Lao Cai increases capital by tens of billions of VND for a series of boarding schools in mountainous areas

Đinh Đại |

Lao Cai - Many ethnic minority boarding high school projects have been adjusted to increase total investment, add items and complete facilities.

In mid-June, the construction atmosphere at key school projects in Lao Cai became more urgent than ever.

Through research, just a few months before entering the 2026-2027 school year, many key school projects in the highlands of Lao Cai are accelerating construction.

At the construction sites, hundreds of workers and machinery and equipment are mobilized to speed up the progress of items to put the project into use.

Phối cảnh Trường Phổ thông dân tộc nội trú Tiểu học và THCS tại Mường Khương. Ảnh: Đinh Đại
Perspective of the Ethnic Minority Boarding Primary and Secondary School in Muong Khuong. Photo: Dinh Dai

Along with the requirement to complete on schedule, some projects have also been adjusted to increase the total investment to supplement items, complete facilities, and better meet the learning and living needs of students.

Information from the Lao Cai Provincial Construction Investment Project Management Board, 4 projects of Ethnic Minority Boarding Primary and Secondary Schools in Muong Khuong, Y Ty, A Mu Sung and Pha Long currently reach from 55% to 75% of the construction volume.

Trường Phổ thông dân tộc nội trú Tiểu học và THCS Mường Khương được điều chỉnh tăng từ 215 tỉ đồng lên 255 tỉ đồng. Ảnh: Đinh Đại
Muong Khuong Ethnic Minority Boarding Primary and Secondary School was adjusted to increase from 215 billion VND to 255 billion VND. Photo: Dinh Dai

Many key items have completed the rough construction, moving to the architectural completion stage, installing technical systems and equipment.

In the process of implementation, the Lao Cai Provincial People's Committee has approved the adjustment of the total investment for two projects in Muong Khuong and Pha Long, raising the total additional capital to more than 80 billion VND.

The adjustment aims to supplement necessary items, synchronously complete technical infrastructure, and meet actual usage requirements after the project is completed.

The project of Muong Khuong Ethnic Minority Boarding Primary and Secondary School was adjusted from 215 billion VND to 255 billion VND, an increase of 40 billion VND.

The project is built on an area of nearly 5 hectares, including 9 building blocks with a scale of 28 classrooms, meeting the learning and living needs of about 980 students.

Reporters' records at the construction site show that the rough construction of most building blocks has been completed.

Classrooms, administration areas, dormitories, dining rooms and multi-purpose buildings are being focused on completion. The total construction volume of the entire project currently reaches about 75%.

Trường Phổ thông dân tộc nội trú Tiểu học và THCS Pha Long sau khi hoàn thành. Ảnh: Đinh Đại
Pha Long Ethnic Minority Boarding Primary and Secondary School after completion. Photo: Dinh Dai

Meanwhile, the project of Pha Long Ethnic Minority Boarding Primary and Secondary School was adjusted with a total investment from 220 billion VND to 262.8 billion VND, an increase of 42.8 billion VND.

This is a large-scale project consisting of 11 building blocks, serving about 980 students in the border area. To date, the implemented volume has reached about 55% of the plan.

Mr. Giang A Chu, a resident of Pha Long commune, believes that investing and completing the project items will help students in border areas access a more spacious and complete learning environment.

People all hope the project will be completed soon so that their children have a stable place to study, especially in the rainy season or cold winter," Mr. Chu said.

Lào Cai tăng hơn 80 tỉ đồng cho hai dự án trường nội trú vùng cao. Ảnh: Đinh Đại
Lao Cai increases more than 80 billion VND for two highland boarding school projects. Photo: Dinh Dai

Representatives of the Lao Cai Provincial Construction Investment Project Management Board said that the capital increase does not change the investment objectives of the projects but aims to complete the works in a synchronous manner, ensuring quality and long-term exploitation efficiency.

According to the Lao Cai Provincial Construction Investment Project Management Board, contractors are focusing manpower, materials and equipment to speed up construction progress. Many finishing materials such as doors, sanitary equipment, and electrical and plumbing materials have been gathered and are ready for installation in the near future.

When completed, the projects will not only meet the learning needs of thousands of students but also contribute to completing the school network in border areas, creating motivation to improve the quality of education in the highlands of Lao Cai.

Đinh Đại
RELATED NEWS

Lang Son urgently builds 7 multi-level boarding schools in border commune

|

Lang Son - 7 boarding schools in border communes are being urgently deployed.

Overview of 11 boarding school projects in Cao Bang ahead of schedule

|

Cao Bang - Assigned to complete before August 30, contractors at the construction site of 11 inter-level boarding schools are accelerating construction.

Lao Cai announces enrollment plan for 4 boarding schools in border areas

|

Lao Cai - The province has just approved the enrollment plan for boarding primary and secondary schools in 4 border communes.

Building a Visionary Press System Development and Management Strategy to 2045

|

On June 15, in Hanoi, the Ministry of Culture, Sports and Tourism organized a workshop to contribute opinions on building a dossier on the Strategy for development and management of the press system to 2030, with a vision to 2045.

Localities are allowed to sign contracts to support commune-level civil servants, not included in the payroll

|

The Ministry of Home Affairs requests localities to sign contracts to support commune-level civil servants, and people working under contracts are not included in the payroll.

Trade unions get involved, seafood processing workers receive late-paying salaries

|

Lam Dong - After the trade union and police worked with businesses, workers at a seafood processing company were paid the delayed salary.

Large amount of soil and dust arises when dismantling Chi Lang stadium in Da Nang

|

Da Nang - Dust arising during the dismantling of Chi Lang stadium is affecting the daily life and business of people in the surrounding area.

18 million phone numbers will be locked for calls on the afternoon of June 15

|

According to information from the Telecommunications Authority (Ministry of Science and Technology), more than 93 million phone numbers have been authenticated by users.

Lang Son urgently builds 7 multi-level boarding schools in border commune

Khánh Linh |

Lang Son - 7 boarding schools in border communes are being urgently deployed.

Overview of 11 boarding school projects in Cao Bang ahead of schedule

Long An |

Cao Bang - Assigned to complete before August 30, contractors at the construction site of 11 inter-level boarding schools are accelerating construction.

Lao Cai announces enrollment plan for 4 boarding schools in border areas

Đinh Đại |

Lao Cai - The province has just approved the enrollment plan for boarding primary and secondary schools in 4 border communes.