Da Nang accelerates the progress of key projects from the beginning of the new year

Hoàng Bin |

Da Nang Da Nang accelerates key projects right from the beginning of 2026, with the atmosphere of continuous construction on construction sites.

Decisive from the beginning of the year, completely removing bottlenecks

On the first day of 2026, Chairman of Da Nang City People's Committee Pham Duc An directly inspected the progress of the Van Ly bridge and access road project, along with the National Highway 14B intersection project with the Da Nang - Quang Ngai expressway. These are all key traffic projects, playing a regional connection role, having a long-term impact on the socio-economic development of the city.

Chu tich UBND thanh pho Pham Duc An kiem tra, don doc du an trong diem ngay dau nam moi 2026. Ảnh: Truong An
Chairman of the City People's Committee Pham Duc An inspects and urges key projects right at the beginning of the new year 2026. Photo: M.Quang

The Van Ly bridge project has a total investment of 575 billion VND, and has now reached about 54% of its value. The Thu Bon river overpass section has been completed, the lighting system has been installed synchronously; many access road sections are being accelerated, striving to pave asphalt concrete before the 2026 Binh Ngo Lunar New Year.

However, site clearance work still has some obstacles, especially in sections passing through Dai Loc and Dien Ban Tay communes. Directly directing at the construction site, Chairman of Da Nang City People's Committee emphasized:

This is a very important project, so units must focus highly, fundamentally and long-term remove difficulties, especially in site clearance and resettlement arrangement for people, ensuring compliance with legal regulations and creating social consensus.

Khong khi thi cong xuyen le tren cong truong du an cau Van Ly, Da Nang. Ảnh: Truong An
Perpetual construction atmosphere at the Van Ly bridge project construction site, Da Nang. Photo: Truong An

Infrastructure goes one step ahead, expanding development space

At the National Highway 14B intersection project with the Da Nang - Quang Ngai expressway, started at the end of December 2025 with an investment of more than 537 billion VND, contractors are urgently cleaning up the ground, constructing service roads, relocating technical infrastructure and organizing safe traffic diversion. The project is expected to be completed in mid-2027, contributing to solving the prolonged traffic unsafety situation at the western gateway of the city.

Assessing the role of dynamic transport projects, Mr. Nguyen Van Hoang - Chairman of Thang Truong Commune People's Committee - said: "When infrastructure is invested synchronously, regional connectivity will be much better. Reality shows that many investors have been and are coming to this area, creating more jobs, increasing income and improving people's lives.

Lanh dao Da Nang kiem tra du an KCN Nam Thang Binh va phoi canh du an. Ảnh: Truong An
Da Nang leaders inspect the Nam Thang Binh Industrial Park project and project perspective. Photo: Truong An

Along with dynamic transportation projects, at the end of December 2025, Da Nang started the Nam Thang Binh Industrial Park Project with a scale of 346ha, total investment of more than 3,373 billion VND. With the orientation of developing green industry, high-tech industry and environmentally friendly, the project is expected to become a new growth pole of the city's East.

According to representatives of local authorities, the groundbreaking ceremony of Nam Thang Binh Industrial Park not only expands the industrial development space, but also creates tens of thousands of jobs, contributing to economic restructuring and increasing budget revenue.

Chu tich UBND thanh pho Da Nang Pham Duc An tang qua, dong vien cong nhan thi cong du an cau Van Ly va nut giao Quoc lo 14B voi cao toc Da Nang - Quang Ngai. Ảnh: M.Quang
Chairman of Da Nang City People's Committee Pham Duc An presents gifts and encourages workers constructing Van Ly bridge and National Highway 14B intersection with Da Nang - Quang Ngai expressway. Photo: M.Quang

Not only transportation and industrial park development, Da Nang also focuses on investing in projects to improve the quality of living space. The project to renovate and upgrade 29 March Park with a total investment of nearly 673 billion VND is being urgently constructed. According to Mr. Truong Quoc Dung - Project Commander, contractors have proactively increased shifts and adjusted construction measures to overcome weather impacts and ensure overall progress.

We identify this as a project with long-term significance in terms of landscape, environment and urban quality of life, so we will make the highest efforts to complete it according to plan," Mr. Dung affirmed.

With wide development potential after the merger, along with the determination to accelerate public investment right from the beginning of the year, Da Nang is gradually completing infrastructure, unlocking resources and creating a solid foundation for sustainable growth in the new period.

Hoàng Bin
RELATED NEWS

Da Nang invites bidders to price the largest wholesale market land in the Central region

|

Da Nang - Da Nang Department of Agriculture and Environment has just invited consultants to determine the starting price of the Hoa Phuoc wholesale market project.

People protect forests and villages in the heart of Da Nang city

|

Trung Son hill forest in Lien Chieu ward, Da Nang city is likened to a green snail in the middle of an urban area, where people have preserved every piece of forest land for generations.

Rights when participating in electronic labor contracts of workers

|

The Government has just issued Decree 337/2025/ND-CP (effective from January 1, 2026) Regulating electronic labor contracts.

Bar owner speaks out about employee threatening to beat tourists at Nha Trang beach

|

Khanh Hoa - The bar owner has just spoken out about the incident of an employee threatening to beat a foreign tourist in the Nha Trang beach park area.

Venezuelan interim President warned by Trump

|

Mr. Trump warned that the Venezuelan interim President would have to "pay a very high price, even higher than Mr. Maduro", if he did not do the right thing.

PSG narrows the gap at the top of Ligue 1

|

In the early morning of January 5 (Vietnam time), Paris Saint-Germain (PSG) won 2-1 against Paris FC in round 17 of Ligue 1.

Man City drops victory over Chelsea in injury time

|

In the early morning of January 5 (Vietnam time), Man City shared points unfortunately with a score of 1-1 against Chelsea in the 20th round of the Premier League.

Medical staff in Nghe An have not received COVID-19 epidemic prevention allowance

|

Nghe An - Doctors and medical staff of Nghi Loc General Hospital propose not to receive epidemic prevention allowances according to Decree 05.

Da Nang invites bidders to price the largest wholesale market land in the Central region

Nguyễn Linh |

Da Nang - Da Nang Department of Agriculture and Environment has just invited consultants to determine the starting price of the Hoa Phuoc wholesale market project.

Tiến độ loạt dự án trọng điểm tại Tuyên Quang

Việt Bắc |

Tuyên Quang - Các dự án sau khi hoàn thành được kỳ vọng sẽ thúc đẩy sự phát triển kinh tế - xã hội của địa phương.

People protect forests and villages in the heart of Da Nang city

Thanh Huyền - Nhã Phương |

Trung Son hill forest in Lien Chieu ward, Da Nang city is likened to a green snail in the middle of an urban area, where people have preserved every piece of forest land for generations.