40m wide road connecting two districts of Hanoi before opening month

HỮU CHÁNH |

Hanoi - The Le Quang Dao extended road project connecting Nam Tu Liem district with Ha Dong is nearing completion, expected to open to technical traffic on October 10 after nearly 2 years of construction.

In early 2023, Hanoi started the investment project to build the extended Le Quang Dao road .

The project is about 2.6 km long, starting at the intersection with Thang Long Avenue, Nam Tu Liem district, and ending at Duong Noi urban area, Ha Dong district.

The project has a total investment of more than 700 billion VND, of which construction costs are more than 408 billion VND.

According to the design, the route will have inter-regional road standards, a cross-section of 40m with 6 lanes, and a design speed of 60 km/h. The section connecting to Thang Long Avenue (about 110m long) will have a cross-section width of 100m.

The representative of the investor - Nam Tu Liem District Construction Investment Project Management Board - said that to implement the Le Quang Dao extended road project, about 11.86 hectares must be reclaimed. Currently, the problem of site clearance has been resolved.

To complete the project on the occasion of the 70th anniversary of the Capital Liberation Day (October 10), the investor has recently directed the contractor to mobilize maximum machinery, workers, and engineers to work in 3 shifts continuously to ensure the project's progress.

However, before and after storm No. 3 Yagi made landfall in Hanoi, heavy rain made construction difficult.

It is expected that when the project is completed, it will help shorten travel time between Nam Tu Liem and Ha Dong districts, reduce traffic pressure on many routes such as To Huu and Sa Doi, and connect many urban areas in the west of the city such as Duong Noi, Louis City, and FLC Premier.

The starting point of the project intersects with Thang Long Boulevard and connects with the existing Le Quang Dao Street.
The starting point of the project intersects with Thang Long Avenue and connects with the existing Le Quang Dao Street. The first 110 meters of the road have a cross-section of up to 100 meters wide. Photo: Huu Chanh
The end point of the route connects with the existing route at Duong Noi (Ha Dong), creating a smooth traffic axis, reducing the load on To Huu and Nguyen Trai - Tran Phu routes.
The end point of the route connects with the existing route at Duong Noi (Ha Dong), creating a smooth traffic axis, reducing the load on To Huu and Nguyen Trai - Tran Phu routes. Photo: Huu Chanh
About 1km of the first route from Thang Long Avenue to Dai Linh Street (Me Tri Ward) has been completed.
After nearly 2 years of construction, the route has taken shape, of which the nearly 1 km section intersecting with Thang Long Avenue to Dai Linh Street (Nam Tu Liem, Hanoi) has basically completed the main items. Photo: Huu Chanh
This road section is paved with stone pavement, asphalt pavement, trees, lighting system and fire fighting water supply system.
This road section is paved with stone pavement, asphalt pavement, trees, lighting system and fire-fighting water supply system. Photo: Huu Chanh
a
The impact of storm No. 3 Yagi caused a series of newly planted trees on Le Quang Dao Street to fall. Photo: Huu Chanh
Meanwhile, the remaining section from Sa Doi Street to the end of the route is still messy, the road surface structure is not completed.
Meanwhile, the remaining section from Dai Linh Street to the end of the route is under construction, waiting for connection. Photo: Huu Chanh
Authorities said the heavy rains had a major impact on the construction. During the rainy days, workers could not construct the roadbed and could only focus on safety and sidewalks.
The construction site is still messy, the road surface structure is not yet complete. Photo: Huu Chanh
Workers install barriers at the intersection of Highway 70 to serve the project's construction. Photo: Huu Chanh
Workers install barriers at the intersection of Highway 70 to serve the project's construction. Photo: Huu Chanh
Authorities said that the impact of Typhoon No. 3 Yagi caused heavy rain, making construction difficult. In recent days, workers have been unable to complete construction items. Photo: Huu Chanh
Authorities said that the impact of Typhoon No. 3 Yagi caused heavy rain, making construction difficult. In recent days, workers have been unable to complete construction items. Photo: Huu Chanh
The entire route has a bridge over the Nhue River, with the main items basically completed. Photo: Huu Chanh
The entire route with the bridge over the Nhue River has basically completed the main items. Photo: Huu Chanh
a
In the photo is the machinery assembly area of ​​the Nhue River overpass. Photo: Huu Chanh
The project is expected to be completed on October 10, helping to facilitate the connection between Nam Tu Liem and Ha Dong districts. Photo: Huu Chanh
The project is expected to be completed on October 10, helping to facilitate the connection between Nam Tu Liem and Ha Dong districts. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

Mong chờ dự án mở đường rộng 80m, vốn gần 19.000 tỉ đồng ở Hà Nội

HỮU CHÁNH |

Người Hà Nội mong dự án mở rộng Quốc lộ 21 sớm được phê duyệt chủ trương đầu tư và triển khai thi công để giải quyết tình trạng ùn tắc, tai nạn giao thông.

Hà Nội tập trung làm đường rộng 120-180m nối 2 cao tốc

HỮU CHÁNH |

Hà Nội đang tập trung giải phóng mặt bằng để triển khai thi công dự án đường nối 2 cao tốc dài 6,7km, vốn đầu tư hơn 5.200 tỉ đồng.

Cảnh tượng đìu hiu công trường dự án chống ùn tắc ở Hà Nội

HỮU CHÁNH |

Hà Nội - Công trường dự án "giải cứu" ùn tắc cửa ngõ phía Nam thời gian qua rơi vào cảnh đìu hiu, thi công cầm chừng vì thiếu mặt bằng.

Ảnh hưởng thi công âu thuyền, nhà dân bị ngập sâu trong nước

YẾN PHƯƠNG - TẠ QUANG |

Việc thi công công trình Âu thuyền Cái Khế đã khiến nhiều nhà dân tại TP Cần Thơ bị lún, nứt nghiêm trọng và ngập sâu trong nước.

Dân Hà Nội khám da liễu hàng tháng vì 6 năm không có nước sạch

KHÁNH AN |

Suốt 6 năm qua, hàng tháng, vợ chồng anh Nguyễn Đình Minh (Hoài Đức, Hà Nội) đều đưa các con đi khám da liễu vì không có nước sạch sử dụng.

Tăng trợ cấp thất nghiệp lên 75% giúp người lao động yên tâm

MINH HÀ - HOÀNG XUYẾN |

Tăng mức hưởng trợ cấp thất nghiệp lên 75% lương bình quân là mong mỏi của rất nhiều người lao động.

Barcelona mất người, thua trận ra quân tại Champions League

tam nguyên |

Eric Garcia sớm nhận thẻ đỏ khiến Barcelona không thể có điểm trên sân AS Monaco.

Nỗ lực định hình tên tuổi từ cái bóng “ngôi sao nhí”

Ngọc Dủ |

Thị trường nhạc Việt từng có không ít sân chơi dành cho các tài năng nhí, nổi bật trong số đó phải kể đến Thần tượng âm nhạc nhí, Giọng hát Việt nhí... Đây được xem là bệ phóng cho không ít tài năng trẻ phát triển và theo đuổi sự nghiệp của mình.

Looking forward to the project of opening an 80m wide road with a capital of nearly 19,000 billion VND in Hanoi

HỮU CHÁNH |

Hanoians hope that the National Highway 21 expansion project will soon be approved for investment and construction to resolve traffic congestion and accidents .

Hanoi focuses on building 120-180m wide roads connecting 2 highways

HỮU CHÁNH |

Hanoi is focusing on site clearance to implement the 6.7km long connecting road project between the two expressways, with an investment capital of more than VND5,200 billion.

Desolate scene at the construction site of the anti-congestion project in Hanoi

HỮU CHÁNH |

Hanoi - The construction site of the project to "rescue" traffic jams at the southern gateway has recently fallen into a state of disrepair, with construction at a standstill due to lack of land .