Quang Ngai's largest dam enters the trial run phase

ĐÔNG GIANG |

Quang Ngai - The Tra Khuc river downstream dam project with a total investment of nearly 1,500 billion VND is being organized for operation, trial run and synchronization of construction equipment.

The Tra Khuc River downstream dam project has a total investment of 1,498 billion VND. The project implementation period is from 2018 to 2025. The project is invested by the Quang Ngai Provincial Traffic Construction Investment Project Management Board.

Công trình có tổng chiều dài khoảng 1.400 m, trong đó phần cầu dài hơn 970 m. Ảnh: Đông Giang
The project has a total length of about 1,400 m, of which the bridge section is more than 970 m long. Photo: Dong Giang

The main item of the project is a river diversion culvert with 19 compartments, total width of nearly 720m; the bridge and combined road are nearly 1.3km long; along with a hydraulic valve gate system controlling opening and closing, fishing paths, bottom discharge, surface overflow and auxiliary items.

Đập dâng hạ lưu sông Trà Khúc là công trình thủy lợi kết hợp giao thông. Ảnh: Đông Giang
The downstream Dam of the Tra Khuc River is an irrigation and transportation project. Photo: Dong Giang

The project is built with the goal of raising water to create landscape, contributing to improving the environment for Quang Ngai city and surrounding areas. At the same time, the project contributes to limiting saltwater intrusion and exploiting land funds for urban development along the river.

On June 30, a representative of the investor said that to date, the Tra Khuc River downstream dam project has basically completed the traffic, irrigation, mechanical system, and electrical equipment items; and is organizing operation, trial run and synchronization of project equipment.

Đập dâng hạ lưu sông Trà Khúc chính thức thông xe dịp Tết Nguyên đán 2026, mở trục giao thông mới, tạo cú hích phát triển đô thị ven sông. Ảnh: Đông Giang
The road on the dam has been opened to traffic. Photo: Dong Giang

In the third quarter of 2026, the investor will invite the Department of Agriculture and Rural Development, the Department of Construction and local authorities to witness the operation, trial run, and synchronization of project equipment.

In addition, the investor will complete 100% of the remaining work items; organize the completion acceptance of the project, report on the completion acceptance work and coordinate with specialized departments to organize the completion acceptance of the project.

In the fourth quarter of 2026, the investor will hand over the project to the management and operation unit and implement project finalization.

Dự án hoàn thành sẽ hạn chế xâm nhập mặn và khai thác quỹ đất phát triển đô thị dọc sông. Ảnh: Đông Giang
The completed project will limit saltwater intrusion and exploit land funds for urban development along the river. Photo: Dong Giang

To avoid damage to trees and crops of households and individuals and to limit the occurrence of complaints and lawsuits when organizing the operation and water storage of the Tra Khuc River downstream dam project, the investor has proposed that the People's Committees of communes and wards: Truong Quang Trong, Cam Thanh, Nghia Lo and An Phu organize a review and soon terminate the term of land lease contracts (if any).

Cửa van được làm bằng tấm thép lớn, được điều khiển lên xuống bằng hệ thống thủy lực. Ảnh: Đông Giang
The valve door is made of large steel plates, controlled up and down by a hydraulic system. Photo: Dong Giang

Notice for households and individuals to proactively collect trees and crops being cultivated on alluvial land, along rivers in the upstream area of works managed by the People's Committees of communes and wards. Time to complete the collection of trees and crops before June 30, 2026.

ĐÔNG GIANG
RELATED NEWS

Opening to traffic of 1,498 billion VND dam project in Quang Ngai

|

Quang Ngai - Tra Khuc river downstream dam officially opens to traffic during Tet, opening a new traffic axis, creating a boost for riverside urban development.

Quang Ngai strives to complete the nearly 1,500 billion VND dam project by the end of 2025

|

Quang Ngai - Accelerate the construction of the Tra Khuc River downstream dam project with a total investment of nearly 1,500 billion VND, expected to be completed by the end of 2025.

The hundred-billion-dong dam in the border area will be completed on April 30

|

Cao Bang - The City People's Committee is aiming to complete the dam project in the city by April 30, 2025.

Supporting two grandmothers and grandchildren in Lai Chau to cross forests and escape streams to safe places

|

Lai Chau - A grandmother and grandchild living 3km from the central area on a forest road have been taken to a safe place by functional forces.

A nearly 3-year-old boy in critical condition after studying at an intervention facility

|

Thanh Hoa - After a class at an intervention facility, a nearly 3-year-old boy was found to have many serious injuries and had to be hospitalized in critical condition.

2026 World Cup Final: The battle of wits begins with personnel choices

|

Before the 2026 World Cup final, Luis de la Fuente and Lionel Scaloni both faced difficult personnel problems.

After organizing the civil servant exam, Cao Bang Department of Education and Training received instructions to reduce 596 staff positions

|

Cao Bang - The Department of Education and Training has a document requesting to temporarily suspend the recruitment of public employees in the Education sector due to a reduction of nearly 600 staff positions.

Opening to traffic of 1,498 billion VND dam project in Quang Ngai

VIÊN NGUYỄN |

Quang Ngai - Tra Khuc river downstream dam officially opens to traffic during Tet, opening a new traffic axis, creating a boost for riverside urban development.

Quang Ngai strives to complete the nearly 1,500 billion VND dam project by the end of 2025

VIÊN NGUYỄN - MỸ LINH |

Quang Ngai - Accelerate the construction of the Tra Khuc River downstream dam project with a total investment of nearly 1,500 billion VND, expected to be completed by the end of 2025.

The hundred-billion-dong dam in the border area will be completed on April 30

Tân Văn |

Cao Bang - The City People's Committee is aiming to complete the dam project in the city by April 30, 2025.