Lao Cai proposes to remove bottlenecks in site clearance for 9 railway stations

Duy Dũng |

Lao Cai - Site clearance work at 9 stations in the area is facing many obstacles regarding dossiers, property compensation and business relocation.

According to the Railway Project Management Board (Ministry of Construction), the latest design plan has adjusted the section passing through Lao Cai province from double-track to single-track.

The route has a length of 143.83km, passing through 12 communes and wards with a total land recovery area of about 651.5ha, a decrease of more than 745ha compared to the pre-feasibility study plan.

On the entire route, 38 stations will be formed with many different functions. The section passing through Lao Cai province has 9 stations, of which Nam Lao Cai Station is identified as an international intermodal station, playing a connecting role with the Chinese railway network through the Ha Khau area.

Lào Cai là điểm khởi đầu của dự án đường sắt. Ảnh: Đinh Đại
Lao Cai is the starting point of the railway project. Photo: Dinh Dai

Over the past time, Lao Cai Provincial People's Committee has coordinated with the Ministry of Construction, the Railway Project Management Board and consulting units to review the route direction and location of stations to limit the impact on existing residential areas, and at the same time create room for the development of logistics centers and new urban areas in the future.

In May 2026, the Railway Project Management Board coordinated with relevant units to hand over land clearance boundary markers for stations in the province.

This is an important basis for localities to update land use planning, urban planning and orientations for industrial and service development along the route.

Bản đồ hướng tuyến đường sắt Lào Cai - Hà Nội - Hải Phòng. Ảnh: Đinh Đại
Map of Lao Cai - Hanoi - Hai Phong railway route. Photo: Dinh Dai

However, the implementation process still faces many difficulties. To date, the dossier for planting markers and site clearance boundaries according to the feasibility study plan has not been fully handed over.

This makes it difficult for localities to have a legal basis to synchronously carry out measurement, inventory, determine the origin of land and develop compensation plans.

One of the areas heavily affected is Dong Pho Moi Industrial Park, Dong Pho Moi Industrial Cluster and Son Man - Van Hoa Industrial Cluster, where site clearance is expected to be carried out to build Nam Lao Cai Station.

Nhiều doanh nghiệp sẽ phải di dời để phục vụ việc thi công. Ảnh: Đinh Đại
Many businesses will have to relocate to serve the construction. Photo: Dinh Dai

Mr. Nguyen Huy Long - Chairman of the Lao Cai Provincial Business Association - said that many businesses in the region are owning production lines, industrial machinery, cold storage, fire prevention and fighting systems and many specialized assets of great value.

The counting, determination of compensation value and relocation plan for these assets is very complicated, requiring a specialized unit to appraise and provide specific guidance.

In addition, localities are also confused in applying the new regulations of the 2024 Land Law and Decree 88/2024/ND-CP related to compensation for housing and construction works.

Many contents need to be clearly guided such as determining the level of compensation for the affected project, criteria for assessing the usability of the remaining part of the project or the handling of materials and supplies after demolition.

Lào Cai chờ cơ chế để đẩy nhanh giải phóng mặt bằng tuyến đường sắt chiến lược. Ảnh: Đinh Đại
Lao Cai is waiting for a mechanism to accelerate site clearance for the strategic railway line. Photo: Dinh Dai

Faced with the above reality, Lao Cai Provincial People's Committee has proposed to the Ministry of Construction and the Railway Project Management Board to soon provide complete land clearance boundary documents for the locality to deploy work according to the plan.

At the same time, it is proposed that the Ministry of Agriculture and Environment guide the removal of obstacles related to compensation for assets and works attached to land when recovered.

According to leaders of Lao Cai Provincial People's Committee, the Lao Cai - Hanoi - Hai Phong railway line is a strategic infrastructure project, of particular importance to socio-economic development, expanding regional linkage space and promoting international trade.

Therefore, the locality proposed that ministries and sectors soon guide and resolve so that site clearance work can be deployed synchronously, creating conditions for the project to start and construct on schedule.

Duy Dũng
RELATED NEWS

Lao Cai removes site bottlenecks for nearly 2,200 billion VND industrial park

|

Lao Cai - By mid-June 2026, Au Lau ward has basically completed site clearance for the western area of the Tran Yen Industrial Park Project with a rate of 99.4%.

Lao Cai increases capital by tens of billions of VND for a series of boarding schools in mountainous areas

|

Lao Cai - Many ethnic minority boarding high school projects have been adjusted to increase total investment, add items and complete facilities.

100-year-old stone bridge in Hai Phong had many ancient stone slabs stolen at night

|

Hai Phong - People reflect that the Dong Trang stone bridge in Ai Quoc ward was stolen many stone components, functional agencies have intervened to verify the incident.

Live Football Austria vs Jordan at World Cup 2026

|

Live football match Austria vs Jordan in Group J World Cup 2026 at 11:00 AM today (June 17).

101 years of Revolutionary Journalism accompanying the country, promoting innovation

|

The 101st anniversary of the Vietnamese Revolutionary Press Day contributes to affirming the journey of accompanying the nation and promoting innovation.

Long Thanh airport passenger terminal technical operation in September

|

Dong Nai - Long Thanh airport passenger terminal will be technically operational in September 2026, moving towards commercial operation at the end of the year.

Hanoi residents gradually switch to green vehicles with new support policies

|

Hanoi - Hanoi residents are starting to switch to green vehicles after a new support policy, contributing to reducing emissions and protecting the urban environment.

Lao Cai removes site bottlenecks for nearly 2,200 billion VND industrial park

Đinh Đại |

Lao Cai - By mid-June 2026, Au Lau ward has basically completed site clearance for the western area of the Tran Yen Industrial Park Project with a rate of 99.4%.

Lào Cai đề nghị truy tố 8 bị can liên quan sai phạm dự án du lịch nông thôn

Đinh Đại |

Lào Cai - Sai phạm trong thanh quyết toán kinh phí tại dự án du lịch nông thôn ở Suối Giàng khiến 8 bị can bị đề nghị truy tố.

Lao Cai increases capital by tens of billions of VND for a series of boarding schools in mountainous areas

Đinh Đại |

Lao Cai - Many ethnic minority boarding high school projects have been adjusted to increase total investment, add items and complete facilities.