Expanding Tran Binh Trong street, a household in Ho Chi Minh City receives nearly 29 billion VND in compensation

NHƯ QUỲNH |

Ho Chi Minh City - The Tran Binh Trong road expansion project currently has 115/116 cases of land handover, of which one household received the highest compensation of more than 28.9 billion VND.

Lao Dong's records in the first days of September, at the construction site of the Tran Binh Trong road expansion investment project (Vuon Lai ward, Ho Chi Minh City), many machines and equipment were gathered, workers were urgently constructing. Along the route, most households have dismantled houses, handed over land, serving the project. Many households are repairing and renovating their residences after handing over the land.

Hầu hết các hộ dân trong diện ảnh hưởng dự án đã tháo dỡ nhà, bàn giao mặt bằng. Ảnh: Như Quỳnh (ảnh chụp Tháng 9.2026)
Most households affected by the project have dismantled their houses and handed over the land. Photo: Nhu Quynh (photo taken in September 2026)
đơn vị thi công tập trung nhân lực, máy móc trên tuyến đường Trần Bình Trọng.
Construction units concentrate manpower and machinery on Tran Binh Trong street. Photo: Nhu Quynh (photo taken in September 2026)

In the Ho Thi Ky flower market area, business activities still take place during the project implementation period. Ms. Lien Trang, who has been doing business here for more than 10 years, said that in the past, the road was small and degraded, and flower trucks could not conveniently enter, so they had to transport goods far away, causing inconvenience.

Now that the road opening project has been implemented, it is expected that when completed, the road will be wide and spacious, and business will also be more convenient. I also plan to renovate the flower shop to be synchronized and attract more customers, especially tourists," Ms. Lien Trang shared.

Theo chị Trang, trước đây xe chở hoa không thể vào sâu trong tuyến đường nên khi vận chuyển hàng hóa phải di chuyển ra đầu đường lớn, quãng đường xa hơn và gặp nhiều bất tiện. Ảnh: Như Quỳnh
According to Ms. Trang, in the past, flower trucks could not go deep into the road, so when receiving goods, they had to move to the beginning of the main road, a longer distance and encountered many inconveniences. Photo: Nhu Quynh (photo taken in September 2026)

According to Ms. Trang, the road construction process was dusty, and travel was also difficult. However, she sympathized and hoped that the project would be completed soon so that people could stabilize their lives.

Mr. Nguyen Hoang Minh Man (Vuon Lai ward, Ho Chi Minh City) said that this area is being invested in by the city with many items in parks and roads, so the appearance changes every day.

After Tet, the road began to focus on clearance, until now I see that the households in the clearance area have almost completed handover. In recent days, construction has been bustling. With this progress, I think it will be completed soon," Mr. Man said and hoped that when Tran Binh Trong road is expanded, it will also contribute to reducing congestion at Ly Thai To intersection and Cong Hoa intersection.

Một số hộ dân tất bật sửa sang, chỉnh trang nhà cửa sau khi bàn giao mặt bằng cho dự án. Ảnh: Như Quỳnh (ảnh chụp Tháng 9.2026)
Some households are busy repairing and renovating their houses. Photo: Nhu Quynh (photo taken in September 2026)
Công nhân triển khai các hạng mục nền đường trên tuyến Trần Bình Trọng.
Workers deploy roadbed items on Tran Binh Trong route. Photo: Nhu Quynh (photo taken in September 2026)

Talking to PV of Lao Dong Newspaper, Mr. Nguyen The Khang - Vice Chairman of Vuon Lai Ward People's Committee informed that as of September 17, 115/116 cases have handed over land, reaching 99.14%; the remaining cases have not been approved for plans due to obstacles in the level of temporary housing support. Currently, the locality has approved compensation, support, and resettlement plans for households in the clearance area.

According to Mr. Khang, the household with the highest compensation amount in the Tran Binh Trong road expansion and clearance project is more than 28.9 billion VND.

Công tác giải phóng mặt bằng dự án Trần Bình Trọng còn một trường hợp chưa hoàn tất.
Land clearance work for the Tran Binh Trong project still has one unfinished case. Photo: Nhu Quynh (photo taken in September 2026)

The locality sets a target to complete site clearance before October 1 to implement phase 2 of the Memorial Park project at No. 1 Ly Thai To.

Regarding construction progress, the items of box culverts, road cross culverts and 17/17 manholes have been 100% completed. The power pipeline system on the right branch line reached 95%, the left branch reached 100%; roadbed reached 40% and sandbed reached 30%.

Ward leaders requested the construction unit to accelerate the roadbed, road surface, and sidewalk items; and at the same time underground the power grid and water supply system.

The project to expand Tran Binh Trong road (from Hung Vuong to Ly Thai To) from 5 m to 15 m, with an investment of more than 985 billion VND. Of which, construction and consulting costs account for more than 40 billion VND, the rest is for compensation, support and resettlement.

It is expected that the entire investment project to expand Tran Binh Trong street, including intersections on the route, will be completed in November 2026.

NHƯ QUỲNH
RELATED NEWS

Continuous traffic jams at the roundabout in Ho Chi Minh City on the first day of traffic light operation

|

Ho Chi Minh City - On the first day of piloting traffic lights at the roundabout at Nga 6 Nguyen Thi Minh Khai - Nguyen Van Cu - Ly Thai To, traffic was adjusted flexibly.

The central intersection of Ho Chi Minh City is about to reduce traffic congestion thanks to the project to open a road 3 times

|

HCMC - The project to expand Tran Binh Trong Street from 5m to 17m is expected to reduce traffic congestion at Ly Thai To intersection and neighboring roads.

Ho Chi Minh City Department of Culture and Sports speaks out about Truong Giang's scandal

|

Before the debate related to Truong Giang, the Ho Chi Minh City Department of Culture and Sports said that the assessment of a specific case needs to be based on verified information.

Former Chairman of Tu Nghia Commune People's Committee allows traffic collisions to cause serious consequences

|

Quang Ngai - Mr. Nguyen Ngoc Hung - former Chairman of the People's Committee of Tu Nghia commune caused a traffic collision causing serious consequences.

Expanding Tran Binh Trong street, a household in Ho Chi Minh City receives nearly 29 billion VND in compensation

|

Ho Chi Minh City - The Tran Binh Trong road expansion project currently has 115/116 cases of land handover, of which one household received the highest compensation of more than 28.9 billion VND.

Live Vietnam women's team vs Thailand at ASIAD 20

|

Live broadcast of Vietnam women's team vs Thailand at ASIAD 20 taking place at 5:30 PM today (September 21).

TPHCM lấy ý kiến đặt tên công viên tưởng niệm nạn nhân COVID-19

NHƯ QUỲNH |

TPHCM đang lấy ý kiến người dân về việc đặt tên công viên để tưởng niệm nạn nhân COVID-19 tại số 1 Lý Thái Tổ.

Continuous traffic jams at the roundabout in Ho Chi Minh City on the first day of traffic light operation

Tú Quỳnh |

Ho Chi Minh City - On the first day of piloting traffic lights at the roundabout at Nga 6 Nguyen Thi Minh Khai - Nguyen Van Cu - Ly Thai To, traffic was adjusted flexibly.

The central intersection of Ho Chi Minh City is about to reduce traffic congestion thanks to the project to open a road 3 times

NHƯ QUỲNH |

HCMC - The project to expand Tran Binh Trong Street from 5m to 17m is expected to reduce traffic congestion at Ly Thai To intersection and neighboring roads.