Cao tốc Châu Đốc - Cần Thơ - Sóc Trăng

Progress of nearly 10 trillion VND expressway through Can Tho

Tạ Quang |

Can Tho - The Chau Doc - Can Tho - Soc Trang expressway project through Can Tho city has achieved 12.40% progress. 15.49% behind schedule, according to the plan, the progress is 27.89%.

Urgently add sand to the highway for more than 11,900 billion VND

PHƯƠNG ANH |

Soc Trang - 2 sand mines are being exploited to serve Component Project 4. However, the capacity is still low compared to the current sand shortage demand.

Soc Trang Chairman requests installation of GPS for sand suction and transportation ships

PHƯƠNG ANH |

The Chairman of the People's Committee of Soc Trang province proposed that it is necessary to install GPS tracking devices for transport ships and suction ships to manage sand mining activities.

Local people live a stable life when participating in highway construction

Tạ Quang - Yến Phương |

Can Tho - Chau Doc - Can Tho - Soc Trang Expressway passing through Can Tho City has created jobs for many local workers.

Away from home, workers work hard on highway construction during September 2nd holiday

TẠ QUANG - YẾN PHƯƠNG |

During the National Day holiday of September 2, many workers on the Chau Doc - Can Tho - Soc Trang expressway project (section through Can Tho ) are still working hard.

Peak 15 days and nights of highway construction

PHƯƠNG ANH |

Contractors constructing the Chau Doc - Can Tho - Soc Trang expressway are urgently competing for a 15-day peak to speed up progress.

Overcoming sun and rain on highway construction projects

PHƯƠNG ANH |

Construction contractors are accelerating the progress of implementing the Chau Doc - Can Tho - Soc Trang component 4 expressway project.

Nearly 1 million m3 of sand has returned to the horizontal highway section of Can Tho

Tạ Quang |

Chau Doc - Can Tho - Soc Trang Expressway (horizontal highway) passing through Can Tho, sand has returned to the construction site over 850,000m3.

Adding sand to highways costs more than 11,900 billion VND in the West

PHƯƠNG ANH |

Many sand mines were continuously started to serve Project Component 4 to help overcome the bottleneck of lack of filling materials.

Expressway progress is more than 9,700 billion VND passing through Can Tho

Tạ Quang |

Can Tho - Chau Doc - Can Tho - Soc Trang expressway project phase 1 is over 188km long, passing more than 37km through Can Tho, with a total investment of more than 9,700 billion VND reaching nearly 8%.

The workers do not eat at home all year round

PHƯƠNG ANH |

Hundreds of workers and engineers constructing the expressway project through Soc Trang province , most of whom are far from home. For them, the camp is their home, their colleagues are their brothers.

Highway Axis Cross-Country Sets Target to Achieve 20% Progress by End of 2024

Tạ Quang |

Can Tho - Since there is sand, highway from Châu Đốc to Can Tho to Sóc Trăng section in Can Tho has increased construction points to speed up the progress, striving to achieve 20% progress by 2024.

Engaging in highway construction projects, many individuals have stable income

Tạ Quang - Yến Phương |

Cần Thơ - Many local workers have stable lives when working on the highway of Cần Thơ - Cà Mau and the Châu Đốc - Cần Thơ - Sóc Trăng highway.

More than 700 thousand m3 of sand is transported to the Can Tho horizontal highway

Tạ Quang |

Can Tho - To date, more than 700 thousand m3 of sand has been delivered to the Chau Doc - Can Tho - Soc Trang expressway construction site (horizontal axis) in the Can Tho section.

Prime Minister inspected nearly 45,000 billion VND highway in the West

Tạ Quang |

On the morning of July 13, Prime Minister Pham Minh Chinh and his working group inspected the Chau Doc - Can Tho - Soc Trang expressway in Can Tho and Hau Giang.