Still stuck in land clearance for DT.719B project, Hon Lan - Tan Hai section

Duy Tuấn |

Binh Thuan - Site clearance faces many difficulties and obstacles affecting the progress of the DT.719B Coastal Axis project, Hon Lan - Tan Hai section.

The DT.719B Coastal Axis Project, Hon Lan - Tan Hai section, is 10.3 km long with a total investment of about 664 billion VND. The implementation period is 4 years and construction starts on December 15, 2022.

According to the Management Board of Traffic Construction Investment Projects, the DT.719B Coastal Axis project, Hon Lan - Tan Hai section, is being constructed on the handed over land area of ​​about 8.4 km out of a total of 10.3 km.

The current construction volume has reached about 30% of the contract. Of which, 2.1 km of the main road has been constructed, 0.7 km of the branch road is being cleared and the Phan River bridge has completed 1 bridge abutment and some bridge piers.

Thi cong du an Truc ven bien DT.719B doan Hon Lan - Tan Hai. Anh: Pham Duy
Construction of the DT.719B coastal axis project, Hon Lan - Tan Hai section. Photo: Pham Duy

During the construction process, the People's Committee of Binh Thuan province regularly inspected the project's progress and directed the urgent implementation of compensation and site clearance, speeding up the construction progress and disbursing public investment capital for the project.

According to the project management board, the site handover for construction has so far only reached 81.6%. Compensation and site clearance work still faces many difficulties and obstacles, and progress is slower than directed by the Provincial People's Committee.

Currently, localities are continuing to speed up the progress of compensation and site clearance to hand over the remaining sites. The Binh Thuan Provincial Traffic Construction Investment Project Management Board is continuing to coordinate with localities in compensation and site clearance.

Vuong giai phong mat bang khien cong tac thi cong gap nhieu kho khan. Anh: Pham Duy
Land clearance issues have made construction difficult. Photo: Pham Duy

At the same time, the committee directed the contractor to increase equipment, human resources, and gather construction materials to ensure construction is completed according to the signed contract deadline of May 3, 2025.

The DT.719B Coastal Axis Project, Hon Lan - Tan Hai section, when completed, will connect the DT.719B coastal axis and open up inter-regional traffic connections, opening up economic development opportunities, especially the tourism industry of Ham Thuan Nam, Ham Tan districts, La Gi town, forming the shortest route connecting Phan Thiet along National Highway 55 to Ba Ria - Vung Tau province.

Duy Tuấn
TIN LIÊN QUAN

Social housing project causes fever because it is as beautiful as a hotel

|

Bac Ninh - Cat Tuong Smart City social housing project (Yen Phong) is causing a stir online with images of interiors and amenities as luxurious as a hotel.

The current situation of titanium mines causes the DT.719B road project to stagnate

|

Binh Thuan - 3.8 km through the titanium mine that has not been cleared yet has caused the project to renew the coastal road DT.719B, Phan Thiet - Ke Ga section, to "standstill".

Planning a coastal road of nearly 15km through the center of Phan Thiet

|

Binh Thuan is planning a coastal route through the center of Phan Thiet city, nearly 15 km long, with a total investment of more than VND9,620 billion.

Heavy thunderstorms fall on Hanoi

|

Hanoi - On the afternoon of April 21, a thunderstorm suddenly fell on the capital.

A martyr unexpectedly returns to his hometown after 45 years of receiving a death certificate from his family

|

Thanh Hoa - After 45 years since his family received the death certificate, Mr. Long (66 years old) suddenly returned in the overwhelming joy of his family and neighbors.

Gold prices soar, buy 1 tael and have to wait a whole month to get your hands on it

|

On April 21, gold prices continued to increase. In Hanoi, people still find it difficult to buy gold. Some people have to wait a whole month to receive gold after placing an order.

Functional foods, COVID-19 testckets thrown everywhere on Hanoi streets

|

Hanoi - A large quantity of functional food boxes and COVID-19 testing kit and masks were thrown everywhere on the sidewalk of Nguyen Lan Street (Thanh Xuan District).

Revealing the most beautiful places to watch parades and parades on April 30 in Ho Chi Minh City

|

The 50th anniversary of the country's reunification has 48 groups of parades and parades, with about 13,000 participants. This is an event that many people and tourists are waiting for.

Social housing project causes fever because it is as beautiful as a hotel

Vân Trường - Đền Phú |

Bac Ninh - Cat Tuong Smart City social housing project (Yen Phong) is causing a stir online with images of interiors and amenities as luxurious as a hotel.

The current situation of titanium mines causes the DT.719B road project to stagnate

Duy Tuấn |

Binh Thuan - 3.8 km through the titanium mine that has not been cleared yet has caused the project to renew the coastal road DT.719B, Phan Thiet - Ke Ga section, to "standstill".

Planning a coastal road of nearly 15km through the center of Phan Thiet

Duy Tuấn |

Binh Thuan is planning a coastal route through the center of Phan Thiet city, nearly 15 km long, with a total investment of more than VND9,620 billion.