Progress of a project worth over VND6,200 billion in the center of Hai Phong

Hoàng Khôi |

Hai Phong - On June 12, Vice Chairman of the City People's Committee Nguyen Duc Tho inspected the progress of the Nguyen Trai Bridge Construction and Urban Renovation Project in the surrounding area.

According to the report of the Hai Phong Traffic and Agricultural Construction Investment Project Management Board, the Nguyen Trai Bridge Construction Investment and Urban Renovation Project in the surrounding area has a total reclaimed land area of about 63.52 hectares. Of which, Ngo Quyen district has 54.47 hectares and Thuy Nguyen city has 9.05 hectares.

Up to now, Ngo Quyen district has handed over 115,885 m2 of land. However, there are still problems with 35 households using collective houses on Nguyen Trai Street (May To Ward), and 3/21 organizations have not yet handed over the entire site. Thuy Nguyen City has basically completed the site clearance work.

The Nguyen Trai Bridge and Urban Renovation Project in the surrounding area started on December 18, 2024 and started construction on January 18, 2025, with a total investment of more than VND 6,235 billion from the central budget and Hai Phong. To date, the value of the project's implementation volume has reached about VND 520.6/3,802 billion, equivalent to 13.69% of the total investment.

Cong truong xay dung cau Nguyen Trai. Ảnh: Cong TTDT Hai Phong
Nguyen Trai Bridge construction site. Photo: Hai Phong Portal

For package 15 (construction of approach bridges, approach roads and intersections), contractors are simultaneously deploying 14 construction points on the two banks of Thuy Nguyen and Ngo Quyen; completed 256/340 bored piles; 14 branch bridge piers; 7 approach bridge piers; 5 retaining walls and 5 branch bridge body walls.

For package No. 14 (construction of the cable-stayed main bridge), contractors are deploying 4 construction teams at the same time, having completed 55/88 bored piles; are constructing the T13 pillar body and closing the ring of the T11 pillar foundation hole. The value of completed volume is estimated at about 180/2,367 billion VND (equivalent to 7.56% of the contract value, excluding contingency costs)...

After inspecting the situation and meeting to listen to the opinions of relevant units, Mr. Nguyen Duc Tho - Vice Chairman of the City People's Committee - requested the People's Committee of Ngo Quyen District to urgently review and propose to the city a plan to clear the land for the two apartment buildings in lane 6, Nguyen Trai Street and No. 8 May To Street no later than June 15.6; complete site clearance of the area belonging to Hai Phong Port Technical Services Joint Stock Company in June 2025.

Regarding the transfer of railway infrastructure assets to the city for management, the Department of Construction and the Department of Finance in coordination with Vietnam Railway Corporation, Vietnam Railway Authority, and the Hai Phong Traffic and Agricultural Construction Investment Project Management Board urgently complete the process to organize the handover and dismantling of railway infrastructure in early July. The contractors mobilized maximum human resources, vehicles, and equipment to carry out the most urgent and scientific construction at both ends of the bridge. The construction process ensures technical and aesthetic requirements for the project; environmental sanitation and traffic safety on both roads and waterways.

Hoàng Khôi
TIN LIÊN QUAN

Supporting housing for meritorious people in Hai Phong: Paying gratitude with action

|

Hai Phong - The city has just approved a Project to support the construction, renovation and repair of houses for people with meritorious services and relatives of martyrs in the area.

Hai Phong does not let the process of restructuring the apparatus affect the work of preventing storm No. 1

|

Hai Phong - The City People's Committee has just issued instructions on closely monitoring developments and proactively responding to storm No. 1 Wutip.

Hai Phong prioritizes investment in 32 key transport projects in the 2026-2030 period

|

Hai Phong - On June 10, the Standing Committee of the City Party Committee met to agree on a list of 32 key transport projects for the 2026-2030 period and investment policies for a number of projects.

Customers cry and laugh when trapped on Ly Son Island to avoid storm No. 1

|

Quang Ngai - Due to the impact of storm No. 1 Wutip, 100 tourists were stranded on Ly Son Island when the ferry stopped operating.

Deputy Minister of Home Affairs said that it will remove sub-licenses for labor export

|

Deputy Head Nguyen Van Hoi said that he will remove "sub-licenses" to improve the quality of service for people and businesses in the labor export sector.

Iran launches more than 100 UAVs to respond to Israel

|

The Israeli military said Iran launched more than 100 unmanned aerial vehicles (UAVs) towards Israel on June 13.

Director of Hoa Binh Provincial Police holds the position of Director of the Traffic Police Department

|

Colonel Do Thanh Binh, Director of Hoa Binh Provincial Police, was transferred to the position of Director of the Traffic Police Department, Ministry of Public Security.

Supporting housing for meritorious people in Hai Phong: Paying gratitude with action

Mai Dung |

Hai Phong - The city has just approved a Project to support the construction, renovation and repair of houses for people with meritorious services and relatives of martyrs in the area.

Hai Phong does not let the process of restructuring the apparatus affect the work of preventing storm No. 1

Hoàng Khôi |

Hai Phong - The City People's Committee has just issued instructions on closely monitoring developments and proactively responding to storm No. 1 Wutip.

Hai Phong prioritizes investment in 32 key transport projects in the 2026-2030 period

Hoàng Khôi |

Hai Phong - On June 10, the Standing Committee of the City Party Committee met to agree on a list of 32 key transport projects for the 2026-2030 period and investment policies for a number of projects.