Large-scale social housing project in Thanh Hoa abandoned for more than a decade

QUÁCH DU |

Thanh Hoa - A social housing project with a scale of nearly 1,000 apartments in Thanh Hoa, after more than a decade of being approved for investment, is still just a vacant lot.

According to the investigation of Lao Dong Newspaper reporters, more than 10 years ago, in 2014, Thanh Hoa Provincial People's Committee had a document approving the investment in the AMC I social housing development project, in Quang Thanh ward, Thanh Hoa city (old), now Quang Phu ward, Thanh Hoa province.

Du an nha o xa hoi
The AMC I social housing project is still just a vacant lot after more than a decade of investment policy approval. Photo: Quach Du

The project is invested by AMC Toan Cau Development Joint Stock Company, and is implemented in a quite prime location, located at the intersection of National Highway 1A, Thanh Hoa City bypass and Vo Nguyen Giap Avenue.

According to the plan, the project includes 3 15-story apartment buildings, along with a system of green trees, traffic roads and auxiliary works. The total land use area is about 22,300m2, of which social housing construction land is about 11,462m2, with about 900 apartments. The green land area is about 7,441m2, the rest is traffic land of about 3,397m2. The total investment of the project is more than 500 billion VND.

Khu vuc cong du an Khu nha o xa hoi
AMC I social housing project gate area. Photo: Quach Du

After many years of slow implementation, in August 2020, Thanh Hoa Provincial People's Committee continued to issue a decision to extend the project implementation time and allocate land to the investor. According to this decision, the implementation time is 30 months, calculated from August 6, 2020 to February 6, 2023.

Next, in early 2021, AMC Toan Cau Development Joint Stock Company held the groundbreaking ceremony for the AMC I social housing area, belonging to the AMC - El Dorado Urban Area Project, in Quang Thanh ward, Thanh Hoa city (old). The investor committed that phase 1 will build a social housing area and a green park - sports; phase 2, expected in the second quarter of 2021, will deploy all remaining items.

However, records of Lao Dong Newspaper reporters as of the end of December 2025 show that the investor has only carried out corrugated iron enclosure around the project area. Inside the project is still a vacant lot, overgrown with weeds, without any construction activities.

Ben trong du an, chu dau tu moi thuc hien duoc it hang muc nho, con lai van la bai dat hoang. Anh: Quach Du
Inside the project, the investor has only completed a few small items, the rest is still vacant land. Photo: Quach Du

Many people living near the project area said that at the time of commencement, the project was once widely implemented, but after only a short time it fell into a state of "immobilization". "The project was approved in principle, land was allocated for many years but no construction was seen. This not only disappoints people who need to buy social housing but also causes waste of land resources," a resident angrily shared.

According to representatives of the Thanh Hoa Provincial Department of Construction, the project delay is the responsibility of the investor, AMC Toan Cau Development Joint Stock Company, because previously, the Provincial People's Committee had agreed to extend the project implementation time to March 2023, but so far the project has not been implemented according to the committed schedule.

Du an nam
The project is in a prime location, located at the intersection of National Highway 1A, Thanh Hoa City bypass and Vo Nguyen Giap Avenue. Photo: Quach Du

Regarding the reasons for the delay, a representative of Thanh Hoa Department of Construction said that the investor has requested to adjust the investment policy, including proposing to add basement area, reduce construction area and increase the height of the project. In the process of implementation, the investor also committed the act of constructing illegal items, and was administratively fined more than 100 million VND and forced to implement remedial measures according to regulations.

It is known that, related to slow-progress projects, recently at the 37th session of the 18th Provincial People's Council (term 2021 - 2026) held on December 8, Mr. Hoang Anh Tuan - Head of the Economic - Budget Committee of the Thanh Hoa Provincial People's Council - said that in 2025, the province comprehensively reviewed 308 direct investment projects and projects using land that are slow to implement and have been prolonged for many years.

The review results show that 280 out of a total of 308 projects are being processed according to plan; the remaining 28 projects have been completed, including projects that have been terminated, are being considered for termination or have removed obstacles to restart.

QUÁCH DU
RELATED NEWS

Ca Mau proposes to revoke the project 20 years later

|

The old Bac Lieu Administrative Central Area Project, now Ca Mau Province, started construction in 1998, and has not been completed after 27 years. 6/34 packages were suspended due to land clearance problems, with an advance payment of VND1.6 billion. The Provincial Inspectorate proposed to collect the debt and terminate the project.

General review of slow-progressing projects in Nghe An

|

Nghe An - Units review and fully update the status of the project behind schedule to advise the Provincial People's Committee to develop an inspection plan for 2026.

7 years of living next to a slow-progressing project in Tam Trinh

|

Hanoi - For the past 7 years, people living next to the Tam Trinh road expansion project have had to endure dust and chaos due to the project's long schedule.

Pension payment schedule for 1,2026 may change due to 4-day New Year holiday

|

The pension and social insurance allowance payment schedule in January 2026 may change after the new New Year holiday schedule.

People's Police Trade Union spreads patriotic emulation movement

|

In the period 2020-2025, the patriotic emulation movement in the People's Police Trade Union has made clear progress.

Fire at electrical and plumbing business house, 4 people in Dak Lak die

|

Dak Lak - A serious fire occurred in the dark at night in Hoa Phu commune, killing 4 people.

Special art program ignites patriotic emulation spirit

|

The special art program celebrating the 11th National Patriotic Emulation Congress left many emotions.

Announcing 10 typical cultural, sports and tourism events of 2025

|

After a period of voting, the Organizing Committee has a list of 10 typical cultural, sports and tourism events of 2025.

Ca Mau proposes to revoke the project 20 years later

NHẬT HỒ |

The old Bac Lieu Administrative Central Area Project, now Ca Mau Province, started construction in 1998, and has not been completed after 27 years. 6/34 packages were suspended due to land clearance problems, with an advance payment of VND1.6 billion. The Provincial Inspectorate proposed to collect the debt and terminate the project.

General review of slow-progressing projects in Nghe An

QUANG ĐẠI |

Nghe An - Units review and fully update the status of the project behind schedule to advise the Provincial People's Committee to develop an inspection plan for 2026.

7 years of living next to a slow-progressing project in Tam Trinh

Hữu Vũ |

Hanoi - For the past 7 years, people living next to the Tam Trinh road expansion project have had to endure dust and chaos due to the project's long schedule.