Hanoi clears nearly 400 houses to build 60-80m wide road

HỮU CHÁNH |

Hanoi - It is expected that nearly 400 houses in Ha Dong and Thanh Tri will be demolished to implement the 10km-long Ring Road 3.5 project, with an investment capital of more than VND8,500 billion.

In July 2023, the Hanoi People's Council issued Resolution No. 14/NQ-HDND on deciding on the investment policy for the project "Investment in the construction of Ring Road 3.5, section from Phuc La - Van Phu to Phap Van - Cau Gie Expressway".

This is a group A project, with a preliminary total investment of about 8,556 billion VND and is divided into 3 component projects.

Component project 1.1: Compensation, support, resettlement for site clearance in Ha Dong district. Preliminary total investment of 684 million VND, with Ha Dong District People's Committee as the investor.

Component project 1.2: Compensation, support, resettlement for site clearance in Thanh Tri district. Preliminary total investment is about 2,271 billion VND, Thanh Tri district People's Committee is the project investor.

Component project 2: Investment in construction of Ring Road 3.5 from Phuc La - Van Phu to Phap Van - Cau Gie expressway with a total investment of VND 5,601 billion, invested by Hanoi Civil Works Investment Project Management Board.

The project has a total length of about 10.34km, starting point Km0+000 on Van Khe street, Ha Dong district, ending point Km10+340 intersecting with Phap Van - Cau Gie expressway with a cross-section width of 60-80m, design speed of 80km/h.

On the route, 6 bridge projects are invested in construction including: Nhue River Bridge, Hoa Binh Bridge, To Lich Bridge, railway overpass, National Highway 1A overpass and Phap Van - Cau Gie Expressway intersection overpass. These bridges have cross-sectional scales suitable for the scale of the route.

a
Construction locations of 6 bridges on the route. Photo: Hanoi Civil Works Investment Project Management Board

The project route includes main intersections including Van Khe intersection (Km0); Southern axis road intersection over the railway (Km1+757.80); existing railway intersection (Km5+857.55); National Highway 1A intersection (Km9+147.75) and Phap Van - Cau Gie expressway intersection (Km10+324.36).

The total land area expected to be recovered to implement the project is about 1,299,353m2 (129.9ha), of which the land for growing two rice crops is about 48.54ha.

Preliminary statistics show that about 386 houses will be demolished to implement the project (of which Ha Dong district has 14 houses, Thanh Tri district has 372).

According to the plan, the investor will select a contractor in the fourth quarter of 2024 - the first quarter of 2025. The project is expected to be completed and handed over in the fourth quarter of 2027.

The completion of the Ring Road 3.5 project from Phuc La - Van Phu to Phap Van - Cau Gie expressway will help reduce traffic congestion, contribute to accelerating the formation of urban areas in the area between Ring Road 3 and Ring Road 4, and promote the exploitation of land fund potential, human resources, and material resources for socio-economic development of the capital in general and the region in particular.

HỮU CHÁNH
RELATED NEWS

Current status of expanding Hanoi central road to 21m wide

|

Hanoi - Thanh Xuan District has basically completed the clearance of construction works, preparing to widen Nguyen Tuan Street from nearly 10m to 21m, with a capital of nearly 400 billion VND.

Image of the 6,000 billion project that Hanoi committed to complete in 2025

|

After 16 years of implementation, the 6,000 billion VND traffic project has just completed and opened to traffic a 18.5 km section. Hanoi has committed to completing the remaining 23 km in 2025.

A railway overpass costing nearly 300 billion is under construction in Hanoi

|

Hanoi - Some items of the National Highway 1A overpass and North-South railway project (Thuong Tin district), with a capital of nearly 300 billion VND, are gradually taking shape after more than half a year of construction.

Tien Linh continues to be silent, Ho Chi Minh City Police loses minimally to Becamex Ho Chi Minh City

|

On the evening of March 1st, Ho Chi Minh City Police Club suffered a 0-1 defeat to Becamex TPHCM in round 13 of LPBank V.League 2025-2026 on Tien Linh's lackluster day.

Metro connecting the two banks of the Saigon River is expected by people

|

Ho Chi Minh City - With a capital of 33,000 billion VND, Ben Thanh - Thu Thiem Metro is expected to be completed soon, meeting the people's expectations for a connected transportation system.

Live football Nam Dinh vs Ninh Binh in round 14 of V.League

|

Live match between Nam Dinh and Ninh Binh in round 14 of LPBank V.League 2025-2026, taking place at 6:00 PM today (March 1).

Iran declares the US suffered heavy casualties in retaliatory attack

|

Iran retaliated against US and Israeli attacks by targeting Washington's military bases throughout the region.

Current status of expanding Hanoi central road to 21m wide

HỮU CHÁNH |

Hanoi - Thanh Xuan District has basically completed the clearance of construction works, preparing to widen Nguyen Tuan Street from nearly 10m to 21m, with a capital of nearly 400 billion VND.

Image of the 6,000 billion project that Hanoi committed to complete in 2025

HỮU CHÁNH |

After 16 years of implementation, the 6,000 billion VND traffic project has just completed and opened to traffic a 18.5 km section. Hanoi has committed to completing the remaining 23 km in 2025.

A railway overpass costing nearly 300 billion is under construction in Hanoi

HỮU CHÁNH |

Hanoi - Some items of the National Highway 1A overpass and North-South railway project (Thuong Tin district), with a capital of nearly 300 billion VND, are gradually taking shape after more than half a year of construction.