The 3,800 billion VND traffic project is "put on hold", people are tired of waiting

Mai Dung |

For more than a year now, the investment project to build a coastal road through Hai Phong City and Thai Binh province has been under construction and had to be "covered", causing traffic and people's activities to be affected.

The reason for the project is left open

Investment project to build a coastal road section through Hai Phong city and 9km in Thai Binh province in the form of public-private partnership with the starting point at the intersection of provincial road 353 at Dong Neo junction area (km11 +800 provincial road 353) in Do Son district, Hai Phong; The end point on the new National Highway 37 connects with the section of the coastal road project through Thai Binh province, in Thai Thuy district. Total length of the route is 29.7km, of which the section passing through Hai Phong is 20.782km; The section through Thai Binh province is 8,925km. Total investment capital of the project is 3,758,600 million VND from BOT capital and State capital.

Started in 2017, expected to be completed in 2019, but after many extensions, up to now, the project is still not completed and has been "under construction" for more than a year.

Latest information from Hai Phong City Traffic Construction Investment Project Management Board (management of coastal road expansion investment project), the completed volume value is about 72.11% of the price. contract value. Among them, many basic items have been completed such as Lach Throat bridge and Van Uc bridge. As for Van Uc bridge, it was completed in May 2023 but has not yet been put into use.

According to a representative of the Project Management Board, the objective reasons are due to the scarcity of construction materials supply, the "storm" in prices of main materials, difficulties in recruitment and fluctuations in labor costs. Along with that, the project has problems related to the ability to continue to mobilize loan capital because the actual loan interest rate is significantly different from the interest rate specified in the signed contract, leading to difficulties for investors. difficulties in continuing to implement the remaining items of the signed contract.

The People's Committee of Hai Phong City has issued a written report and requested the Prime Minister to agree in principle on adjusting the project's BOT Contract loan interest rate and is awaiting central direction.

The Hai Phong - Thai Binh coastal road project is being implemented slowly, affecting people's lives. Photo: Hoang Khoi
The Hai Phong - Thai Binh coastal road project is being implemented slowly, affecting people's lives. Photo: Hoang Khoi

People are tired of waiting

The project was "covered up" and had a significant impact on people's lives, especially people in Minh Duc ward, Do Son district.

Talking to Labor, Mr. Nguyen Manh Ninh - Vice Chairman of Minh Duc Ward People's Committee - said: The 2.9km coastal road project is located in Minh Duc ward, passing through 5 residential groups: Nguyen Hue, Quang Trung, Ngo Quyen, De Tham and Dan Tien. The route is expected to be a lifeline for economic development of both Do Son district as well as Minh Duc ward. Therefore, as soon as the project was implemented, the local government actively implemented it, the people supported it, and completed site clearance in mid-2020, basically on schedule.

However, after handing over the site, the construction project was slower than planned. Up to now, the section passing through Minh Duc ward still has many unfinished items such as street lights, curbs, and sidewalks.

“At the end of 2022, early 2023, the project stopped construction, contractors withdrew machinery and equipment. The project has been going on for many years, but now it has temporarily stopped implementation, making people frustrated and making many petitions" - a representative of the Ward People's Committee said.

Not only that, the road is not complete, but many people travel, leading to many unfortunate traffic accidents. We must mention the accident on July 1, 2023 that left one shift worker dead and another injured. Immediately after this accident, the investor and local authorities barricaded the intersection with Pham Van Dong street in the ward with large concrete panels.

Recently, on July 18, forces continued to stretch ropes and barricade the route. However, in reality there is still a situation where some workers and people ride motorbikes across the unfinished route.

"The government and people of Minh Duc ward are looking forward to the project soon removing difficulties, continuing construction and soon putting into use, meeting the people's travel needs" - Vice Chairman of Ward People's Committee Nguyen Manh Ninh share.

Mai Dung
TIN LIÊN QUAN

3 dự án giao thông 2.670 tỉ đồng ở Đồng Nai sắp hết niên độ

HÀ ANH CHIẾN |

Đồng Nai - 3 dự án Đường trục trung tâm TP Biên Hòa, Hương lộ 2 và cầu Vàm Cái Sứt (có tổng mức đầu tư 2.670 tỉ đồng) sắp hết niên độ.

Dân chưa đồng thuận, dự án giao thông ở Quảng Ngãi gặp khó

VIÊN NGUYỄN |

Quảng Ngãi - Cho rằng phương án bồi thường chưa thoả đáng, nhiều người dân không bàn giao mặt bằng để thi công các dự án giao thông.

Gỡ khó cho địa phương cấp phép khai thác cát cho dự án giao thông trọng điểm

Thành Nhân |

Sau khi Phó Thủ tướng Chính phủ Trần Hồng Hà chỉ đạo làm việc tại Bến Tre, Tổ công tác liên ngành đã vào làm việc với 2 địa phương Bến Tre và Tiền Giang để tháo gỡ các vướng mắc, khó khăn của địa phương trong việc cung cấp cát cho các dự án giao thông trọng điểm khu vực phía Nam.

Vụ công trình làm nứt nhà dân ở Hà Nội, chính quyền nói gì?

NHÓM PV |

Theo chính quyền phường Quang Trung, hình ảnh công nhân đang làm việc tại công trình số nhà 19, ngõ 136/98 Tây Sơn là để hút nước phòng dịch sốt xuất huyết.

Triều Tiên cho nổ tung tuyến đường bộ nối với Hàn Quốc

Khánh Minh |

Triều Tiên cho nổ tung các tuyến đường nối với Hàn Quốc vốn từng được coi là biểu tượng của sự hợp tác liên Triều.

Thân tín của bà trùm ma túy Oanh "Hà" được trả công 15 tỉ

Việt Dũng |

Trong số hơn 626kg ma túy mua bán xuyên quốc gia do bà trùm Oanh "Hà" cầm đầu, Nguyễn Văn Nam có mặt hầu hết ở các chuyến hàng, nhận công hậu hĩnh.

Bất cập tiền công đức 2 đền ở Ninh Bình do nguồn thu quá lớn

NGUYỄN TRƯỜNG |

Ninh Bình - Những tồn tại, bất cập trong việc quản lý tiền công đức tại đền Dâu và đền Quán Cháo (thành phố Tam Điệp) là do nguồn thu quá lớn.

Chánh văn phòng hãng luật bị tố đe dọa, xúc phạm phụ nữ

TRÍ MINH |

Một chánh văn phòng hãng luật bị tố cáo có hành vi đe dọa, xúc phạm danh dự, nhân phẩm phụ nữ. Người dân đã trình báo sự việc tới cơ quan công an.