Workers work through the September 2 ceremony to ensure the progress of Quang Ngai Expressway

Viên Nguyễn |

The Quang Ngai - Hoai Nhon Expressway project mobilized 3,000 human resources, constructing through the September 2 ceremony, striving to complete the project by the end of 2025.

Working day and night, determined to finish on time

The North-South Expressway Construction Investment Project, Quang Ngai - Hoai Nhon section, has a total investment of more than VND 20,400 billion (of which the construction value is nearly VND 14,500 billion), with a length of 88km, passing through the provinces of Quang Ngai (60.3km) and Binh Dinh (27.7km). This is the largest project of the 12 component projects.

The route has 3 tunnels across the mountain including: tunnel No. 1 is 610m long, tunnel No. 2 is 698m long and tunnel No. 3 is 3,200m long, along with 77 bridges, 586 culverts, 81 underpasses for people.

Responding to the peak movement of "500 days and nights of competition to complete 3,000km of expressway" launched by the Prime Minister, contractors constructing the Quang Ngai - Hoai Nhon component project are making efforts to work day and night to speed up the project's progress.

A representative of Deo Ca Group (the lead contractor of the consortium) said that 50 50 50 50 50 working hours with 3,000 personnel and 1,100 equipment are being deployed at the construction site. Total output to date has reached about 10,250 billion VND, equivalent to 77% of the total volume.

Regarding the road, crushed stone aggregate has been constructed to 98% and nearly 70km of asphalt paving has been carried out. According to the plan, the asphalt concrete construction is expected to be completed by the end of September 2025.

There are 77 bridges on the route, all bridges have completed the lower structure, the beam casting and installation of beams and are under construction of the bridge deck. Regarding the tunnel, tunnels 1 and 2 have basically completed the construction and installation of electromechanical equipment and ITS system. tunnel No. 3 has dug through 2 tunnels, and is constructing concrete for tunnel lining and roadbed.

Regarding production, the assembly of traffic safety components reached about 95% of output. Currently, the construction of safety nets on both sides of the route has been completed, and the installation of guardrails, median strips, signs, etc. is underway.

Quang Ngai strives to resolve problems related to land

To date, the construction volume has reached about 80% of the contract value. Regarding the construction of the rest stop on the expressway through Dinh Cuong commune, the construction contractor has approached the site and implemented construction on an area of 7 hectares, reaching 58%. However, the project's site clearance progress is still slow, not meeting the set plan.

At a meeting related to some contents on the construction progress of the Quang Ngai - Hoai Nhon section, the section passing through the province, Mr. Nguyen Ngoc Sam - Vice Chairman of the Provincial People's Committee - said that there are still problems while the time to complete and put the project into operation is very little.

Therefore, the leaders of the Provincial People's Committee requested heads of agencies, units, and Chairmen of People's Committees of communes and wards to focus resources, uphold a sense of responsibility, and be determined in directing and operating, to promptly support the construction unit to complete the project in accordance with the requirements of the Government, the Prime Minister, and the province.

On August 27, a representative of Deo Ca Group said that according to the contract, the project completion date is August 2026. However, the parties are striving to basically complete the bridge and road section before September 30, 2025, while tunnel No. 3 will be completed before December 31, 2025 - 8 months ahead of schedule in the contract.

"In order to ensure the set progress, construction units at the Quang Ngai - Hoai Nhon expressway project will continue to work as usual on September 2 this year" - said a representative of Deo Ca Group.

Viên Nguyễn
RELATED NEWS

In the middle of the night, the Quang Ngai - Hoai Nhon expressway construction site is still bustling with the sound of machinery

|

Under the lights, thousands of workers are working on the Quang Ngai - Hoai Nhon expressway, racing against time to complete the project by the end of 2025.

The third largest mountain tunnel in the country on the Quang Ngai - Hoai Nhon expressway has been dug

|

tunnel No. 3, part of the Quang Ngai - Hoai Nhon expressway component project, has been dug. When completed, this will be the third largest mountain tunnel in the country.

Quang Ngai - Hoai Nhon Expressway accelerates, ready to open to traffic by the end of 2025

|

The Quang Ngai - Hoai Nhon expressway project has 6 months left to open to traffic. The contractor is speeding up the progress, ensuring the project is completed on time.

Quang Ngai to completely handle the existence of the Quang Ngai - Hoai Nhon expressway before June 30

|

Quang Ngai - Resolutely remove obstacles and completely handle existing problems related to the Quang Ngai - Hoai Nhon Expressway before June 30

The streets of Ho Chi Minh City are brightly decorated with flags and flowers, celebrating the 80th anniversary of National Day on September 2

|

HCMC - These days, the streets of the city named after Uncle Ho are filled with the colorful flags and flowers of the people celebrating National Day on September 2.

Many experiences in watching the A80 parade successfully

|

The commemoration, parade, and parade to celebrate the 80th anniversary of the August Revolution and National Day on September 2 are solemn events. Tourists should prepare carefully.

Hanoi wears red flag with yellow star, brilliantly celebrating the National Day

|

Hanoi - These days, the capital is brilliant with the red flag with yellow star, wearing a heroic and atmospheric appearance to welcome the September 2 holiday.

Inside the military equipment gathering place before the 2.9 parade

|

Hanoi - Many people flocked to the F1 racetrack to watch the blocks of vehicles, military fireworks, and police special vehicles practicing before the parade and parade on the occasion of the 80th anniversary of National Day.

In the middle of the night, the Quang Ngai - Hoai Nhon expressway construction site is still bustling with the sound of machinery

VIÊN NGUYỄN |

Under the lights, thousands of workers are working on the Quang Ngai - Hoai Nhon expressway, racing against time to complete the project by the end of 2025.

The third largest mountain tunnel in the country on the Quang Ngai - Hoai Nhon expressway has been dug

VIÊN NGUYỄN |

tunnel No. 3, part of the Quang Ngai - Hoai Nhon expressway component project, has been dug. When completed, this will be the third largest mountain tunnel in the country.

Quang Ngai - Hoai Nhon Expressway accelerates, ready to open to traffic by the end of 2025

VIÊN NGUYỄN |

The Quang Ngai - Hoai Nhon expressway project has 6 months left to open to traffic. The contractor is speeding up the progress, ensuring the project is completed on time.

Quang Ngai to completely handle the existence of the Quang Ngai - Hoai Nhon expressway before June 30

VIÊN NGUYỄN |

Quang Ngai - Resolutely remove obstacles and completely handle existing problems related to the Quang Ngai - Hoai Nhon Expressway before June 30