On July 26, Binh Duong Provincial Information Portal said that the leaders of the Provincial People's Committee had a meeting to hear reports on the situation and progress of implementing key traffic projects in the province.
Notably, for the 26km Ho Chi Minh City Ring Road 3 project through Binh Duong, 11km of construction has now been implemented, the remaining 15.3km of Binh Duong province is applying for investment policy.
This 15.3km section of Ring Road 3 of Ho Chi Minh City from Tan Van intersection to Binh Chuan intersection coincides with My Phuoc Tan Van street.
Regarding legal procedures, on June 17, the Standing Committee of the Binh Duong Provincial Party Committee agreed to invest in phase 1 to clear the land on one side and build a 4-lane elevated highway bridge. The investment method is public-private partnership (PPP) with a total expected investment capital of about 24,000 billion VND. Currently, the People's Committee of Binh Duong province has sent a document to report to the Prime Minister and the Ministry of Transport on this plan.
The People's Committee of Binh Duong province also has a document requesting the Ministry of Transport to complete the Tan Van intersection, invest in adding emergency stopping lanes to the highway, and invest in additional 2 parallel bridges at the bridge. Send Comment.
Speed up the progress of 4 construction and installation packages
For the construction of 4 construction packages nearly 11km long, currently construction package 1 (Tan Van intersection at Di An) has broken ground. The units are approaching the site, completing construction drawing design procedures and implementing construction and installation. The contractor is clearing and clearing the site and constructing test piles for pillars P11-P14 and pillar P38, abutment A2, and test piles for 2 canal overpasses.
Construction package 2 (Binh Chuan intersection in Thuan An city) has currently completed 23% of the contract volume.
Construction package 3 (section from Binh Chuan intersection to Binh Goi bridge) has been completed reaching about 6.81% of the contract volume.
Construction package 4 (building Binh Goi bridge across the Saigon River), currently the construction volume reaches 42% of the contract volume.
According to Binh Duong Department of Transport, currently the project has disbursed 1,131 billion VND, reaching 23.1% of the total estimate.
For the site clearance project, currently 122.4 hectares have been recovered, reaching about 95%. Localities have disbursed compensation of VND 6,752 billion.