Nguyen Tuan Street transforms after expansion, reducing traffic congestion in Thanh Xuan area

Hữu Vũ |

Hanoi - The project to renovate and expand Nguyen Tuan Street helps reduce traffic congestion, connect infrastructure, and create a new look for the city before the National Day celebration on September 2.

On August 14, according to Lao Dong, after a period of expansion, many important items of the Nguyen Tuan Street renovation project (Thanh Xuan Ward, Hanoi) have been completed, bringing a new look to the street that is considered a traffic "bottleneck".

Previously, Nguyen Tuan was always overloaded with vehicles due to high traffic volume, plus a series of offices and high-rise apartments growing densely on both sides of the road.

Duong Nguyen Tuan nhin tu tren cao. Anh: Dinh Thien
Nguyen Tuan Street seen from above. Photo: Dinh Thien

The narrow road surface causes frequent congestion during rush hour. However, after the site was cleared and expanded, the road became airy, vehicles no longer crowded, especially at a time when the capital was urgently preparing for the 80th Anniversary of the August Revolution and National Day on September 2.

According to observations, the construction unit has dismantled corrugated iron fences at many locations, conducted technical traffic opening, ensuring smooth traffic.

The road surface has been renewed, and part of the section from 162 Nguyen Tuan to the Nguyen Tuan - Nguyen Huy Tuong intersection has been paved with asphalt concrete.

Nhieu diem thi cong da duoc thao do rao chan. Anh: Dinh Thien
Many construction sites have had their barriers removed. Photo: Dinh Thien

Items such as sewers, stations for water supply and drainage systems, installation of communication pipes and lighting systems are still being implemented.

Mr. Dang Hoang Linh, Head of the Thanh Xuan Ward Infrastructure and Investment Project Management Board, said that the construction progress was adjusted from September 2025 to early 2026, expected to be completed in March 2026.

The main reason is the process of converting local governments at two levels, changing investors, processes and procedures for bidding, causing some packages to be slower than planned.

The site clearance work still has problems at 35A Nguyen Tuan, an old 2-storey apartment building with 6 households living there. Currently, because the specific land price has not been determined to calculate compensation when reclaiming, the handover of the site cannot be completed.

a
Most of the site has been handed over by the investor to the contractor for construction. Photo: Dinh Thien

The Nguyen Tuan Street expansion project was approved by the People's Committee of the old Thanh Xuan District in 2018, with a total investment of nearly 400 billion VND. The road is 720m long, starting from Nguyen Trai intersection, ending at alley 162 Nguyen Tuan. The cross-section is expanded to 21m, of which the roadway is 15m, with sidewalks on both sides 3m.

Mot so vat lieu tap ket tren cong truong du an. Anh: Dinh Thien
Some materials gathered at the project site. Photo: Dinh Thien

To implement the project, the government has reclaimed and cleared 14,334m2 of land from 11 organizations and 160 households and individuals. However, many households did not agree to hand over the site, causing the project to stall for a long time.

It was not until November 2024, after many campaigns and mobilizations, that the liberation work was basically completed. Immediately afterwards, the local government directed the Construction Investment Project Management Board to coordinate with contractors to speed up the progress.

When completed, the expanded Nguyen Tuan route is expected to reduce traffic pressure on neighboring roads such as Le Van Luong and Nguyen Trai, while contributing to urban beautification, creating momentum for socio-economic development for Thanh Xuan area and Hanoi City.

Hữu Vũ
RELATED NEWS

Clearing a series of constructions, preparing to expand Nguyen Tuan street

|

Hanoi - It is expected that in December, Thanh Xuan district will complete the clearance of construction works to expand Nguyen Tuan street, 720m long, with a capital of nearly 400 billion VND.

National Highway 91 in Can Tho has a surplus of more than VND3,000 billion: Reviewing and determining the cost of site clearance

|

Can Tho - The investor is coordinating with relevant units to conduct a review to determine the cost of site clearance (GPMB) of the project.

Young man throws 20-liter water bottle from the 26th floor of an apartment building in Ho Chi Minh City to the ground

|

HCMC - On August 14, social networks spread a clip recording the scene of many 20-liter water bottles falling from the upper floors of an apartment building, endangering people.

Hanoi has heavy rain, people leave their meals unused and run away from flooding

|

Hanoi - The heavy rain at noon on August 14 quickly turned Truong Dinh street into a river, in some places flooding nearly 30cm deep.

SJC gold bar price increases sharply, reaching a peak of 125 million VND/tael

|

After many sessions of struggling at a narrow range, the price of gold bars this morning (August 14) was unexpectedly adjusted by some businesses to increase sharply to 800,000 VND/tael.

28 enterprises will be honored as "Outstanding Enterprises for Workers"

|

The "Outstanding Enterprise for Workers" Award is scheduled to take place at 7:30 p.m. on August 15.

Ì ạch thi công mở rộng đường Nguyễn Tuân, Hà Nội

HỮU CHÁNH |

Hà Nội - Hoạt động thi công diễn ra ì ạch trên công trường mở rộng đường Nguyễn Tuân dù mặt bằng đã được bàn giao cách đây gần 3 tháng.

Clearing a series of constructions, preparing to expand Nguyen Tuan street

HỮU CHÁNH |

Hanoi - It is expected that in December, Thanh Xuan district will complete the clearance of construction works to expand Nguyen Tuan street, 720m long, with a capital of nearly 400 billion VND.

Tiến độ dự án 400 tỉ đồng mở rộng, cải tạo đường Nguyễn Tuân

Tuấn Anh |

Dự án mở rộng đường Nguyễn Tuân (Thanh Xuân, Hà Nội) đang hoàn thiện giải phóng mặt bằng và chuẩn bị khởi công nhằm xóa điểm đen về ùn tắc tại khu vực này.