North-South high-speed railway resettlement area through Ho Chi Minh City at risk of delay

MINH QUÂN |

Ho Chi Minh City - Long Buu resettlement area serving the North-South high-speed railway project through Ho Chi Minh City is at risk of delay due to many problems.

The North-South high-speed railway line passing through Ho Chi Minh City is about 17 km long, running parallel to the Ho Chi Minh City - Long Thanh - Dau Giay expressway, through An Phu intersection on Mai Chi Tho road before turning into Thu Thiem station.

On the route are Thu Thiem station (area of more than 17 ha) and Long Truong Depot (width of more than 60 ha).

Based on the preliminary boundary provided by the Ministry of Construction, the Ho Chi Minh City People's Committee has determined the scope of land recovery to be about 110 hectares, belonging to An Khanh, Binh Trung, Long Truong, Long Phuoc wards.

Through review, the entire route has about 200 affected houses. Among them, 106 households are arranged for resettlement with apartments (expected at Linh Trung apartment building), and 94 households need to arrange resettlement land in Long Buu Resettlement Area (phase 2 - Sub-area 2) with an area of about 6 hectares.

The preliminary total cost for compensation, support and resettlement for the section through Ho Chi Minh City is estimated at about 2,575 billion VND.

Khoang 94 ho se duoc bo tri nen tai dinh cu tai Khu tai dinh cu Long Buu.  Anh: Anh Tu
About 94 households will be allocated resettlement land in Long Buu Resettlement Area. Photo: Anh Tu

According to the plan, Ho Chi Minh City will approve the compensation, support, and resettlement project in October 2025, and set a target to complete the construction of the resettlement area in the second quarter of 2026.

However, the actual progress is currently very slow. According to a report by the Ho Chi Minh City Department of Construction, the Long Buu Resettlement Area project is facing a series of obstacles.

First of all, it is a conflict with the Law on Public Investment No. 58/2024/QH15. According to new regulations, investment projects are not allowed to overlap with projects that have had investment decisions. Meanwhile, the 6-hectare land area in Sub-area 2 is located in a technical infrastructure project approved in 2005, invested and implemented by District 9 Public Service One Member Limited Company.

In addition, the old project was implemented in the form of self-avanced construction capital, without using the budget, but so far the reimbursement of investment costs has not been completed. The project is also temporarily suspended to implement the conclusions of the Government Inspectorate, while independent audits to determine the volume and cost of unfinished construction have not been completed.

In addition, the 1/500 detailed planning project of the entire Long Buu area phase 2 (including Sub-area 2) is still in the process of adjustment, waiting for approval, causing many difficulties in implementing the next steps.

Faced with the above situation, on December 18, 2025, the Ho Chi Minh City Department of Construction issued an official letter requesting the Department of Finance to guide the Ho Chi Minh City Urban Infrastructure Investment Project Management Board to prepare a Report proposing investment policies for the technical infrastructure project of the resettlement area serving the North-South high-speed railway. In case of problems arising, departments and branches need to summarize and report to the Ho Chi Minh City People's Committee for consideration and decision.

The Ho Chi Minh City Urban Infrastructure Investment Project Management Board has proposed to the Ho Chi Minh City People's Committee to urgently disburse and repay expenses to District 9 Public Services One Member Limited Liability Company so that this unit has capital to complete unfinished infrastructure items.

This is considered a feasible and fastest option, ensuring inheritance, synchronization, and meeting the progress required by the Prime Minister.

MINH QUÂN
RELATED NEWS

Thu Thiem Station and the hope of the people after decades of waiting

|

HCMC - Many households in the Thu Thiem Railway Station railway project hope that the project will be fully implemented soon to stabilize their lives.

HCMC prepares to reclaim land, build resettlement areas to build the North-South high-speed railway

|

Ho Chi Minh City will approve compensation and resettlement for the North-South high-speed railway project in October 2025, and hand over the site to the construction unit in December 2026.

Brokers massively sell off-price land auctioned near Hanoi up to 300 million VND

|

Hanoi - The auction of 33 land plots in Yen Lang commune saw many brokerage groups advertising hundreds of millions of VND per land plot right after the auction.

Regional minimum wage increase from January 1, 2026, motivation for workers

|

Increasing the regional minimum wage from January 1, 2026 will create motivation for workers right from the beginning of the new year, according to labor expert - trade union.

From piles of rubble to new roofs in Nam Tra My, Da Nang

|

Da Nang - 157 landslide points, hundreds of households affected. From the rubble after floods, new roofs are gradually appearing in Nam Tra My.

Explaining why many headquarters in Nghe An were handed over but are slow to operate

|

Nghe An - Many headquarters have been transferred to receiving units but are slow to operate because they are completing legal procedures, usage plans and functional conversion.

The Ministry of Finance has transferred money to localities to deploy Tet gifts

|

The Ministry of Finance said that it has transferred funds for localities to implement giving Tet Nguyen Dan Binh Ngo 2026 gifts to subjects according to regulations.

The address of the show organizing company "Come here, four birds of paradise" closed and removed the signboard

|

After announcing the cancellation of the show on the evening of December 28, many viewers could not contact the organizing unit of the program "Come here, four sky birds" to request ticket refunds.

200 hộ dân phía Đông TPHCM di dời, nhường đất xây đường sắt tốc độ cao Bắc - Nam

MINH QUÂN |

TPHCM đẩy nhanh thu hồi đất khoảng 200 hộ dân làm đường sắt tốc độ cao Bắc - Nam, tổng kinh phí bồi thường, hỗ trợ, tái định cư gần 2.600 tỉ đồng.

Thu Thiem Station and the hope of the people after decades of waiting

NGỌC ÁNH |

HCMC - Many households in the Thu Thiem Railway Station railway project hope that the project will be fully implemented soon to stabilize their lives.

HCMC prepares to reclaim land, build resettlement areas to build the North-South high-speed railway

MINH QUÂN |

Ho Chi Minh City will approve compensation and resettlement for the North-South high-speed railway project in October 2025, and hand over the site to the construction unit in December 2026.