According to reporters' records on May 5, the 9-story hotel next to Hoan Kiem Lake is being demolished.
The entire facade of the project is surrounded by two large layers of tarpaulin extending from the roof to the foot of the project. This "armure" layer both isolates the construction site from crowded areas and limits dust and materials from spilling into the surrounding environment.
Inside, demolition activities began to be carried out from the top floors. On the roof of the building, excavators with hydraulic hammers continuously chiseled large concrete slabs. After being loosened, the materials were collected and then pushed downwards, forming large piles of waste in the construction site.




At the bottom, machinery continues to level and collect waste, and the water spraying system is maintained to reduce dust.
Accelerating the demolition progress of this project is one of the important steps to complete site clearance for the Hoan Kiem Lake East square and park project - a project with a scale of more than 2.1ha with a total investment of trillions of VND.


Details of phases of the Hoan Kiem Lake East square and park project:
Period 1:
- Compensation, support, and resettlement for home and land users within the land area of about 21,151m2 to implement the project to invest in building the TOD area east of Hoan Kiem Lake; Total number of users: 59 home and land users, including 17 organizations (7 units of the electricity industry and 10 other units) and 42 households.
- Planning, organizing, and arranging the space of the square: leveling ground, paving stone, green trees, lawns, parking bays,... (according to the approved design plan). In which, the building of the Department of Culture, the Institute of Literature will be retained, researching the relocation of the Lighthouse, temporarily keeping 2 architectural works of Northern Power Corporation to study specific handling plans in phase 2 (phase 2); Researching the plan to retain the Artdeco style architectural works of Hoan Kiem Power Company, considering the plan to open the 1st floor...
- Invest in technical infrastructure systems: water supply and drainage, lighting, provision of urban equipment (garbage bins, stone benches, WCs...); Wifi system, security cameras;
Renovation and renovation of some remaining buildings: the building of the Department of Culture, the building of the Institute of Literature...
- Moving underground and above-ground works (if any) and some other related items.
Period 2:
Implemented by separate projects according to the planning and architectural plan appraised and approved by competent authorities in accordance with regulations, with the orientation of the approved Plan as follows:
- Research planning and organization of underground space in the area east of Hoan Kiem Lake (about 3 basements), connecting the underground space of station C9 - urban railway line No. 2, phase 1 (2. 1) Nam Thang Long - Tran Hung Dao, having appropriate technical solutions for conservation works during the construction of basements; propose functions for using underground space to ensure land use efficiency, meeting the needs of the people (should research and propose multi-functional use: public, cultural, service, commercial, infrastructure...).