Close-up of the bypass road costing over 80 billion VND/km in Tuyen Quang

Nguyễn Tùng |

Tuyen Quang - The Son Duong town bypass road is over 4km long, with a total investment of over 329 billion VND and is about to be completed.

The Son Duong town bypass and the construction of a bridge across the Pho Day River have a total length of more than 4km, with a total investment of over 329 billion VND, including site clearance (GPMB) and construction packages. The project is invested by the Department of Transport of Tuyen Quang province. Construction started in November 2021.

According to the reporter, on October 23, after 3 years of implementation, the project is almost completed. The entire length of the route has basically been paved with asphalt concrete, sidewalks have been paved, and auxiliary items such as lighting, signs, and lane markings are being implemented.

Currently, there are nearly 400m of road left at the end of the route due to hard rocky terrain, so the contractor is focusing on chiseling and breaking rocks to create a construction surface. Expected completion in October 2024.

Meanwhile, the Pho Day River overpass, the final section connecting to Km 188 National Highway 37, is also being re-constructed after more than a year of being suspended due to land clearance failure.

tuyen
Once completed, the route will avoid traffic congestion for people and vehicles passing through National Highway 37, Son Duong town, and open up new urban development space. Photo: Nguyen Tung.

Ms. Tran Thi Lien (Son Duong town), one of the households whose land was recovered for the project, said that after receiving compensation, her family rebuilt the house in a new location and has been living there for nearly half a year now.

"This is the first bypass of the town. Once completed, traffic will be convenient and our people will have the opportunity to trade and develop the economy," said Ms. Lien.

To implement the project, 17.8 hectares of land were acquired, spanning 9 residential groups of Son Duong town and 1 village of Tu Thinh commune with nearly 230 affected households.

Speaking to reporters, Mr. Bui Ngoc Van - Director of 27/7 Company, the construction contractor, said that according to the contract schedule, the project will be completed in November 2024. Currently, only the last section of the route is being cleared of rocks to create a flat surface.

"Because the final section of the route has complex terrain, the design of some items had to be adjusted and re-approved to suit the reality, so the construction was delayed. We are coordinating with the investor and relevant agencies to speed up this work," Mr. Van informed.

According to the investor, currently, the construction progress has reached over 90%, the problems in the project have been basically resolved, striving to complete and put the route into use by the end of 2024.

Some recorded images:

Diem dau tuyen duong tranh thi tran Son Duong giao cat voi Km183 QL37.
The starting point of the Son Duong town bypass intersects with Km183 of National Highway 37. Photo: Nguyen Tung.
Gan 4 km mat duong tren tuyen da duoc tham nhua.
Nearly 4km of road surface on the route has been paved. Photo: Nguyen Tung.
Cac hang muc phu tro dang tiep tuc duoc hoan thien
Auxiliary items continue to be completed. Photo: Nguyen Tung.
Mot so vi tri ta luy duong xung yeu, nguy co sat lo duoc gia co be mat.
Some landslide-prone slopes have their surfaces reinforced. Photo: Nguyen Tung.
Hon 400 m cuoi tuyen gap dia hinh da dan toi thi cong keo dai.
The last 400m of the route encountered rocky terrain, leading to prolonged construction. Photo: Nguyen Tung.
Cau vuot song Pho Day ket noi voi QL 37 tai Km188,
The 127m-long Pho Day River Overpass connects with National Highway 37 at Km188. This is also the largest construction item of the project with a value of over 50 billion VND. Photo: Nguyen Tung.
Mot khu tai dinh cu duoc xay dung canh tuyen duong cho 29 ho dan phai di chuyen cho o de thuc hien du an. Hien tai mot so ho da toi xay nha, on dinh cuoc song. Anh: Nguyen Tung.
A resettlement area was built next to the road for households who had to move to implement the project. Currently, some households have moved in to build houses and stabilize their lives. Photo: Nguyen Tung.

Nguyễn Tùng
RELATED NEWS

After inspection, many mineral violations were revealed in Tuyen Quang

|

The Ministry Inspectorate of Natural Resources and Environment has pointed out that dozens of mineral exploitation licenses in Tuyen Quang were granted without auction.

Lo River bank through Tuyen Quang eroded and devastated

|

Tuyen Quang - Many areas of fertile agricultural land in Cap Tien commune, Son Duong district are eroding every day into the Lo river, leaving farmers helpless.

Please extend the implementation of the bypass project in Quang Tri

|

QUANG TRI - The Eastern bypass project of Dong Ha city is at risk of falling behind schedule, so the locality has requested an extension of the implementation time and capital disbursement.

Ukraine suffers unpredictable consequences after a series of accusations from NATO countries against Russia

|

Ukraine could face further pressure if some NATO members do not make a concession and accuse Russia of allowing UAVs to violate airspace.

Accident on Phap Van - Cau Gie Expressway, limousine overturned, deformed

|

Ninh Binh - The accident on the Phap Van - Cau Gie Expressway caused the limousine to overturn and deform.

Viet Long Company announces will continue to exploit stone, despite objections

|

Lao Cai - Viet Long Company has just issued a document announcing that it will continue to exploit stone at Lieu Do 2 mine, although it has not reached an agreement with the people.

The Ministry of Education and Training proposes to teach Cambodian, Thai, and Indonesian languages to high school students

|

The Ministry of Education and Training proposes that from 2026, Vietnam will start teaching Lao, Cambodian, Thai, and Indonesian in schools in need.

Russian Minister of Health directly rescues passengers on a flight to Vietnam

|

Russian Health Minister Mikhail Murashko was praised for his timely actions to rescue a passenger while the plane was flying from Moscow to Hanoi.

After inspection, many mineral violations were revealed in Tuyen Quang

Việt Bắc |

The Ministry Inspectorate of Natural Resources and Environment has pointed out that dozens of mineral exploitation licenses in Tuyen Quang were granted without auction.

Lo River bank through Tuyen Quang eroded and devastated

Việt Bắc |

Tuyen Quang - Many areas of fertile agricultural land in Cap Tien commune, Son Duong district are eroding every day into the Lo river, leaving farmers helpless.

Please extend the implementation of the bypass project in Quang Tri

HƯNG THƠ |

QUANG TRI - The Eastern bypass project of Dong Ha city is at risk of falling behind schedule, so the locality has requested an extension of the implementation time and capital disbursement.