Procedures for granting new construction permits for individual houses according to new regulations

Như Hạ |

Decision 864/QD-BXD in 2025, effective from July 1, 2025, stipulates the procedures for granting construction permits for individual houses.

According to sub-section 1, Section C, Part II issued with Decision 864/QD-BXD in 2025, the procedures for granting new construction permits for individual houses are as follows:

- The investor submits a request for a construction permit to the Commune-level Public Administration Service Center.

- Within 7 working days from the date of receipt of the dossier, the competent authority granting the construction permit for level III and level IV works must organize the dossier appraisal, on-site inspection, and notify the investor in writing once to supplement and complete the dossier if the documents are still missing, the documents are not in accordance with regulations or are not in reality.

The construction licensing agency is responsible for checking the conditions for granting a construction permit according to the provisions of Article 50 of Decree 175/2024/ND-CP.

The inspection is conducted as follows:

+ Compare the suitability of the construction design drawings in the construction permit application with the basic design assessed by the construction expertise agency and stamped for confirmation for works under the project with a request for appraisal of the feasibility study report at the construction expertise agency;

+ Check the suitability of the construction design drawings in the construction permit application with the construction design drawings approved for fire prevention and fighting by competent authorities for construction works subject to fire prevention and fighting approval requirements;

+ Check the completeness and validity of the inspection results report (if any) for works requiring design examination according to the provisions of Decree 175/2024/ND-CP as amended and supplemented by Decree 105/2025/ND-CP and Decree 144/2025/ND-CP.

- Within 5 working days from the date of receipt of additional documents but not meeting the requirements according to the notice, the competent authority issuing the construction permit is responsible for notifying the investor in writing to continue completing the documents.

In case the supplementation of documents still does not meet the contents according to the notice, within 3 working days from the date of receipt of the supplementary documents, the competent authority issuing the construction permit is responsible for notifying the investor about the reason for not granting a construction permit for level III and level IV works.

- The competent authority issuing the construction permit compares the conditions according to the provisions of the Construction Law to send a document to collect the opinion of the relevant state management agency.

Within 12 days from the date of receipt of the dossier, the state management agencies are asked for opinions and are responsible for responding in writing to the contents under their management functions.

After the above deadline, if these agencies do not have an opinion, they will be considered to have agreed and must be responsible for the contents under their management functions; the construction licensing agency shall base on current regulations to decide on the granting of a construction permit for level III and level IV works.

- Within 20 days (or 15 days for individual houses) from the date of receiving a complete and valid dossier, the competent authority is responsible for considering granting a construction permit for a level III or level IV project.

Như Hạ
RELATED NEWS

Conditions for construction permits issued by phase

|

A construction permit by phase is a form of licensing suitable for large and complex projects.

Da Nang announces list of major projects exempted from construction permits

|

Da Nang - The Da Nang Department of Construction has just issued a notice regarding the exemption of construction permits for projects that meet the conditions.

Things to know about granting construction permits to level 4 houses

|

The granting of a construction permit for a level 4 house is carried out in accordance with legal regulations, depending on the purpose of land use, planning area and construction location.

UAV attack, Dubai airport temporarily closed

|

A series of UAV attacks on Dubai airport in the United Arab Emirates killed 1 person.

Accelerate completion of Ring Road 2.5 section Kim Dong - Dam Hong before handover date

|

Hanoi - Ring Road 2.5 Kim Dong - Dam Hong section gradually reveals a new face when the final items are being urgently constructed before the handover time.

Rumors spread that Iran's Supreme Leader secretly went abroad for treatment

|

Iranian Supreme Leader Mojtaba Khamenei is believed to have been injured in the airstrike on February 28 and may have been taken abroad for treatment.

Starlink satellite Internet subscribers in Vietnam are expected to pay 2.2 million VND per month

|

Starlink satellite Internet service in Vietnam is expected to have a monthly subscription fee of about 2.2 million VND.

Da River dries up to the bottom, in many sections people can stroll in the middle of the river

|

The water level of the Da River downstream of Hoa Binh Hydropower Plant is low, revealing many sandbanks and gravel in the middle of the river, people can wade through the water or walk quite far into the middle of the stream.

Conditions for construction permits issued by phase

Như Hạ (T/H) |

A construction permit by phase is a form of licensing suitable for large and complex projects.

Da Nang announces list of major projects exempted from construction permits

Thu Giang |

Da Nang - The Da Nang Department of Construction has just issued a notice regarding the exemption of construction permits for projects that meet the conditions.

Things to know about granting construction permits to level 4 houses

Như Hạ |

The granting of a construction permit for a level 4 house is carried out in accordance with legal regulations, depending on the purpose of land use, planning area and construction location.