Ho Chi Minh City reclaims land from 1,164 households in Thu Duc, how will it be compensated?

MINH QUÂN |

Thu Duc City will reclaim 61.15 hectares of land, affecting 1,164 households to build Ho Chi Minh City's Ring Road 2, causing many people to worry about compensation and resettlement support plans.

Sharing about the readiness to hand over the site for the project, Ms. Dang Thi Hue, a resident of Phuoc Long B ward, said: “We accept the relocation, but the State needs to complete the project soon. For households that agree to the relocation, the State agency must compensate and support appropriately. In particular, households wishing to resettle on the spot need to be resolved harmoniously, so that people can feel secure to start a new life.”

Mr. Vo Tri Dung - Head of Compensation and Site Clearance of Thu Duc City, said that the Beltway 2 project through Thu Duc City includes two sections: the section from Phu Huu Bridge to Vo Nguyen Giap Street and the section from Vo Nguyen Giap Street to Pham Van Dong Street, with a total length of more than 6km.

The total area of ​​land recovered is 61.15 hectares, affecting 1,164 households and organizations.

As of early October 2024, the Thu Duc City Compensation and Site Clearance Board has handed over the field boundaries to the relevant wards to prepare for compensation according to regulations. The consulting unit is conducting land valuation to determine the compensation unit price, then submitting it to the Compensation Council for approval.

Huong tuyen Vanh dai 2 du kien di qua.  Anh: Anh Tu
The proposed route of Ring Road 2. Photo: Anh Tu

Regarding the resettlement plan, the project plans to arrange 574 plots of land and 86 apartments for phase 1, while phase 2 will have 90 plots of land and 12 apartments.

However, only a few apartments are currently available for immediate resettlement. The remaining resettlement land funds need to complete legal and infrastructure before being eligible for resettlement, expected before November 2024.

Many households expressed their desire to be resettled near the clearance site. Therefore, Thu Duc City authorities have considered using public land funds around the project area to build resettlement areas, meeting the wishes of the people.

Vanh dai 2 di qua khu vuc nga tu Binh Thai tren duong Vo Nguyen Giap.  Anh: Anh Tu
Beltway 2 passes through the Binh Thai intersection on Vo Nguyen Giap Street. Photo: Anh Tu

Mr. Hoang Tung - Chairman of Thu Duc City People's Committee, said that the locality is stepping up the verification of land origin and related documents to proceed with compensation.

He emphasized that the Compensation Board needs to grasp the thoughts and aspirations of each household, from which to have measures to propagate and mobilize people to agree. In addition, digitizing compensation records will help the process become more transparent and easier to monitor.

“We will publicize the compensation policy so that people can monitor the progress, and at the same time publicize the resettlement areas and support policies, creating conditions for people to feel secure in handing over the land, speeding up the progress of the Ring Road 2 project,” said Mr. Hoang Tung.

Chairman of the Ho Chi Minh City People's Committee Phan Van Mai also directed Thu Duc City to complete disbursing at least VND7,600 billion in compensation capital for the project by the end of this year.

According to the Ho Chi Minh City Traffic Construction Investment Project Management Board, if the site is handed over on schedule, construction of these two sections of Ring Road 2 will begin in the second quarter of 2025 and be completed in 2027.

The two sections of Ring Road 2 through Thu Duc City were approved by the Ho Chi Minh City People's Council for investment in late 2023 with a total cost of about VND13,871 billion.

Both projects will have their entire land cleared from the beginning, 67m wide, then parallel roads will be built on both sides with 6 lanes (each road is 17m wide, 3 lanes). The vacant land in the middle of the route will be reserved for future road expansion.

MINH QUÂN
RELATED NEWS

Real estate faces a turning point in comprehensive transparency

|

The establishment of the Real Estate Trading Center is considered one of the strong moves to help transparentize the real estate (RE) market.

Workers carrying the colors of spring, hoping for a full Tet with their families

|

Hanoi - In the days leading up to Tet, on the streets of the Capital, it is not difficult to see images of drivers busily carrying peach and kumquat trucks.

Dinh Bac surpasses Son Tung M-TP in the ranking of people with influence on social networks

|

Striker Nguyen Dinh Bac entered the top 10 most prominent influencers on social networks in December 2025, ranked above Son Tung M-TP and Tran Thanh.

Truck plunges into abyss on Bao Loc Pass, driver dies

|

Lam Dong - While going down Bao Loc Pass, a truck carrying an excavator lost its brakes and plunged into a cliff about 5m deep, killing the driver on the spot and injuring the assistant driver who had to be hospitalized.

Phuoc An bridge connecting Ho Chi Minh City and Dong Nai reaches 50% of construction progress

|

Ho Chi Minh City - Phuoc An bridge across the Thi Vai River connecting to Dong Nai, with a total investment of nearly 4,900 billion VND, has reached nearly 50% of the construction progress.

Pork prices increase near Tet, supermarkets in Ho Chi Minh City get involved in price stabilization

|

Pork prices in Ho Chi Minh City increased sharply near the Lunar New Year 2026, supermarkets deployed price stabilization, promotions and increased reserves to support consumers.

Fishing boat sinks at La Gi Port, 15 crew members escape in time

|

Lam Dong - A fishing boat carrying 15 crew members just departed from La Gi Port, when it reached the port entrance, it sank.

Party cell secretary dares to think and dare to do in the high mountainous area of Tuyen Quang

|

Amidst the mountains and rocks of the highlands of Tuyen Quang, Party Secretary Tho Mi Xa with enthusiasm and determination has contributed to changing the lives of the people every day.

Tuyến đường dài 64km bao quanh TPHCM chờ ngày khép kín

MINH QUÂN |

Vành đai 2 dài 64km bao quanh TPHCM sau 17 năm quy hoạch đến nay còn 14km chưa khép kín, chia làm 4 đoạn.

7 năm chưa làm xong 2,7km đường vành đai ở TPHCM

MINH QUÂN |

TPHCM – Khởi công năm 2017, dự kiến hoàn thành sau 2 năm, nhưng đến nay 2,7km đường Vành đai 2 (từ đường Phạm Văn Đồng đến nút giao Gò Dưa, TP Thủ Đức) mới đạt gần 44% khối lượng và tạm ngưng thi công 4 năm qua.

Dự án Vành đai 2 TPHCM lận đận 16 năm vẫn chưa khép kín

MINH QUÂN |

TPHCM - Dự án đường Vành đai 2 TPHCM được quy hoạch từ năm 2007 với tổng chiều dài 64km có vai trò quan trọng giúp phân luồng, giảm áp lực giao thông nội đô. Tuy nhiên, cho đến nay, đường Vành đai 2 hiện vẫn còn 14 km (chia làm 4 đoạn) chưa được khép kín.