Progress of site clearance for the 2.14 ha project adjacent to Hoan Kiem Lake

SÓNG HỮU |

Hanoi - Many houses and agency headquarters have been cleared for the construction of the Hoan Kiem Lake East square - park project, with a scale of 2.14 ha.

Lao Dong's records in recent days at the land area where Hoan Kiem Lake East square - park will be built (Hoan Kiem ward, Hanoi), workers and machinery are being mobilized to demolish a series of houses and headquarters within the project site clearance area.

The headquarters of Hoan Kiem Power Company has basically completed the dismantling of items. Pho Thin Bo Ho restaurant at No. 61 Dinh Tien Hoang, a familiar culinary address, has also been dismantled.

s
s
s
s
Workers and machinery dismantling works within the scope of the Hoan Kiem Lake East square - park project (Hanoi). Photo: Song Huu

On Tran Nguyen Han street, the National Power Transmission Corporation located within the project scope has also announced the relocation of a new workplace.

A 10-story hotel on Ly Thai To street and some other projects will also be demolished by the construction unit in the near future.

The demolition of the project is expected to be completed in the first quarter of 2026.

According to Hoan Kiem Ward People's Committee, there are 17 organizations and 43 households in the land acquisition and site clearance area to implement the Hoan Kiem Lake East square - park project. Up to now, organizations, households, and individuals have basically agreed with the compensation, support and resettlement plan.

s
s
A 10-story hotel on Ly Thai To street will be demolished to implement the project. Photo: Song Huu
s
Headquarters of the National Power Transmission Corporation (Tran Nguyen Han street) in the area of site clearance for project implementation. This Corporation has announced the relocation to a new address. Photo: Song Huu

The project to invest in building the square - park east of Hoan Kiem Lake has a scale of about 2.14 ha, bordering Hoan Kiem Lake and Dinh Tien Hoang street to the west; existing residential area to the north; Ly Thai To street to the east; Tran Nguyen Han street to the south.

The project to build the square - park east of Hoan Kiem Lake is divided into 2 phases.

Phase 1 includes compensation, support, and resettlement for home and land users. Functional agencies will plan, organize, and arrange the square space including leveling, paving stone, green trees, lawns, parking lots... according to the approved design plan.

Functional agencies will also renovate and renovate some buildings to retain and relocate underground and above-ground works and some other related items.

Phối cảnh dự án quảng trường - công viên phía Đông hồ Hoàn Kiếm. Ảnh: UBND TP Hà Nội
Perspective of the square - park project east of Hoan Kiem Lake. Photo: Hanoi People's Committee

Phase 2 will be implemented by a separate project according to the planning and architectural plan appraised and approved by competent authorities in accordance with regulations, with the orientation of the approved plan.

In phase 2, functional agencies will study the planning and organization of underground space in the area east of Hoan Kiem Lake (about 3 basements), connecting the underground space of station C9 - urban railway line No. 2 Nam Thang Long - Tran Hung Dao.

At the same time, there should be appropriate technical solutions for conservation works during the construction of the basement.

For phase 2, Hoan Kiem ward will study carefully with orientations according to the approved plan and opinions of the Hanoi People's Committee.

SÓNG HỮU
RELATED NEWS

Hanoi urgently clears ground to open a 120-180m wide road

|

Hanoi - The progress of land acquisition and site clearance to build a nearly 7km long road with a cross-section of 120-180m is recording many positive results.

Nghe An Provincial Party Committee directs replacement of officials who avoid and push in site clearance

|

Nghe An - The Provincial Party Committee requests replacement of weak officials, avoiding responsibility in site clearance.

Vietnam's oldest industrial park clears more than 227ha of land

|

Dong Nai - Bien Hoa 1 Industrial Park (Tran Bien ward) converted into an urban - commercial - service area and has cleared more than 227ha of land.

Will cold air cause rain and severe cold during the 2026 Lunar New Year

|

According to representatives of the meteorological agency, there are no signs of strong cold air appearing during the Lunar New Year 2026 period.

Cambodia condemns Thailand's move along the border

|

The Cambodian government believes that Thailand's actions violate the agreement, change the border status, and hinder the lives of local people.

Progress of site clearance for the 2.14 ha project adjacent to Hoan Kiem Lake

|

Hanoi - Many houses and agency headquarters have been cleared for the construction of the Hoan Kiem Lake East square - park project, with a scale of 2.14 ha.

Hanoi Metro adjusts peak hours, increases train frequency

|

Hanoi Metro adjusts peak hours and applies new train schedules on two routes Cat Linh - Ha Dong and Nhon - Hanoi Station.

Russian budget red alert right at the beginning of 2026

|

The Russian budget opened the year with worrying figures when the deficit in January was equivalent to nearly half of the full-year deficit target.

Hanoi urgently clears ground to open a 120-180m wide road

SÓNG HỮU |

Hanoi - The progress of land acquisition and site clearance to build a nearly 7km long road with a cross-section of 120-180m is recording many positive results.

Nghe An Provincial Party Committee directs replacement of officials who avoid and push in site clearance

QUANG ĐẠI |

Nghe An - The Provincial Party Committee requests replacement of weak officials, avoiding responsibility in site clearance.

Vietnam's oldest industrial park clears more than 227ha of land

HÀ ANH CHIẾN |

Dong Nai - Bien Hoa 1 Industrial Park (Tran Bien ward) converted into an urban - commercial - service area and has cleared more than 227ha of land.