National Assembly working group inspects the progress of Can Tho - Ca Mau expressway project

TẠ QUANG |

Can Tho - With a construction output of more than 74%, the Can Tho - Ca Mau expressway project is accelerating, to reach the finish line on schedule on December 19, 2025.

On the afternoon of August 21, the working group of the National Assembly's Economic and Financial Committee had a field inspection of the progress of the Can Tho - Ca Mau expressway project, the section passing through Vi Thuy commune, Can Tho city.

Reporting to the working group, Mr. Phan Duy Lai - Deputy Director of My Thuan Project Management Board - said that up to now, the construction output of the Can Tho - Ca Mau expressway project has reached more than 74% of the plan. Contractors have unloaded more than 28km; asphalt concrete pavement has been paved for more than 10km.

Of the 95 bridges on the main route, 90 have been completed, the remaining bridges are expected to complete the bridge deck in August 2025.

Anh: Ta Quang
Mr. Phan Duy Lai - Deputy Director of My Thuan Project Management Board - reported on the project progress. Photo: Ta Quang

To ensure progress, the units are deploying human resources to work in "3 shifts, 4 teams", determined to complete the entire project by December 19, 2025 according to the direction of the Government.

"For the two rest stops under the project, the rest stop in Can Tho City with a scale of more than 6 hectares has been opened for bidding and is implementing an investor selection assessment. The remaining station in An Giang province has a scale of about 3 hectares, the Board has submitted to the Vietnam Road Administration for approval of the investor selection results, said Mr. Lai.

Anh: Ta Quang
The Can Tho - Ca Mau expressway construction project is 110.85km long. Photo: Ta Quang

Regarding the material source, Mr. Nguyen The Minh - Deputy Director of the Department of Economics - Construction Investment Management - informed that the source of sand and stone materials has been mobilized enough, ensuring service for the project to reach the finish line on schedule.

However, for major intersections such as IC5, IC10, IC12... on the route, due to high traffic volume, it will be completed on December 19. For the remaining intersections, the overall unloading and construction will take place after October 2025 and is expected to be completed in June 2026.

After listening to the report, Mr. Nguyen Minh Son - Deputy Chairman of the National Assembly's Economic and Financial Committee - encouraged the units to soon complete the project on December 19 as requested by the Government. At the same time, he also interested in discussing the implementation progress and construction locations of infrastructure related to expressways such as toll stations and stopping stations on the route.

The Can Tho - Ca Mau expressway construction project is 110.85km long, divided into 2 component projects: Can Tho - Hau Giang section and Hau Giang - Ca Mau section. The total investment of the project is VND 27,523 billion, started on January 1, 2023, and is scheduled to be completed in December 2025.

Can Tho - Ca Mau Expressway is the final project of the North - South Eastern Expressway Phase II, expected to close the "new threshold" along the area, connecting within the region and inter-regional areas, promoting the economic and social development of the entire Southwest region.

TẠ QUANG
RELATED NEWS

Remove obstacles to soon start upgrading 7km of National Highway 91 in Can Tho

|

Can Tho - Up to now, the National Highway 91 Upgrade and Expansion Project (section from Km0-Km7) has paid compensation to 45/121 affected cases in Cai Khe ward.

More than 2,100 Can Tho - Ca Mau Expressway construction personnel on completion days

|

Can Tho - Despite unfavorable weather, more than 2,100 employees at the Can Tho - Ca Mau expressway construction site are still working hard.

Despite bad weather, the Can Tho - Ca Mau expressway construction site is still bustling

|

Can Tho - engineers and workers working tirelessly on the Can Tho - Ca Mau expressway, even taking advantage of the rain to roll the roadbed.

Forecast of the time when the low pressure area will enter the East Sea and strengthen, causing bad weather

|

According to the meteorological agency, in the next 24-36 hours, the low pressure area in the eastern Philippines is forecast to enter the East Sea and is likely to strengthen into a tropical depression.

Western tourists are excited to watch the 2.9 parade with the people

|

Foreign tourists eagerly watched the parade and parade before the 80th anniversary of National Day on September 2.

President Zelensky sets out conditions to meet President Putin

|

Ukrainian President Volodymyr Zelensky said his meeting with President Vladimir Putin could take place after security guarantees are agreed upon.

Dismantling a virtual currency capital mobilization ring that appropriated more than 200 billion VND

|

Hanoi City Police have just dismantled a group of subjects mobilizing virtual currency capital, appropriating about 200 billion VND from more than 3,000 investors.

Air Force squadron practices parade in Hanoi sky

|

This morning (8.21), the air force of Mi-17 and L-39NG helicopters practiced parading in the sky of Hanoi.

Remove obstacles to soon start upgrading 7km of National Highway 91 in Can Tho

TẠ QUANG |

Can Tho - Up to now, the National Highway 91 Upgrade and Expansion Project (section from Km0-Km7) has paid compensation to 45/121 affected cases in Cai Khe ward.

More than 2,100 Can Tho - Ca Mau Expressway construction personnel on completion days

Tạ Quang |

Can Tho - Despite unfavorable weather, more than 2,100 employees at the Can Tho - Ca Mau expressway construction site are still working hard.

Despite bad weather, the Can Tho - Ca Mau expressway construction site is still bustling

Tạ Quang |

Can Tho - engineers and workers working tirelessly on the Can Tho - Ca Mau expressway, even taking advantage of the rain to roll the roadbed.