Final sprint to complete border schools in Lam Dong

Phan Tuấn |

Lam Dong is accelerating the construction of school projects in border areas, determined to complete them on schedule, meeting teaching and learning needs.

Speeding towards the finish line

Thuan An Inter-level Boarding Primary and Secondary School Project (Thuan An commune), with a total investment of nearly 226 billion VND.

To date, the project has reached 75% of the volume, and the body part has been completed 100% of the volume. There are currently about 330 workers constructing project items at the construction site.

Similarly, the Quang Truc Inter-level Boarding Primary and Secondary School Project has a total investment of 240 billion VND, built on an area of nearly 5ha in Bu Dar hamlet, Quang Truc commune.

The project started construction in November 2025. To date, the project has completed about 65% of the volume and about 430 workers are working at the construction site.

To ensure that August 15, 2026 will complete the items in the house and before August 30, organize the acceptance of the project, the investor proposed to mobilize an additional 170 workers to work.

On July 25, Member of the Party Central Committee, Chairman of Lam Dong Provincial People's Committee Ho Van Muoi directly inspected the construction progress of Quang Truc and Thuan An Inter-level Boarding Primary and Secondary Schools.

At the inspection, departments and branches proposed that investors and construction units mobilize and rearrange the workforce in a reasonable direction.

In which, focus on completing the main items serving teaching, learning, and boarding. Relevant departments must be present at the scene 24/24h for technical handling. For equipment installation, items that are completed first, focus on installing equipment immediately...

Ông Hồ Văn Mười, Ủy viên Ban Chấp hành Trung ương Đảng, Phó Bí thư Tỉnh ủy, Chủ tịch UBND tỉnh Lâm Đồng kiểm tra thực tế tiến độ thi công các dự án trường học ở vùng biên. Ảnh: Đặng Dương
Mr. Ho Van Muoi, Member of the Party Central Committee, Deputy Secretary of the Provincial Party Committee, Chairman of Lam Dong Provincial People's Committee inspects the actual progress of construction of school projects in the border area. Photo: Dang Duong

Overtime, increased shifts to complete the project

At the inspection, Chairman of Lam Dong Provincial People's Committee Ho Van Muoi emphasized that these are projects of particularly important political significance, directly serving the education cause of the locality.

Therefore, the entire political system must get involved with the highest sense of responsibility, determined to complete and hand over before August 30 to be ready for the new school year.

According to Chairman of Lam Dong Provincial People's Committee Ho Van Muoi, the time fund is only 35 days and nights. Therefore, investors and construction units need to mobilize maximum manpower, organize overtime, increase shifts, and race against time to ensure progress.

Also according to Chairman of Lam Dong Provincial People's Committee Ho Van Muoi, the investor and local authorities need to regularly stick to the construction site, monitoring progress every hour, every day.

In which, priority is given to completing essential items such as dormitories, classrooms, then the campus, yards and auxiliary items. Any items that are completed will be accepted and handed over in a rolling manner to shorten the time.

Regarding mobilizing more human resources, localities and contractors need to proactively plan to arrange labor resources. Volunteers and students participating in construction support must be fully guaranteed food, accommodation and living conditions.

In parallel with the construction, the Chairman of the Provincial People's Committee requested the Department of Education and Training, the Department of Finance and localities to complete the procurement and gathering of school equipment before August 20 for installation immediately when the project is handed over. Units that cause equipment shortage will be responsible to provincial leaders.

In addition, schools, localities and socio-political organizations need to mobilize union members and youth to participate in environmental sanitation, renovate campuses, plant trees, create green - clean - beautiful landscapes, and be ready to welcome students into the new school year.

According to Decision No. 3317/QD-UBND of Lam Dong Provincial People's Committee, in the 2026 - 2027 school year, two schools are assigned to enroll students, including Thuan An Inter-level Boarding Primary and Secondary School (Thuan An commune) and Quang Truc Inter-level Boarding Primary and Secondary School (Quang Truc commune), with a total target of 1,770 students.

In which, Thuan An Inter-level Boarding Primary and Secondary School enrolls 870 students, organizing 30 classes; Quang Truc Inter-level Boarding Primary and Secondary School enrolls 900 students with 30 classes.

Phan Tuấn
RELATED NEWS

Lam Dong traffic police open road to rescue man with heart attack

|

Lam Dong - While patrolling on Ho Chi Minh Road, traffic police promptly paved the way and took a man with a myocardial infarction to the emergency room.

Processing and manufacturing industry plays a leading role in growth in Lam Dong

|

Lam Dong - In the first six months of 2026, the processing and manufacturing industry increased by 16.92%, continuing to be a driving force for growth, making an important contribution to the province's GRDP.

Thunderstorm clouds cover Ho Chi Minh City, thunderstorms will continue tonight

|

Widespread thunderstorms appeared in Ho Chi Minh City on the afternoon of July 25 and are forecast to continue to expand tonight.

China evacuates more than 20,000 people before Typhoon Noul makes landfall

|

China evacuated more than 20,000 people and temporarily suspended railway operations in the south as Typhoon Noul made landfall.

Vietnam speaks out about being imposed a new 12.5% tariff by the US

|

It is requested that the US fully assess the measures Vietnam has implemented to adjust the tax rates applied to Vietnamese goods.

Deploying the search and repatriation of martyrs' remains in Minh Duc commune, Dong Nai city

|

Dong Nai - General Phan Van Giang, Member of the Politburo, Deputy Prime Minister, Minister of National Defense attends the ceremony to deploy the search and repatriation of martyrs' remains.

Triệt xóa 4 vụ đánh bạc gần 86 tỉ đồng, Công an phường ở Lâm Đồng được thưởng nóng

Phúc Khánh |

Lâm Đồng - Công an phường Đông Gia Nghĩa được thưởng nóng 20 triệu đồng sau khi triệt xóa 4 vụ đánh bạc trên không gian mạng gần 86 tỉ đồng.

Lâm Đồng tháo dỡ công trình xây dựng trái phép trên đất công tại xã Quảng Sơn

Phúc Khánh |

Lâm Đồng - UBND xã Quảng Sơn tháo dỡ công trình xây dựng trái phép trên đất công do Nhà nước quản lý, xử lý lấn chiếm, lập lại trật tự quản lý đất đai.

Lam Dong traffic police open road to rescue man with heart attack

Phúc Khánh |

Lam Dong - While patrolling on Ho Chi Minh Road, traffic police promptly paved the way and took a man with a myocardial infarction to the emergency room.

Processing and manufacturing industry plays a leading role in growth in Lam Dong

Phúc Khánh |

Lam Dong - In the first six months of 2026, the processing and manufacturing industry increased by 16.92%, continuing to be a driving force for growth, making an important contribution to the province's GRDP.