Dien Bien focuses efforts to accelerate the progress of a series of inter-level school projects

THANH BÌNH |

Dien Bien - With only more than 2 months left until the new school year, the locality is focusing its efforts to complete the inter-level school projects in border communes in time.

According to the report of the Working Group of the Steering Committee for the implementation of the inter-level boarding school construction project of Dien Bien province, currently 5/9 schools started construction in 2025 are behind schedule, in the communes: Muong Nha, Na Bung, Quang Lam, Nua Ngam and Sin Thau.

The actual construction progress at these projects currently reaches from 53% to 59% of the volume.

Muong Nha Inter-level Boarding School with a total investment of 200 billion VND, reaching about 59%; Na Bung School 220 billion VND, reaching 53%; Nua Ngam School nearly 215 billion VND, reaching 53%; Sin Thau School 197 billion VND, reaching 54% and Quang Lam School 220 billion VND, reaching 55%.

Chủ tịch UBND tỉnh Điện Biên Lê Văn Lương kiểm tra tiến độ trường liên cấp tại xã Mường Nhà.
Chairman of Dien Bien Provincial People's Committee Le Van Luong inspects the progress of the inter-level school in Muong Nha commune. Photo: Ngoc Thuy

Accordingly, the reason for the slow progress is due to difficult construction conditions in the border highlands, strongly affected by fluctuations in construction material prices and increased labor costs (especially from March 2026).

The implementation process has seen problems arising that have not been fully assessed from the beginning. Typically, the landslide incident at the project in Muong Nha.

In addition, investing in a domestic water system due to being far from water sources, costly and causing problems for people in Na Bung and Nua Ngam.

Thời điểm hiện tại tổng nhân lực thi công tại dự án Trường Phổ thông nội trú liên cấp Tiểu học và Trung học cơ sở tại xã Quảng Lâm là 327 lao động
The inter-level school project in Quang Lam commune has 327 workers working. Photo: Ngoc Thuy

In contrast, 4 projects started in 2025 in Thanh Nua, Thanh Yen, Nam Ke, Sam Mun communes still closely followed or exceeded the plan. In which, the project in Thanh Nua has completed over 80% of the construction volume.

With only more than 2 months left until the new school year, and to prevent projects from being delayed and preventing waste of resources, leaders of Dien Bien Provincial People's Committee directly "shared the spearhead" to inspect the reality and grasp the situation in order to complete it before August 30.

Đoàn công tác xem phối cảnh tổng thể nhà công vụ Trường Phổ thông nội trú liên cấp Tiểu học và Trung học cơ sở xã Quảng Lâm
Vice Chairman of the Provincial People's Committee Nguyen Van Doat (3rd from right to left) inspects the progress of the inter-level school in Quang Lam commune. Photo: Ngoc Thuy

On June 11, Chairman of the Provincial People's Committee Le Van Luong inspected the progress in Muong Nha, Nua Ngam and Sam Mun communes. Vice Chairman Nguyen Van Doat was also present in Na Bung, Sin Thau, Quang Lam, Nam Ke communes to directly remove bottlenecks on June 14-15.

Here, Chairman of the Provincial People's Committee Le Van Luong requested contractors to focus maximum resources, develop appropriate construction plans in the rainy season, prioritize completing the roof for projects that have completed the body to ensure they can continue construction in unfavorable weather conditions.

Khối lượng thực hiện Trường Phổ thông nội trú liên cấp tiểu học và trung học cơ sở xã Núa Ngam đến thời điểm báo cáo dự án đạt khoảng 59%
Inter-level boarding primary and secondary school in Nua Ngam commune. Photo: Ngoc Thuy

Along with that, pay attention to investing in domestic water supply systems, ensuring living conditions for students and teachers when schools go into operation. Construction units need to improve their determination, rationally calculate priority items, accelerate progress, and strive to complete projects as soon as possible.

The Chairman of the Provincial People's Committee also requested localities to coordinate and mobilize human resources to support construction units during peak periods in the project implementation process.

Dien Bien province is currently implementing 15 projects to build Inter-level Boarding Primary and Secondary Schools in border communes, with a total investment of more than 3,550 billion VND.

Among these, the school project in Si Pa Phin commune was inaugurated at the end of January 2026. The remaining 9 projects started in 2025 are being focused on construction, and 5 projects started in 2026 are completing investment procedures.

THANH BÌNH
RELATED NEWS

Dien Bien rolls out the red carpet to welcome investors, many social housing projects are about to start construction

|

Dien Bien - Many social housing projects are being urgently completed with procedures and are expected to be grounded in early July.

Lai Chau is about to start construction of 6 multi-level schools in border communes

|

Lai Chau - On March 17, the Provincial People's Committee held a meeting to prepare for the groundbreaking ceremony of inter-level boarding schools in border communes.

Dien Bien assigns tasks to investors of 5 border multi-level school projects

|

Dien Bien - The Provincial People's Committee has just continued to assign the task of investors for 5 investment projects to build Inter-level Boarding Schools in 5 border communes.

Bad news

|

Mr. Tran Dinh Moc, born in 1940, is the father-in-law of comrade Phan Van Anh - former Vice President of the Vietnam General Confederation of Labor - passed away at 01:34 on June 16, 2026 (ie May 2, Binh Ngo year), at the age of 87.

Britain will supply enriched uranium to Ukraine

|

Britain will provide enriched uranium worth $280 million to support the operation of Ukraine's nuclear power plants in the next 2 years.

Ready to provide direct legal advice to thousands of workers and laborers

|

Many problems will be answered at the Legal Consulting Program organized by Lao Dong Newspaper, Vietnam Bar Federation and Ho Chi Minh City Labor Federation on June 21.

Dien Bien rolls out the red carpet to welcome investors, many social housing projects are about to start construction

THANH BÌNH |

Dien Bien - Many social housing projects are being urgently completed with procedures and are expected to be grounded in early July.

Lai Chau is about to start construction of 6 multi-level schools in border communes

QUANG ĐẠT |

Lai Chau - On March 17, the Provincial People's Committee held a meeting to prepare for the groundbreaking ceremony of inter-level boarding schools in border communes.

Dien Bien assigns tasks to investors of 5 border multi-level school projects

QUANG ĐẠT |

Dien Bien - The Provincial People's Committee has just continued to assign the task of investors for 5 investment projects to build Inter-level Boarding Schools in 5 border communes.