Can Tho Secretary inspects progress of nearly 10 trillion VND expressway

TẠ QUANG |

Can Tho - On October 25, Secretary of the Can Tho City Party Committee Nguyen Van Hieu inspected the construction progress of the Chau Doc - Can Tho - Soc Trang expressway, the section passing through the city.

At the inspection, Secretary of Can Tho City Party Committee Nguyen Van Hieu requested the City People's Committee to direct investors, departments, branches, Land Fund Development Center and local authorities to closely coordinate to speed up the project's progress.

Bi thu Thanh uy Can Tho Nguyen Van Hieu dan dau doan cong tac kiem tra cao toc Chau Doc - Can Tho - Soc Trang, doan qua TP Can Tho. Anh: Ta Quang
Can Tho City Party Secretary Nguyen Van Hieu (6th from left) led a delegation to inspect the Chau Doc - Can Tho - Soc Trang expressway, the section passing through Can Tho City. Photo: Ta Quang

In the process of land acquisition and site clearance, it is necessary to have the consensus and support of local people, ensuring transparency, fairness, and compliance with legal regulations in decisions related to land acquisition, compensation and resettlement.

The Secretary of the Can Tho City Party Committee requested Co Do district to soon complete the recovery of an area of ​​17.9 hectares to build a rest stop, ensuring the overall progress of the entire project.

Emphasizing the planning and land use along the expressway, the Secretary of the Can Tho City Party Committee stated that it is necessary to implement it effectively, in conjunction with the development of transport infrastructure and economic activities. Urban planning and land use planning around important traffic intersections, making the most of the existing land fund to serve the socio-economic development of the locality, avoiding waste.

Bi thu Thanh uy Can Tho Nguyen Van Hieu cung doan cong tac tang qua cho cong nhan. Anh: Ta Quang
Can Tho City Party Secretary Nguyen Van Hieu (4th from left) and the delegation presented gifts to workers. Photo: Ta Quang

The Chau Doc - Can Tho - Soc Trang expressway project through Can Tho City, invested by the Can Tho City Construction Investment Project Management Board (CMBPM), has a total of 5 construction packages (including 4 construction packages and 1 traffic safety system construction package). The total value of the 4 main construction packages is over 13%.

According to the report, the total demand for sand for filling of component project 2 is about 7 million m3. Sand is supplied from mines in An Giang and Tien Giang provinces; of which, the volume of sand qualified for use for the expressway that An Giang can supply is about 2.3 - 2.4 million m3, and Tien Giang is about 2.62 million m3.

However, about 700,000m3 of sand in An Giang province has been transferred to the Can Tho - Ca Mau expressway. The total sand source that An Giang and Tien Giang provinces plan to provide for component 2 project is about 4.3 million m3. Thus, up to now, the Chau Doc - Can Tho - Soc Trang expressway project through Can Tho is still short of more than 1.92 million m3 of sand.

Du an cao toc Chau Doc - Can Tho - Soc Trang doan di qua dia ban TP Can Tho. Anh: Ta Quang
Chau Doc - Can Tho - Soc Trang expressway project, section passing through Can Tho city. Photo: Ta Quang

The investor proposed that the People's Committee of Tien Giang province continue to support the implementation of the next procedures to soon exploit sand materials at the mines. The investor also proposed that the People's Committee of An Giang province consider and support the return of the volume of 700,000m3 of sand transferred from Binh Phuoc Xuan mine to Can Tho city to ensure the source of materials for the project section through Can Tho city.

The total area that needs to be cleared for the entire project route is nearly 258.5 hectares with 1,055 households. To date, 1,015 households have handed over the land with an area of ​​about 240 hectares, reaching nearly 93% equivalent to more than 36.5km; of which, the cases located on the main expressway route have been handed over at 100%.

There is a rest stop on the route in Co Do district with an area of ​​nearly 17.9 hectares. In the construction of the rest stop, 40 households will be affected, and land acquisition is expected to be completed in November 2024.

The Chau Doc - Can Tho - Soc Trang Expressway Project Phase 1 is over 188km long, passing through 4 provinces/cities: An Giang, Can Tho, Hau Giang and Soc Trang. The scale of Phase 1 includes 4 lanes, designed speed of 100km/h. The total investment of the project is about 44,700 billion VND. Component 2 project is located in Can Tho, over 37km long, total investment of over 9,700 billion VND.

TẠ QUANG
TIN LIÊN QUAN

More than 13 billion VND to relocate the landfill blocking the Can Tho - Ca Mau highway

|

Can Tho - The cost of relocating the landfill blocking the Can Tho - Ca Mau expressway is 13.08 billion VND and will complete handover of 100% of the site before December 31.

Progress of nearly 10 trillion VND expressway through Can Tho

|

Can Tho - The Chau Doc - Can Tho - Soc Trang expressway project through Can Tho city has achieved 12.40% progress. 15.49% behind schedule, according to the plan, the progress is 27.89%.

Floating sea of ​​clouds on the roof of Tak Po in the middle of the mountains and forests of Quang Nam

|

Quang Nam - Not Hoi An or the famous My Son Sanctuary, Tak Po peak is a new tourist destination that attracts nature lovers.

People's Artist Chi Trung reveals the 3-generation family-run chicken pho restaurant in Hanoi

|

People's Artist Chi Trung revealed that his favorite pho restaurant on Hoa Ma Street, Hanoi, has quality chicken that is hard to find anywhere else. He likes to order chicken pho with less bread and extra fish balls.

4 good movies premiering in early November

|

Horror, thriller, and suspense films dominate theaters early this November.

Businesses in Da Nang take advantage of storms to dump waste and garbage

|

The Department of Natural Resources and Environment of Da Nang City said that many businesses located in the city have taken advantage of storms and rain to discharge waste and throw garbage into the environment.

Israel reels after series of missiles launched from Lebanon

|

A residential area in southern Israel was suddenly attacked by a series of rockets launched from Lebanon on November 2, injuring 11 people.

Vietnam team faces difficulties before AFF Cup 2024

|

The Vietnam team will not have any official friendly matches during FIFA Days in November, which will more or less affect the preparation plan for the AFF Cup 2024.

More than 13 billion VND to relocate the landfill blocking the Can Tho - Ca Mau highway

Tạ Quang |

Can Tho - The cost of relocating the landfill blocking the Can Tho - Ca Mau expressway is 13.08 billion VND and will complete handover of 100% of the site before December 31.

Progress of nearly 10 trillion VND expressway through Can Tho

Tạ Quang |

Can Tho - The Chau Doc - Can Tho - Soc Trang expressway project through Can Tho city has achieved 12.40% progress. 15.49% behind schedule, according to the plan, the progress is 27.89%.

Cao tốc Châu Đốc - Cần Thơ - Sóc Trăng đoạn qua Hậu Giang chậm tiến độ 44%

Tạ Quang |

Hậu Giang - Tính đến ngày 5.6.2024, tổng giá trị thực hiện dự án thành phần 3 thuộc dự án cao tốc Châu Đốc - Cần Thơ - Sóc Trăng giai đoạn 1 là 520 tỉ đồng/6.291,7 tỉ đồng, đạt 8,26% giá trị hợp đồng, chậm 44% so với kế hoạch.