Ring Road 4 - Capital Region faces the risk of "road waiting for bridge"

HỮU CHÁNH - KHÁNH AN |

The parallel road of Ring Road 4 is being accelerated and is expected to be completed in 2025, but to date, the three bridges including Me So, Hong Ha and Hoai Thuong have not yet started construction, most likely "the road is finished but the bridge is not seen".

No sign of bridge construction yet

The Ring Road 4 project in the Capital Region has a total length of nearly 113km, passing through 3 provinces and cities, including Hanoi (58km), Hung Yen (19.3km), Bac Ninh (36.2km). The starting point of the project is at the Hanoi - Lao Cai expressway connection point, the end point is at the Noi Bai - Ha Long expressway connection point.

The project is implemented in 7 component projects, operating independently. Of which, Hanoi implements 3 component projects: Compensation, support, resettlement; Construction of parallel roads (urban roads) in Hanoi and investment in the construction of expressway systems under the PPP method. Ring Road 4 of the Capital region has 3 large bridges, including Me So bridge, Hong Ha bridge across the Red River and Hoai Thuong bridge across the Duong River.

Me So Bridge is about 600m downstream from Hong Van pumping station, Thuong Tin district (Hanoi). In Van Giang district (Hung Yen), the approach road to the bridge runs through Me So and Thang Loi communes and next to the 500kV power line. Once completed, Me So Bridge will open a new direction for vehicles from the center of Hanoi to Van Giang district and vice versa instead of going towards Thanh Tri bridge as before.

Hong Ha Bridge intersects with Hong Ha Street, the section passing through Gia Le Pagoda, located between Lien Hong Secondary School and Bong Lai village, in Lien Hong commune (Dan Phuong district) connecting with Van Khe commune (Me Linh district).

Located on the Ring Road 4 axis of the Capital region, there is also Hoai Thuong Bridge across the Duong River, Bac Ninh province.

The Hanoi People's Committee said that it will strive to complete site clearance and handover before December 31, 2024; in some difficult cases, it will be completed before the Lunar New Year. The city also strives to complete the parallel project in the fourth quarter of 2025.

However, according to Lao Dong, there are still more than 100 households in Khe Ngoai 2 village, Van Khe commune, Me Linh, located within the construction boundary of Hong Ha bridge, whose land has not been cleared. Similarly, in Dan Phuong, many households subject to land clearance for the construction of Hong Ha bridge have not been relocated.

Meanwhile, the Me So bridge on Thuong Tin side (Hanoi) has been cleared, while the Van Giang side (Hung Yen) has not been cleared and there is currently no sign of construction of the Me So bridge in this area. This makes many people worried that the parallel road will be completed but they will have to "wait for the bridge".

Speaking with Lao Dong, a representative of a contractor constructing a parallel road to the Ring Road 4 project said: In the case that the parallel road is completed but the bridge is not completed and traffic is not open, it will not bring benefits to the people as well as economic efficiency.

Duong song hanh du kien hoan thanh trong nam 2025 nhung 3 cau qua song Hong, song Duong chua duoc trien khai xay dung. Anh: Huu Chanh
The parallel road is expected to be completed in 2025, but the construction of three bridges across the Red River and Duong River has not yet begun. Photo: Huu Chanh

Traffic must be smooth.

Associate Professor, Dr. Nguyen Hong Thai - Head of the Faculty of Transport and Economics (University of Transport) said that in the transport infrastructure, the ring road is extremely important, preventing vehicles from running through the city center.

“The purpose of parallel roads is to serve the highway, not the highway to serve parallel roads. So if there are only parallel roads, the service will not be effective,” Associate Professor Nguyen Hong Thai emphasized.

According to Vice Chairman of Hanoi People's Committee Duong Duc Tuan, this project is planned to be completed in 2026 and put into operation in 2027. Up to now, the progress of implementing Component Project 1.1 - Compensation, support, site clearance and Component Project 2.1 - Construction of parallel roads has basically met the requirements.

However, the biggest difficulty now is implementing Component Project 3 - Investing in the construction of expressways under the public-private partnership (PPP) method to ensure progress and disbursement of the central capital allocated for the project in 2024 of VND 4,190 billion.

Currently, the parallel road component projects (Component Project Group 2) are being accelerated to ensure completion by the end of 2025 as directed by the Prime Minister.

Thus, when the parallel road system is expected to be completed in 2025, it still cannot connect the entire route because major bridges such as Hong Ha Bridge, Me So Bridge (over the Red River), Hoai Thuong Bridge (over the Duong River) belonging to the public investment sub-project in Component Project 3 have not been completed, reducing investment efficiency.

In that situation, the Hanoi People's Committee respectfully requests the Prime Minister to propose to the National Assembly to allow the implementation of the Public Investment Sub-project in Component Project 3 as a normal public investment project and to be implemented independently, in parallel and not depending on the progress and results of selecting investors to implement the remaining part of Component Project 3.

HỮU CHÁNH - KHÁNH AN
TIN LIÊN QUAN

Image of the large bridge on Ring Road 4 in the Capital region under construction

|

The 27-span railway overpass (part of package 8 - construction of the parallel road to Ring Road 4) has taken shape and is expected to be completed in April 2025.

Total construction force, completion of parallel road of Ring Road 4 by 2025

|

According to plan, the parallel road of Ring Road 4 through Hanoi, Hung Yen and Bac Ninh will be completed in 2025. Contractors are focusing on construction, closely following the schedule.

New information about a 5-year-old child who died at school

|

Ha Tinh - The Department of Education and Training (GDDT) of Cam Xuyen district has fully informed about the incident of a 5-year-old boy dying at Cam Trung Kindergarten.

The Supreme People's Court may have a maximum of 27 judges

|

The draft Law on the Organization of the People's Court amends the proposal to increase the number of judges of the Supreme People's Court (SPC) from 13 to 17 people to 23 to 27 people.

Completely eliminate the Ministry Inspectorate, Department and District Inspectorates

|

According to the draft Law on Inspection (amended), regulations on the Inspectorate of Ministries, Departments and districts have been completely abolished.

Pope Francis's funeral was held in St. Petro Square

|

papal Francis's funeral took place mainly in the Vatican, before the papal's body was buried in the civil throne of Rome.

Appointing Lieutenant General Nguyen Hong Thai as Deputy Minister of National Defense

|

Lieutenant General Nguyen Hong Thai was appointed by the Prime Minister to hold the position of Deputy Minister of National Defense.

Criteria for leadership positions of commune-level party committees after the merger

|

The Central Organizing Committee guides the criteria and standards for the positions of leaders of the Party Committees at the commune level and the number of positions after the merger.

Image of the large bridge on Ring Road 4 in the Capital region under construction

HỮU CHÁNH |

The 27-span railway overpass (part of package 8 - construction of the parallel road to Ring Road 4) has taken shape and is expected to be completed in April 2025.

Hiện trạng nơi xây cầu vượt sông Hồng, sông Đuống trên Vành đai 4

NHÓM PV |

Có 3 cây cầu lớn trên Vành đai 4 sẽ được đầu tư xây dựng gồm Hồng Hà và Mễ Sở qua sông Hồng, cầu Hoài Thượng qua sông Đuống.

Total construction force, completion of parallel road of Ring Road 4 by 2025

NHÓM PV |

According to plan, the parallel road of Ring Road 4 through Hanoi, Hung Yen and Bac Ninh will be completed in 2025. Contractors are focusing on construction, closely following the schedule.