Many projects in Kon Tum are stuck with construction sites

THANH TUẤN |

Kon Tum - Many construction projects with a capital of hundreds of billions of VND in Kon Tum are currently stuck with clean land to speed up construction.

On April 2, the Management Board of Investment and Construction of Traffic, Civil and Industrial Works of Kon Tum province said that some contractors are still waiting for people to hand over the site to speed up the project's construction progress and implement construction contracts.

Specifically, the Kon Tum City Western Main Axis Road Project (total investment of VND1,492.6 billion, nearly 20 km long) has only handed over nearly 7 km of site, causing difficulties for construction. In particular, package No. 3 (Km11 - Km19+840) cannot be implemented due to problems in reclaiming rubber trees and crops.

At the Truong Chinh Road project (total capital of 457.126 billion VND), although construction started in 2020, it has not been completed after nearly 5 years.

The Provincial Road 671 upgrade project (total capital of 128.94 billion VND) was expected to be completed in May 2025, but to date, the site clearance has not been completed, causing the contractor to not reach the planned workload.

These are all key projects with large investment scale in Kon Tum province. Although the provincial Department of Construction has transferred enough funds to the City Land Fund Development Center, the specific compensation plans for the projects have not yet been approved, affecting the implementation progress.

Faced with prolonged difficulties in site clearance, Deputy Secretary of Kon Tum Provincial Party Committee Nguyen Duc Tuy directly inspected the situation and requested local authorities to urgently verify the origin of land, houses, trees, and crops to develop a compensation and support plan in accordance with regulations, ensuring the rights of the people.

At the same time, commune and ward leaders need to strengthen propaganda and mobilization work to speed up the progress of site handover.

THANH TUẤN
TIN LIÊN QUAN

Deadline for handing over the Tuyen Quang - Ha Giang expressway site

|

The Chairman of Tuyen Quang Provincial People's Committee requested localities to complete the handover of the entire Tuyen Quang - Ha Giang expressway site before April 5.

There is still 1 month left to hand over enough land to expand Tam Trinh Street

|

Hanoi - Hoang Mai District scheduled to hand over enough land to expand Tam Trinh Street on April 30. Thus, there is 1 month left for the locality to complete this target.

Dry port project in Hoai Duc abandoned for many years

|

The ICD My Dinh dry port project in Hoai Duc, Hanoi has been approved for nearly 10 years but has not been completed. However, the project's land has shown signs of lease.

Deputy Prime Minister Ho Duc Phoc is about to go to the US

|

Deputy Prime Minister Ho Duc Phoc paid a working visit to the US and an official visit to the Republic of Cuba.

Hanoi promotes tourism with a unique gift festival

|

Hanoi To stimulate tourism, from April 11 to 13, Hanoi will organize the 2025 Tourism gift Festival.

Deadline for handing over the Tuyen Quang - Ha Giang expressway site

Việt Bắc |

The Chairman of Tuyen Quang Provincial People's Committee requested localities to complete the handover of the entire Tuyen Quang - Ha Giang expressway site before April 5.

There is still 1 month left to hand over enough land to expand Tam Trinh Street

HỮU CHÁNH |

Hanoi - Hoang Mai District scheduled to hand over enough land to expand Tam Trinh Street on April 30. Thus, there is 1 month left for the locality to complete this target.

Đồng Nai giải phóng mặt bằng 3 đường nối sân bay Long Thành

HÀ ANH CHIẾN |

Đồng Nai yêu cầu 6 huyện, thành phố khẩn trương giải phóng mặt bằng 3 dự án đường ĐT 770B, đường ĐT 773, đường ĐT 769 kết nối sân bay Long Thành.