bảo Ninh xây dựng dang dở rồi bỏ hoang nhiều năm, cỏ dại bao phủ. Ảnh: Nguyễn Luân
A bungalow in the Saigon - Bao Ninh Eco-tourism Area project was unfinished and abandoned for many years, covered with weeds. Photo: Nguyen Luan

One of the major obstacles arising in the implementation process is the transfer of the investor from Saigon - Quang Binh Tourism Joint Stock Company to Bao Ninh Tourism Co., Ltd. not being approved by competent authorities. The process of processing investor adjustment dossiers and registering land changes is prolonged, leading to additional procedures related to investment and land.

Nhiều hạng mục xuống cấp, hư hỏng sau thời gian dài không được hoàn thiện và đưa vào sử dụng. Ảnh: Nguyễn Luân
Many items are degraded and damaged after a long time of not being completed and put into use. Photo: Nguyen Luan

Notably, the project has been suspended since 2020, but the investor has not yet fulfilled its financial obligations to the State. As of November 10, 2025, the total amount of land rent and late payment of the project has reached more than 39.543 billion VND.

The Inspectorate also identified the responsibility of some state management agencies for slow handling of existing problems of the project. In which, the Department of Finance has not promptly urged investors to fulfill financial obligations and guided the completion of procedures for adjusting investors; the Department of Agriculture and Environment is slow to advise on handling land procedures as well as land recovery when meeting the conditions according to regulations.

Hệ thống cây xanh trong khuôn viên dự án chết khô, gây lãng phí nguồn lực và mất mỹ quan. Ảnh: Nguyễn Luân
The green system in the project grounds is withered, causing waste and unsightliness. Photo: Nguyen Luan

According to the Provincial Inspectorate, the project has sufficient grounds not to continue adjusting the investment registration certificate, and is also eligible for consideration to terminate operations and recover land according to the provisions of law.

However, considering the fact that the project has completed more than 43% of the total investment, the Inspectorate proposed that the Provincial People's Committee assign departments and branches to review and agree on a plan with the investor to definitively remove obstacles related to investment and land after completing financial obligations. In case the investor does not meet the conditions according to regulations, it will advise to terminate the project and recover land to avoid further waste of resources.

The Saigon - Bao Ninh Eco-tourism Area project was approved for investment by the People's Committee of Quang Binh province (old) in 2009 in the Bao Ninh area, now belonging to Dong Hoi ward, Quang Tri province.

The project has an area of 42,483m2, with an initial total investment of 120 billion VND, after adjustment it increased to 424.831 billion VND. According to the plan, the project includes a 19-story hotel with 229 rooms meeting international 5-star standards, 64 resort villas, along with a system of restaurants, beach clubs, pool bars, swimming pools, technical infrastructure and auxiliary works.

NGUYỄN LUÂN
RELATED NEWS

Proposal to build an eco-tourism project worth nearly 4,500 billion VND in Son La

|

Son La - The eco-resort project with a total investment of nearly 4,500 billion VND may be implemented in To Mua commune.

Hue disciplines many officials for violations at the Provincial Party Committee Guest House Project

|

The Hue City Party Committee's Inspection Committee disciplined many collectives and individuals for violations in the implementation of the Thua Thien Hue Provincial Party Committee Guesthouse Project.

Residential area project has been finalized, but many items are still unfinished

|

Quang Tri - People in Duc Dien residential area are struggling because the infrastructure is not synchronized, and for many years they have had to temporarily draw electricity to serve daily life.

Resort project worth more than 400 billion VND on golden land built but still not completed

|

Quang Tri - Expected to become a high-class coastal resort with a 5-star hotel, but the Saigon - Bao Ninh Eco-tourism Area project has not been completed yet.

8 PM News: Case of many 10s in Tuyen Quang, Prime Minister will directly work with local authorities

|

8 PM News on July 14th: Prime Minister will work with Tuyen Quang on many unusual 10 points; Localities review and arrange commune-level administrative units;...

More positive signals for the project to eliminate traffic black spots in the East of Ho Chi Minh City

|

Ho Chi Minh City - People living along Nguyen Duy Trinh street are happy when the road expansion project has more positive changes, hoping to soon eliminate traffic black spots in the East.