Important notes on the order of construction of urgent construction projects

Khương Duy |

The Ministry of Construction has made many important notes on the deployment of urgent construction projects.

Mr. Lo Cam Hong (Son La province) reflected questions related to the procedures for implementing construction projects in urgent cases. According to him, for projects under the provisions of point a, clause 1, Article 130 of the 2014 Construction Law, which was amended and supplemented in 2020, do investors have to carry out appraisal procedures at specialized construction agencies and submit projects for approval before proceeding with construction?

Answering this content, the Ministry of Construction said that the provisions in point a, clause 1, Article 130 of the Construction Law have been detailed in Article 69 of Decree No. 175/2024/ND-CP of the Government on management of construction activities.

Việc triển khai thi công các công trình xây dựng khẩn cấp được thực hiện theo quy định của pháp luật nhằm bảo đảm đáp ứng yêu cầu xử lý kịp thời các tình huống cấp bách, đồng thời tuân thủ các quy định về quản lý hoạt động xây dựng. Ảnh: Tô Công
The Ministry of Construction notes that the deployment of emergency construction works is carried out in accordance with the law to ensure meeting the requirements of timely handling of urgent situations, while complying with regulations on construction activity management. Photo: To Cong

According to the provisions of the above decree, for urgent construction projects, the law does not set the requirement to carry out the appraisal step of the specialized construction agency as well as the project approval procedure before deploying construction.

This means that projects in emergencies will be organized and implemented according to their own procedures, in order to meet the requirements of timely handling of urgent situations. Construction is carried out according to the procedures specified in Article 69 of Decree No. 175/2024/ND-CP.

The Ministry of Construction requests people and related organizations to study current legal regulations to implement them in the correct order for urgent construction projects.

Khương Duy
RELATED NEWS

Real estate leasing with revenue over 500 million VND needs to pay attention to tax declaration milestones

|

Individuals leasing real estate when having revenue over 500 million VND/year must declare and pay taxes according to new regulations.

Thanh Hoa voters worry about Son Thuy bridge damage, what does the Ministry of Construction say

|

Thanh Hoa voters propose repairing Son Thuy bridge on National Highway 16 due to damage. The Ministry of Construction has responded in writing and stated the handling direction.

Bringing 3 industrial park projects near Long Thanh airport into infrastructure construction

|

Dong Nai - The Provincial People's Committee requests to soon put 3 industrial park projects with a scale of more than 2,244 ha near Long Thanh airport into infrastructure construction.

Ho Chi Minh City builds a house number digitization database: People do not have to change house numbers

|

Ho Chi Minh City builds a city-wide house number database using GIS technology. This does not change the current house numbers of people.

Agricultural land converted to residential land in 2026: What procedures should be noted to avoid errors?

|

Agricultural land that wants to be converted to residential land must carry out procedures to apply for permission from competent authorities and meet the conditions according to the provisions of law.

Patients in the kidney dialysis village eagerly await the election day on March 15

|

Hanoi - Patients being treated in the "kidney dialysis hamlet" in Bach Mai ward have been propagated the Election Law and expressed their excitement to wait for the March 15th election day.

Liverpool disappointingly lost at Galatasaray's stadium

|

In the early morning of March 11 (Vietnam time), Liverpool lost to Galatasaray 0-1 in the first leg of the Champions League round of 16 in the 2025-2026 season.

Verifying a car stopping in the middle of the road, moving abnormally causing traffic obstruction

|

Quang Tri - Functional agencies are verifying cars stopping in the middle of the road, unusually moving backwards in Dong Hoi ward.

Real estate leasing with revenue over 500 million VND needs to pay attention to tax declaration milestones

Song Anh |

Individuals leasing real estate when having revenue over 500 million VND/year must declare and pay taxes according to new regulations.

Thanh Hoa voters worry about Son Thuy bridge damage, what does the Ministry of Construction say

Khương Duy |

Thanh Hoa voters propose repairing Son Thuy bridge on National Highway 16 due to damage. The Ministry of Construction has responded in writing and stated the handling direction.

Bringing 3 industrial park projects near Long Thanh airport into infrastructure construction

HÀ ANH CHIẾN |

Dong Nai - The Provincial People's Committee requests to soon put 3 industrial park projects with a scale of more than 2,244 ha near Long Thanh airport into infrastructure construction.

Ho Chi Minh City builds a house number digitization database: People do not have to change house numbers

MINH QUÂN |

Ho Chi Minh City builds a city-wide house number database using GIS technology. This does not change the current house numbers of people.

Agricultural land converted to residential land in 2026: What procedures should be noted to avoid errors?

Thạch Lam |

Agricultural land that wants to be converted to residential land must carry out procedures to apply for permission from competent authorities and meet the conditions according to the provisions of law.