Accelerate the progress of deploying the nearly 9,500 billion VND coastal road in Lam Dong

Duy Tuấn |

Lam Dong - The coastal road project through Phan Thiet center is accelerating the implementation progress, completing many preparatory contents.

The coastal road project passing through Phu Thuy, Phan Thiet and Tien Thanh wards (Lam Dong province) is planned with a total length of about 14.6km.

The starting point connects to the roundabout of DT. 706B street in Phu Thuy ward, the ending point intersects with DT. 719 street in the Cambodian slope area, Tien Thanh ward.

Vị trí vòng xoay đầu đường ĐT.706B nhìn về trung tâm Phan Thiết, cũng là vị trí tính toán làm điểm đầu của tuyến đường ven biển. Ảnh: Duy Tuấn
The position of the roundabout at the beginning of DT. 706B road facing the center of Phan Thiet, is also the location calculated as the starting point of the coastal road. Photo: Duy Tuan

According to the design plan, the road has a scale of 6 lanes for motorized vehicles, with synchronous sidewalks and medians. The project is expected to level a part of the sea surface area to build the road.

In addition, two overpasses across rivers are oriented to be built according to modern cable-stayed bridge architecture. The total investment of the entire project is estimated at nearly 9,500 billion VND.

On March 24, Mr. Nguyen Thanh Hien - Deputy Director of Construction Investment Project Management Board No. 2 of Lam Dong province said that so far many contents prepared for the project have been completed, creating a basis for early submission to competent authorities for consideration and decision on investment policies.

Pre-feasibility study report preparation achieved clear results. The unit has selected a survey consulting contractor, completed the survey volume and built a complete pre-feasibility study dossier.

Notably, through researching the exploitation plan of the land fund formed from the project, the revenue generated is assessed as positive. After deducting infrastructure investment costs, revenue from the land fund may reach more than 16,000 billion VND.

This not only contributes to financial balance but also promotes urban embellishment, synchronous development of housing and commercial services along the route.

Vị trí tuyến đường ven biển dự kiến sẽ đi qua. Ảnh: Duy Tuấn
A location along the coast in Phu Thuy ward, Lam Dong province. Photo: Duy Tuan

Regarding the organization of implementation, the Project Management Board has proposed to divide the project into 2 construction packages to speed up the construction progress. The investment phasing plan is calculated appropriately, expected to shorten the implementation time and put the project into operation soon.

Along with that, the preparation of construction material sources is also specifically calculated. Functional agencies have preliminarily identified the number of affected households, and at the same time proposed suitable resettlement areas to serve site clearance work.

Phó Chủ tịch UBND tỉnh Lâm Đồng Nguyễn Hồng Hải khảo sát thực địa dự án tuyến đường ven biển, yêu cầu các đơn vị đẩy nhanh triển khai các thủ tục. Ảnh: Duy Tuấn
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai surveys the site of the coastal road project, requesting units to accelerate the implementation of procedures. Photo: Duy Tuan

Through actual inspection and working with departments, branches, localities and investors, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai emphasized that the project received many expectations from the people. Provincial leaders assigned the Department of Finance to preside over the appraisal of investor capacity and advise the Provincial People's Committee to consider and decide.

At the same time, relevant units are required to complete supplementary planning and coordinate to accelerate the implementation of necessary procedures.

Investors are required to proactively work with the Department of Finance, Department of Construction and related agencies to implement the next steps immediately after the project is approved for investment policy.

Duy Tuấn
RELATED NEWS

Resettlement for people in disaster-stricken areas, accelerating progress and quality

|

Gia Lai - Resettlement for people needs to accelerate procedures, and construction needs to be quality and sustainable.

Hanoi removes site bottlenecks, accelerates traffic congestion prevention projects

|

Hanoi drastically clears ground, focuses resources on accelerating key traffic projects, reducing congestion and improving traffic in the Southern region.

Inspecting old apartment buildings, accelerating the process of urban reconstruction

|

Hanoi and Ho Chi Minh City are accelerating the inspection of thousands of old apartment buildings to assess safety, as a basis for renovation and reconstruction, gradually promoting the process of urban reconstruction.

Hai Phong Trade Union intervenes after workers' reflections on overtime

|

Hai Phong - In the afternoon of March 24, Hai Phong City Labor Federation worked with businesses after workers' reflections on working overtime on Sundays.

Vietnamese men's football and new hopes

|

A series of titles and promotion in the rankings once again bring many hopes for Vietnamese men's football in the near future.

The Vietnam Register speaks out about the proposal to abolish the exhaust gas test method

|

On March 24, the Vietnam Register spoke out about the proposal to abolish the method of pedaling the entire accelerator when checking emissions of some cars.

Fire burns down many properties inside a pub in Da Lat

|

Lam Dong - The fire that occurred at noon burned down many properties at a pub in Lam Vien ward - Da Lat, fortunately there were no casualties.

Hanoi is about to open for sale 254 social housing units in phase 1, priced from 14.9 million VND/m2

|

Hanoi - The Department of Construction has just announced a plan to receive applications to buy 254 social housing units (rented units for sale) at buildings N04, N05 of the Ecohome 3 project (phase 1).

Resettlement for people in disaster-stricken areas, accelerating progress and quality

THANH TUẤN |

Gia Lai - Resettlement for people needs to accelerate procedures, and construction needs to be quality and sustainable.

Hanoi removes site bottlenecks, accelerates traffic congestion prevention projects

Minh Hạnh |

Hanoi drastically clears ground, focuses resources on accelerating key traffic projects, reducing congestion and improving traffic in the Southern region.

Inspecting old apartment buildings, accelerating the process of urban reconstruction

Linh Trang - Gia Miêu |

Hanoi and Ho Chi Minh City are accelerating the inspection of thousands of old apartment buildings to assess safety, as a basis for renovation and reconstruction, gradually promoting the process of urban reconstruction.