Dong Nai - Tri An Hydropower Plant has an expanded capacity of 200MW, with an average annual electricity output of about 200 million kWh.

On the morning of August 19, in Tri An commune, Dong Nai province, a groundbreaking ceremony for the expansion of Tri An hydropower plant took place.

Cac dai bieu du le khoi cong nha may thuy dien Tri An mo rong. Anh: HAC
Delegates attending the groundbreaking ceremony for the expanded Tri An hydropower plant. Photo: HAC

The ceremony was attended by Senior Lieutenant General Nguyen Truong Thang, member of the Party Central Committee, Deputy Minister of National Defense; Ms. Phan Thi Thang, Deputy Minister of Industry and Trade.

Dong Nai province attended the ceremony with Mr. Vo Tan Duc - Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of Dong Nai province.

Ong Vo Tan Duc - Pho Bi thu Tinh uy, Chu tich UBND tinh Dong Nai. Anh: HAC
Mr. Vo Tan Duc - Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of Dong Nai province spoke at the ceremony. Photo: HAC

The Tri An Hydropower Plant expansion project is invested by Vietnam Electricity Group. The consortium consists of 6 contractors, headed by Lung Lo Construction Corporation.

The project has a total capital of about VND3,900 billion, expected to be completed by the end of 2027.

This is a national key project in the energy sector.

The expanded Tri An Hydropower Plant is built in Tri An commune, Dong Nai province.

The project consists of 2 generators, with a capacity of 200MW, an average annual electricity output of about 200 million kWh, connected to the 220kV power distribution station of the existing Tri An Hydropower Plant.

Thuy dien Tri An hien huu o tinh Dong Nai. Anh tu lieu: HAC
Tri An Hydropower Plant is present in Dong Nai province. Documentary photo: HAC

After completion, the project will not only supplement an important power source to the national power system to ensure power supply for the socio-economic development of the region in general, the double-digit growth target of Dong Nai province in particular, but also demonstrate the determination to implement the green and sustainable energy development strategy, in line with Vietnam's commitment at COP 26 on the goal of net zero emissions by 2050.

Tap doan Dien luc Viet Nam (EVN) to chuc le trien khai thi cong xay dung cau Hieu Liem thuoc du an Nha may thuy dien Tri An mo rong vao ngay 29.12.2024. Anh: HAC
Vietnam Electricity Group (EVN) held a ceremony to launch the construction of Hieu Liem bridge under the Tri An Hydropower Plant expansion project on December 29, 2024. Photo: HAC

Previously, on December 29, 2024, Vietnam Electricity Group (EVN) held a ceremony to launch the construction of Hieu Liem bridge under the Tri An Hydropower Plant expansion project.

Hieu Liem Bridge is an important item of the project, approved as a level II project with a length of 249.5 m and a width of 9 m. The bridge was built to serve the transportation of materials and equipment during the project construction process. After the project was completed, Hieu Liem Bridge was left to serve the travel needs of people in the area, helping to connect traffic and contributing to the socio-economic development of the area.

Hà Anh Chiến
RELATED NEWS

Ready to start construction of the Tri An Hydropower Project to expand nearly 4,000 billion VND on August 19

|

Dong Nai - It is expected that on August 19, Vietnam Electricity Group (EVN) will start the Tri An hydropower project to expand, with a total investment of nearly 4,000 billion VND.

Signing a contract worth over VND1,450 billion for the construction package of the Tri An Hydropower Plant expansion

|

On June 3, 2025, a contract signing ceremony for the construction package of the Tri An Hydropower Plant expansion project took place in Hanoi.

Building Hieu Liem Bridge in Tri An Hydropower Plant Expansion Project

|

Dong Nai - On December 29, Vietnam Electricity Group (EVN) held a ceremony to start construction of Hieu Liem Bridge under the Tri An Hydropower Plant Expansion Project.

Former Director of Ho Chi Minh City Academy of Officials becomes Secretary of Saigon Ward

|

HCMC - Associate Professor, Dr. Nguyen Tan Phat will be Party Committee Secretary and Chairman of the People's Council of Saigon Ward for the 2025 - 2030 term.

Waiting for the performance of the Vietnam women's team against Thailand

|

The Vietnamese women's team will enter the final match of the 2025 Southeast Asian Women's Football Championship with the goal of winning against Thailand.

US resolutely refuses military aid to Ukraine

|

Despite US President Donald Trump's announcement of a halt in military aid, Ukraine is still trying to convince Washington to make other security commitments.

Dien Bien spends nearly 8 billion VND to repair a lake over 10 years old

|

Dien Bien spent nearly 8 billion VND to implement the project to repair and repair the Nam Ngam - Pu Nhi reservoir, after more than 10 years of operation.

Delegates have high expectations for the Party Congress of the Vietnam General Confederation of Labor for the 2025 - 2030 term

|

This morning, August 19, at the headquarters of the Vietnam General Confederation of Labor, a special session was held by the 1st Congress of the Vietnam General Confederation of Labor Party Committee, term 2025 - 2030.

Ready to start construction of the Tri An Hydropower Project to expand nearly 4,000 billion VND on August 19

HÀ ANH CHIẾN |

Dong Nai - It is expected that on August 19, Vietnam Electricity Group (EVN) will start the Tri An hydropower project to expand, with a total investment of nearly 4,000 billion VND.

Signing a contract worth over VND1,450 billion for the construction package of the Tri An Hydropower Plant expansion

Thạch Lam |

On June 3, 2025, a contract signing ceremony for the construction package of the Tri An Hydropower Plant expansion project took place in Hanoi.

Building Hieu Liem Bridge in Tri An Hydropower Plant Expansion Project

HÀ ANH CHIẾN |

Dong Nai - On December 29, Vietnam Electricity Group (EVN) held a ceremony to start construction of Hieu Liem Bridge under the Tri An Hydropower Plant Expansion Project.