300 billion VND route
Dynamic urban development project - Yen Bai City sub-project - Construction of the road connecting Nguyen Tat Thanh street to Au Co street invested by Yen Bai Provincial Construction Investment Project Management Board.
The 4.2km long route is constructed by a consortium of Nam Phong Investment, Construction and Trading Joint Stock Company, Yen Bai Traffic Construction Joint Stock Company and Thanh Trung Construction and Trading Company Limited, with a total investment of nearly 300 billion VND.
Construction started in December 2022 and is expected to be completed in April 2025.
According to Lao Dong's records, on the days before Lunar New Year, at the project site, dozens of workers and many machines were working hard to bring the project on schedule.
Mr. Dao Dinh Tung (32 years old, Tan Thinh, Yen Bai City) said that he hopes that after the completion of the road, it will help connect traffic: "The road will make traveling much more convenient, along with that, the new road will help significantly shorten travel time from home to the city center".
Speaking with Lao Dong, Mr. Doan Van Hai - project manager - said that according to the contract, the route is expected to be completed in April 2025.
"The unit is striving to take advantage of favorable weather to pave the entire road surface," said Mr. Hai.
According to research, the project to comprehensively develop dynamic urban areas has been implemented in Yen Bai city since 2019 with a total investment of 63.27 million USD, equivalent to more than 1,423 billion VND.
Of which, the World Bank (WB) loan is 39.46 million USD, equivalent to 888 billion VND and domestic counterpart capital is 23.81 million USD, equivalent to 535 billion VND.
The road connecting Au Co Street and Nguyen Tat Thanh Street is a sub-project of Yen Bai City.
300 billion VND intersection connecting the highway
IC13 Interchange Project of Noi Bai - Lao Cai Expressway (section Km 122 + 240), located in Au Lau Commune, Yen Bai City. The project was approved and adjusted by the Chairman of Yen Bai Provincial People's Committee on August 19, 2021 and October 7, 2022, with a total investment of VND 302.8 billion.
The project started construction in March 2023, constructed by a joint venture of Hanoi D&T Construction Investment Consulting Joint Stock Company - 307 Quang Phu Joint Stock Company - Elcom Technology - Telecommunication Joint Stock Company.
Once completed, the project is expected to make travel from the provinces of Lao Cai, Phu Tho, Vinh Phuc... to some localities of Yen Bai such as Tran Yen, Yen Bai City and western districts and towns such as Van Chan, Nghia Lo, Tram Tau, Mu Cang Chai more convenient.
According to the design, the project consists of 2 main items. The IC13 intersection includes: the main branch road system (branch A) and 4 branches (B, C, D, E) connecting branch A with Noi Bai - Lao Cai highway at Km 122 + 240.
Branch A is 0.5 km long, roadbed width 23.5 m; branches B, C, D, E have a total length of 1.5 km, roadbed width 8 m.
According to the representative of the Yen Bai Traffic Construction Investment Project Management Board, the unit is currently striving to bring the project to the finish line and into operation soon.
"The project is completing the final stages and is expected to be completed in the first quarter of 2025," the representative informed.