200MW hydropower plant project in Dong Nai entangled with site clearance

HÀ ANH CHIẾN |

Dong Nai - On March 12, the Provincial People's Committee worked with relevant units on the progress of site clearance for the Tri An Hydropower Plant expansion project.

According to the report of Power Project Management Board 3 (Vietnam Electricity Group), the project implementation process is facing some difficulties and obstacles related to site clearance and materials.

Regarding compensation and site clearance, the main construction area currently does not have land to construct the pressure pipeline section to the factory; the Hieu Liem bridge item has not yet been handed over the construction site at the head of abutment B and the bridge access road...

Vị trí xây dựng cầu Hiếu Liêm để vận chuyển vật liệu, thiết bị thi công Dự án Nhà máy thủy điện Trị An mở rộng. Ảnh tư liệu: HAC
Location of construction of Hieu Liem bridge for transporting materials and equipment for the Tri An Hydropower Plant expansion project. Photo source: HAC

Power Project Management Board 3 proposed to hand over the entire clean site in March 2026 to serve the construction of the main project and the Hieu Liem bridge item.

Concluding the working session, Vice Chairman of Dong Nai Provincial People's Committee Ho Van Ha assigned the Department of Agriculture and Environment to support localities in site clearance, support investors in connecting material sources to serve project construction; at the same time, proposed to accelerate the construction of resettlement area infrastructure, in order to soon hand over land to people to stabilize their lives; support temporary residence for affected households while waiting for resettlement.

The Tri An Hydropower Plant expansion project in Tri An commune is a national key project in the energy sector, which was started in August 2025. The project has a capacity of 200MW, and is expected to be completed and put into operation in 2027.

HÀ ANH CHIẾN
RELATED NEWS

Tri An Hydropower Plant Project to Expand Nearly VND4,000 Billion is stuck in site clearance

|

Dong Nai - The Tri An Hydropower Plant expansion project is invested by EVN, with a total investment of nearly 4,000 billion VND, expected to be completed by the end of 2027.

Starting construction of Tri An hydropower plant to expand capacity to 200MW, total investment of VND 3,900 billion

|

Dong Nai - Tri An Hydropower Plant has an expanded capacity of 200MW, with an average annual electricity output of about 200 million kWh.

Ready to start construction of the Tri An Hydropower Project to expand nearly 4,000 billion VND on August 19

|

Dong Nai - It is expected that on August 19, Vietnam Electricity Group (EVN) will start the Tri An hydropower project to expand, with a total investment of nearly 4,000 billion VND.

Building Hieu Liem Bridge in Tri An Hydropower Plant Expansion Project

|

Dong Nai - On December 29, Vietnam Electricity Group (EVN) held a ceremony to start construction of Hieu Liem Bridge under the Tri An Hydropower Plant Expansion Project.

Russia tightened the siege around Konstantinovka in the Donetsk region

|

Russia's capture of Novodmitrovka is exerting strong pressure by surrounding all Kiev forces stationed in Konstantinovka.

Nottingham Forest sets one foot in Europa League final

|

In the early morning of May 1st (Vietnam time), Nottingham Forest defeated Aston Villa 1-0 in the first leg of the Europa League semi-finals of the 2025-2026 season.

U17 Vietnam finalizes the list for the 2026 AFC U17 Championship finals

|

U17 Vietnam has finalized the list of 23 players before heading to Saudi Arabia to participate in the 2026 AFC U17 Championship finals.

U17 Vietnam and lessons at the Asian tournament

|

Coach Roland understands clearly that if they do not win 4 points or more in the group stage of the 2026 AFC U17 Championship, U17 Vietnam will again fall into the "rut" of 1 year ago.

Tri An Hydropower Plant Project to Expand Nearly VND4,000 Billion is stuck in site clearance

HÀ ANH CHIẾN |

Dong Nai - The Tri An Hydropower Plant expansion project is invested by EVN, with a total investment of nearly 4,000 billion VND, expected to be completed by the end of 2027.

Starting construction of Tri An hydropower plant to expand capacity to 200MW, total investment of VND 3,900 billion

Hà Anh Chiến |

Dong Nai - Tri An Hydropower Plant has an expanded capacity of 200MW, with an average annual electricity output of about 200 million kWh.

Ready to start construction of the Tri An Hydropower Project to expand nearly 4,000 billion VND on August 19

HÀ ANH CHIẾN |

Dong Nai - It is expected that on August 19, Vietnam Electricity Group (EVN) will start the Tri An hydropower project to expand, with a total investment of nearly 4,000 billion VND.

Building Hieu Liem Bridge in Tri An Hydropower Plant Expansion Project

HÀ ANH CHIẾN |

Dong Nai - On December 29, Vietnam Electricity Group (EVN) held a ceremony to start construction of Hieu Liem Bridge under the Tri An Hydropower Plant Expansion Project.