Chau Doc - Can Tho - Soc Trang Expressway
Chairman of Can Tho directs sand mining for expressway, determined to replace weak contractors
|
Can Tho - Exploitation at sand mines serving the Chau Doc - Can Tho - Soc Trang expressway is slow, with output lower than the permitted capacity.
Morning in the West 4.9: Prosecution of 13 subjects for organizing drug use at karaoke bar in Phu Quoc
|
Morning in the West 4.9: Prosecution of 13 subjects for organizing drug use at karaoke bar in Phu Quoc; Chau Doc - Can Tho - Soc Trang Expressway Project is still not out of challenge
The Chau Doc - Can Tho - Soc Trang expressway project is still not out of challenges
|
Can Tho - According to the investor, the project's difficulties are due to erratic weather and scattered raw materials, mainly sand.
Morning in the West 2.9: All night, through the September 2 ceremony, Can Tho - Ca Mau Expressway is under construction
|
Morning in the West 2.9: Working all night, giving National Day gifts to people; Construction through the festival, determined to bring the Can Tho - Ca Mau expressway to the finish line on time;...
Construction without a day off at the Chau Doc - Can Tho - Soc Trang expressway construction site
|
Can Tho - On the occasion of the September 2 holiday, nearly 1,000 workers and 500 equipment are still working hard on the Chau Doc - Can Tho - Soc Trang expressway through the old Can Tho city.
Construction of a highway worth over VND27,000 billion in the West overnight, through the September 2 ceremony
|
Can Tho - Even during the National Day holiday on September 2, the Can Tho - Hau Giang expressway construction site is still brightly lit.
Two expressways worth over VND72,000 billion in the West are determined to finish on time
|
Can Tho - Two key expressways, Can Tho - Ca Mau and Chau Doc - Can Tho - Soc Trang, with a total investment of more than VND 72,000 billion, are being accelerated.
Chau Doc - Can Tho - Soc Trang Expressway adjusts design to make up for slow progress due to sand shortage
|
The Western region - Chau Doc - Can Tho - Soc Trang Expressway is currently only at 45% of the volume, the investor and contractor are studying to adjust the design to keep up with the schedule.
Shortening relocation time, speeding up construction progress of key projects in Can Tho
|
Can Tho - The City People's Committee assigned the Project Management Board and related units to urgently organize implementation based on the functions and tasks prescribed by law.
Accelerating the construction of bridges on the Chau Doc - Can Tho - Soc Trang Expressway
|
Can Tho - To date, 96 bridges on the Chau Doc - Can Tho - Soc Trang expressway section through Can Tho city have been constructed, many of which are about to be completed.
Lack of materials, contractors still strive to build bridges to keep up with the progress of the expressway
|
Can Tho - The entire Chau Doc - Can Tho - Soc Trang expressway has constructed 96/100 bridges, many bridges are about to be completed and open to traffic in August.
Morning in the West 5.8: The Western Expressway is still slow due to lack of sand
|
Morning in the West 5.8: Scene of a major fire that burned down 2 factories in Tay Ninh; The highway is still slow due to lack of sand, investors are looking for more construction solutions.
Chau Doc - Can Tho - Soc Trang Expressway still lacks nearly 7 million m3 of sand
|
Can Tho - The Chau Doc - Can Tho - Soc Trang expressway project, the section through Can Tho city, has reached more than 41.5% of the volume but is still behind schedule due to a shortage of nearly 7 million m3 of sand.
Not afraid of rain and wind, workers cling to the construction site of the Western Expressway
|
Can Tho - Heavy rain has interrupted the construction of the Chau Doc - Can Tho - Soc Trang expressway, but contractors are still taking advantage of the opportunity to speed up the progress.
The expressway is still slow due to lack of sand, investors are looking for more construction solutions
|
Can Tho - The expressway project is behind schedule due to lack of sand, the investor is urgently adding materials and adjusting construction solutions to keep up with the schedule.