Land recovery for 503 cases in Tan Khanh ward for 5,892 billion VND project

ĐÌNH TRỌNG |

Ho Chi Minh City - Tan Khanh Ward People's Committee is accelerating the progress of mobilizing people to receive compensation to recover land for the Suoi Cai dredging and reinforcement project.

According to Tan Khanh Ward People's Committee (HCMC), in the ward, there are 494 households and 9 organizations affected when implementing the Suoi Cai dredging and reinforcement project. The total land area in the ward that needs to be recovered for project implementation is 613,465 m2. Up to now, the issuance of land recovery notices for 503 cases has been completed, reaching a rate of 100%. At the same time, units have also completed the measurement and inventory of land and assets attached to land.

Functional agencies have approved compensation and support plans for 503 households, with an amount of 1,509.9 billion VND, reaching a rate of 100%. Regarding compensation and support payments, 473 cases have been paid, with a total amount of 1,469.4 billion VND. The handover and land recovery rate reached 88.8%.

According to the Ward People's Committee, ward leaders have directly met with the remaining households to propagate and mobilize consensus on the policy of compensation and handover of land for project implementation.

Leaders of Tan Khanh Ward People's Committee also listened to and recorded the thoughts, aspirations and recommendations of each household. The ward hopes that households will share and accompany the locality, soon agree on compensation plans and hand over land.

In the coming time, specialized agencies of Tan Khanh ward will continue to review, guide and resolve contents under their authority in accordance with regulations to recover land. All compensation and support regimes are implemented publicly, fully, and in accordance with regulations, ensuring the legitimate and lawful rights and interests of the people.

Dự án nạo vét, gia cố Suối Cái. Ảnh: Đình Trọng
Suoi Cai dredging and reinforcement project. Photo: Dinh Trong

It is known that the project to dredge and reinforce Suoi Cai section from Tho Ut bridge to Dong Nai river is invested by the Ho Chi Minh City Urban Infrastructure Project Management Board with a total investment of more than 5,892 billion VND. The project has a length of nearly 19 km passing through Binh Duong ward, Tan Hiep ward and Tan Khanh ward. Currently, Binh Duong ward and Tan Hiep ward are about to complete land acquisition. The construction of packages about 6 km long through these two localities is also about to be completed.

ĐÌNH TRỌNG
RELATED NEWS

Land acquisition must go hand in hand with rebuilding people's lives

|

Land acquisition for development is necessary, but compensation must be aimed at helping people rebuild their lives and stabilize long-term livelihoods.

66 households in Ho Chi Minh City have their land recovered, the highest compensation price is 170 million VND/m2

|

Ho Chi Minh City recovers more than 22,000 m2 of land from 66 households and 1 organization on Luong Dinh Cua street, the highest expected land compensation price is about 170 million VND/m2.

Land acquisition of 346 cases for phase 2 construction of DT 748 road expansion project

|

Ho Chi Minh City - The land recovery for the project to upgrade and expand DT 748 road through Phu An ward is basically completed, creating conditions for phase 2 of the project to be constructed.

Multiple car accident with 7 cars on the Ho Chi Minh City - Trung Luong highway

|

Tay Ninh - A chain collision between 7 cars on the Ho Chi Minh City - Trung Luong expressway caused traffic congestion for more than 2 km.

Thailand issues curfew after 51 attacks overnight

|

Narathiwat provincial authorities have issued a curfew after a series of attacks occurred in this locality and 2 southern provinces of Thailand, Yala and Pattani.

Scene of a multi-vehicle accident between a passenger car and a truck and a car in An Long, Ho Chi Minh City

|

Ho Chi Minh City - On Tao Luc Bac Tan Uyen - Phu Giao - Bau Bang road, a traffic accident occurred between a sleeper bus and a truck and a car.

Vietnam national team has 2 days to prepare for the decisive match against Thailand

|

The Vietnamese team returned to Hanoi earlier than Thailand and has 2 days to prepare for the second leg of the ASEAN Cup 2026 final.

31 Tuyen Quang Specialized Students admitted to Hanoi University of Science and Technology

|

Among the 31 students of Tuyen Quang High School for the Gifted who were admitted to Hanoi University of Science and Technology after the supplementary consideration, only 1 student was admitted based on high school graduation exam scores.

Land acquisition must go hand in hand with rebuilding people's lives

Hoàng Văn Minh |

Land acquisition for development is necessary, but compensation must be aimed at helping people rebuild their lives and stabilize long-term livelihoods.

66 households in Ho Chi Minh City have their land recovered, the highest compensation price is 170 million VND/m2

MINH QUÂN |

Ho Chi Minh City recovers more than 22,000 m2 of land from 66 households and 1 organization on Luong Dinh Cua street, the highest expected land compensation price is about 170 million VND/m2.

Land acquisition of 346 cases for phase 2 construction of DT 748 road expansion project

ĐÌNH TRỌNG |

Ho Chi Minh City - The land recovery for the project to upgrade and expand DT 748 road through Phu An ward is basically completed, creating conditions for phase 2 of the project to be constructed.