Road connecting the Northern mountainous provinces is being constructed slowly

Nhóm PV |

Yen Bai - Every time it rains, people in Van Chan district suffer and travel on the route connecting the northern mountainous provinces.

Unfinished construction, lack of warning signs

The project connects traffic in the northern mountainous provinces with a total investment of more than VND6,000 billion to shorten the journey from the political and economic centers of Lai Chau, Lao Cai, Yen Bai and other related localities to Hanoi.

The project consists of 2 routes. Of which, the route connecting Nghia Lo (Yen Bai) with Noi Bai - Lao Cai Expressway is about 53km long, expected to be implemented in 5 years (from 2019-2024).

Du an thi cong i ach khien nguoi dan di lai kho khan. Anh: Bao Nguyen
The project connecting the northern mountainous provinces is being constructed slowly, making it difficult for people to travel. Photo: Bao Nguyen

According to the reporter of Lao Dong Newspaper, the section through Van Chan district (under the XL-11) package constructed by Dong Do Group Joint Stock Company, although it is too ahead of schedule, has only completed a part of the volume.

Along the route, many construction sites are unfinished, lacking warning signs in dangerous areas, posing a potential risk to the safety of people and vehicles passing by.

Recorded by Lao Dong Newspaper reporters at the XL-11 package of the Northern Mountainous Province Traffic Connection Project.

Teacher Ly Thi Thuy Tien (working at An Luong Kindergarten) said: "From my house to the road through Suoi Quyen commune, there is a section of dirt road that is very difficult to travel and often landslides. Many other sections have rocks and deep holes that often cause people to fall and break their legs. On muddy days, teachers have to leave their vehicles on the road many times, walking 3-4km to get to class.

Nhieu doan thieu bien canh bao nguy hiem, vat lieu ngon ngang, gay kho khan cho nguoi dan di lai
Many sections lack warning signs of danger and scattered materials. Photo: Bao Nguyen

Fatal work accident during construction

According to local people, the project's delay and prolongation have greatly affected people's travel.

Many sections have landslides on one side, and on the other side are embankments but lack markers and warning signs to create traps for traffic participants, especially at night.

Chiec xe tai bi sa lay nhung khong nhan duoc su ho tro cua don vi thi cong khien giao thong tren tuyen anh huong
A local truck was muddy and stranded on June 5. Photo: Bao Nguyen

Not to mention, there are also frequent work accidents during the construction process. Mr. Dang Kim Ly - Chairman of Suoi Quyen Commune People's Committee - said: Most recently, at around 1:00 p.m. on May 9, Mr. L.T.S was driving an excavator to build a road (the construction section of Dong Do Group Joint Stock Company) when he was suddenly hit by a large rock falling from above.

As a result, the excavator was severely damaged in the front and Mr. S died tragically.

Den nay du an chua hoan thanh 50% khoi luong.
To date, the project has not completed 50% of the volume. Photo: Bao Nguyen

Through the survey, many items such as box culverts, embankments to prevent landslides along the road have signs of poor quality construction, peeling and cracking...

Some sections of the contractor used cement for patching; many box culverts that did not ensure quality were still put into construction.

Nhieu cau kien be tong co dau hieu khong dam bao chat luong, bi bong troc, ro to ong va nut vo.
Many concrete components show signs of poor quality, peeling, holes in beehives and cracking. Photo: Bao Nguyen
Trong long cong hop thoat nuoc, be tong nut vo duoc nha thau tram va lai.
Inside the drainage box culvert, the broken concrete was patched by the contractor. Photo: Bao Nguyen

On June 7, speaking with Lao Dong, Mr. Tran Nhat Phong, Deputy Director of Project Management Board 2, Ministry of Construction (representative of the investor said that up to now, the XL-11 package (due to 3 joint ventures) has only completed 40% of the construction and has extended the progress to June 2026.

Regarding the case of a worker who died in a work accident, immediately after receiving the information, the unit coordinated with the authorities and local authorities to be present at the scene to clarify the cause.

At the same time, direct contractors to strictly comply with regulations on labor safety, carefully inspect the terrain, processes, and machinery before implementing the work.

Dat da thi cong du an khong duoc thanh thai dan den chay tran lan ra long suoi. Anh: Van Duc
The project's construction soil and rock are not cleared, leading to overflowing into the stream bed. Photo: Van Duc

According to the Deputy Director of Project Management Board 2, due to the difficult terrain of the area and the slow site clearance work, the construction progress has not met the requirements.

Regarding the reflections of reporters at the section constructed by Dong Do Group Joint Stock Company, Mr. Tran Nhat Phong said that he will urge the supervision consultant and contractor to rectify and overcome them.

Dong Do Group Joint Stock Company is located at Thang Long Ecological Area, Dong Son Commune, Chuong My District, Hanoi City, with Mr. Pham Duc Thang as Chairman of the Board of Directors and General Director.

Since 2015, this enterprise has participated in the construction of 43 packages with a total winning bid capital of more than VND 5,740 billion (of which the independent role is more than VND 355 billion; the joint venture role is more than VND 5,380 billion).

At Project Management Board 2 alone, Dong Do Group Joint Stock Company won 3 bid packages with a total capital of more than 1,300 billion VND, including the following projects: Construction of the section Km38+252 - Km 54+069 of the Nghia Lo connecting route; Project to renovate and upgrade National Highway 19, section Km90-Km108 in Gia Lai province; Construction of the An Khe bypass.

Nhóm PV
RELATED NEWS

sad news

|

Mr. Ngo Duy Son, born in 2013, passed away at 1:45 p.m. on December 10, 2025 (ie October 21, At Ty year), at the age of 93.

The role of the Vietnam Fatherland Front in the market economy and international integration in the current period

|

On December 10, in Hanoi, the Standing Committee of the Central Committee of the Vietnam Fatherland Front organized a scientific workshop on "New factors of market economy and international integration affecting the gathering work, promoting the strength of national solidarity and the role of the Vietnam Fatherland Front in implementing a market economy in our country".

SEA Games 33 Medal Schedule on December 10: Vietnam temporarily ranked 4th

|

Updated the total score for the 33rd SEA Games medal table after the end of the competition on December 10.

Image processing process of AI cameras is about to spread in Hanoi

|

Hanoi - The City Police are about to put into operation more than 1,800 AI cameras, installed at nearly 200 intersections in the area.

Hour 9: Divorced but still living together - Part 1

|

Hour 9 No. 180 - Postpartum depression, the pressure to take care of 2 young children makes the wife exhausted. Too stuck, she filed for divorce. Can this marriage be saved?

Unusual stem cell liposuction service at Chang Cosmetic Clinic

|

Many promotional videos of AI claiming to be doctors, along with strange activities at the CW Endocrinology and Aesthetics Institute (Chang Cosmetic Clinic) performing absorbed stem cell services.

Nhiều dấu hiệu kém chất lượng tại dự án kè chống lũ ở Yên Bái

Nhóm PV |

Yên Bái - Trong quá trình xây dựng, nhiều hạng mục của Dự án xây dựng kè chống lũ suối Cầu Dài thi công sai thiết kế và sử dụng vật tư không đảm bảo chất lượng.

Khắc phục bất cập tại dự án đường nghìn tỉ nối các tỉnh miền núi phía Bắc sau phản ánh của Báo Lao Động

LONG NGUYỄN - BẢO NGUYÊN |

Sau phản ánh của Báo Lao Động, Bộ Giao thông Vận tải đã yêu cầu đơn vị tư vấn giám sát và nhà thầu khắc phục những bất cập trong quá trình thi công Dự án giao thông miền núi phía Bắc qua địa bàn tỉnh Lai Châu.

Ngổn ngang tại dự án đường nghìn tỉ nối các tỉnh miền núi phía Bắc

Long Nguyễn - Bảo Nguyên |

Quá trình thi công Dự án giao thông miền núi phía Bắc qua địa bàn tỉnh Lai Châu không đảm bảo an toàn, gây nhiều phiền toái cho người tham gia giao thông.