Preparing to demolish the remaining section of Phong Chau bridge

Tô Công |

Phu Tho - The remaining section of Phong Chau bridge at risk of collapse, mainly in Phung Nguyen commune, Lam Thao district, is being prepared to be demolished and cleared.

As reported, the remaining Phong Chau bridge section (mainly Phung Nguyen commune side, Lam Thao district), span N5 has tilted outwards towards the Red River (there are signs of subsidence at pier T6).

Bridge spans 4, 3, and 2 show signs of being twisted and tilted in the direction of the Red River's flow. The expansion joints (connecting bridge spans) are much wider than the original design.

Doan cau Phong Chau con lai phia xa Phung Nguyen, huyen Lam Thao. Anh chup ngay cau sap 9.9: To Cong.
The remaining section of Phong Chau bridge in Phung Nguyen commune, Lam Thao district. Photo taken on the day the bridge collapsed on September 9: To Cong

Given the above situation, to ensure the safety of people's lives and property, and to ensure the site for the construction of the new Phong Chau bridge, which is expected to start in December 2024, the remaining section of Phong Chau bridge must be demolished.

Mat bang xung quanh cau da duoc don dep de phuc vu cong tac pha do. Anh: To Cong.
The area around the bridge has been cleared for demolition work. Photo: To Cong

According to Lao Dong Newspaper reporters on November 18, the ground around the remaining Phong Chau bridge section in Phung Nguyen commune has been prepared.

Cac nhip gian thep cua doan cau Phong Chau con lai chuan bi duoc pha do. Anh: To Cong.
Spans 1-5 of the remaining Phong Chau bridge section are about to be demolished. Photo: To Cong

It can be seen that the functional units have set up fences, tarpaulins, and densely placed warning signs in the area, and at the same time mobilized a number of human resources and machinery to the scene...

Toan bo khu vuc duoc phong toa. Anh: To Cong.
The entire area was sealed off. Photo: To Cong

Recently, the Ministry of Transport requested to speed up the investment process of building Phong Chau bridge on National Highway 32C to ensure the quality and progress required by the Emergency Construction Order.

Doan cau Phong Chau con lai con nhieu hang muc can pha do nhu: Lan can cau, den, mat cau, dam thep, cau kien dam be tong cot thep, tru cau, mo cau... Anh: To Cong.
The remaining Phong Chau bridge section still has many items that need to be demolished such as: bridge railings, lights, bridge deck, steel beams, reinforced concrete beam structures, bridge piers, bridge abutments... Photo: To Cong

Regarding the dismantling of the old bridge, the Ministry of Transport (MOT) requested the Thang Long Project Management Board to proactively and actively coordinate closely with the Vietnam Road Administration; the Department of Transport of Phu Tho province to continue to complete the dismantling of the collapsed steel spans of the old bridge in accordance with the progress and construction measures of the new bridge according to the principle of simultaneous implementation while ensuring safety, without affecting the project progress.

Muc nuoc tai khu vuc cau Phong Chau dang xuong thap, con cat noi len giua song. Anh: To Cong.
Water levels at Phong Chau bridge are dropping, sand dunes are emerging under the old bridge section. Photo: To Cong

Recently, the Department of Transport of Phu Tho province and functional forces have dismantled and salvaged the structure of the collapsed Phong Chau bridge under the river. Up to now, span N7 of the bridge and many submerged vehicles have been brought to shore, and are currently continuing to handle span N6 in the middle of the river, about 50 meters downstream from the bridge.

Tô Công
TIN LIÊN QUAN

Additional 800 billion VND to build new Phong Chau bridge

|

Add 800 billion VND to the Ministry of Transport to implement the investment project to build the new Phong Chau bridge, the project must be completed by December 31, 2025 at the latest.

Sand dredgers arrive at Phong Chau bridge to assist in salvage

|

Phu Tho - Sand dredgers have been mobilized to serve the demolition and salvage of span N6 of Phong Chau bridge, which is submerged deep under layers of sand and alluvium.

People are looking forward to the construction of new Phong Chau and Tinh Cuong bridges

|

Phu Tho - The new Phong Chau Bridge and a bridge connecting Cam Khe district with Thanh Ba district are two projects that people hope will be built soon.

Russia arrests bomb maker for Ukrainian intelligence

|

The Russian Federal Security Service (FSB) has just arrested a suspect accused of making homemade bombs for the activities of the Ukrainian intelligence agency.

Ba Vi is congested from morning to afternoon, visitors flock to see wild sunflowers

|

Thousands of tourists go to Ba Vi National Park (Quoc Oai, Hanoi) to hunt clouds and see wild sunflowers blooming, causing serious traffic jams on weekends.

Yen rebounds after bottoming out

|

The Yen Recovers After a Sharp Fall, Thanks to Possible Japanese Government Intervention.

Educational innovation needs to change old habits and thinking

|

Minister Nguyen Kim Son said that to innovate education, we must change old habits, ways of thinking, ways of thinking and ways of doing things.

Finished meat prices climb despite pork prices falling

|

Pig prices today, November 18, fluctuated across the country, trading in the range of 60,000 - 63,000 VND/kg. Meanwhile, the price of finished meat products is at a high level.

Additional 800 billion VND to build new Phong Chau bridge

PHẠM ĐÔNG |

Add 800 billion VND to the Ministry of Transport to implement the investment project to build the new Phong Chau bridge, the project must be completed by December 31, 2025 at the latest.

Sand dredgers arrive at Phong Chau bridge to assist in salvage

Tô Công |

Phu Tho - Sand dredgers have been mobilized to serve the demolition and salvage of span N6 of Phong Chau bridge, which is submerged deep under layers of sand and alluvium.

People are looking forward to the construction of new Phong Chau and Tinh Cuong bridges

Tô Công |

Phu Tho - The new Phong Chau Bridge and a bridge connecting Cam Khe district with Thanh Ba district are two projects that people hope will be built soon.