Many projects in Kon Tum are stuck with construction sites

THANH TUẤN |

Kon Tum - Many construction projects with a capital of hundreds of billions of VND in Kon Tum are currently stuck with clean land to speed up construction.

On April 2, the Management Board of Investment and Construction of Traffic, Civil and Industrial Works of Kon Tum province said that some contractors are still waiting for people to hand over the site to speed up the project's construction progress and implement construction contracts.

Specifically, the Kon Tum City Western Main Axis Road Project (total investment of VND1,492.6 billion, nearly 20 km long) has only handed over nearly 7 km of site, causing difficulties for construction. In particular, package No. 3 (Km11 - Km19+840) cannot be implemented due to problems in reclaiming rubber trees and crops.

At the Truong Chinh Road project (total capital of 457.126 billion VND), although construction started in 2020, it has not been completed after nearly 5 years.

The Provincial Road 671 upgrade project (total capital of 128.94 billion VND) was expected to be completed in May 2025, but to date, the site clearance has not been completed, causing the contractor to not reach the planned workload.

These are all key projects with large investment scale in Kon Tum province. Although the provincial Department of Construction has transferred enough funds to the City Land Fund Development Center, the specific compensation plans for the projects have not yet been approved, affecting the implementation progress.

Faced with prolonged difficulties in site clearance, Deputy Secretary of Kon Tum Provincial Party Committee Nguyen Duc Tuy directly inspected the situation and requested local authorities to urgently verify the origin of land, houses, trees, and crops to develop a compensation and support plan in accordance with regulations, ensuring the rights of the people.

At the same time, commune and ward leaders need to strengthen propaganda and mobilization work to speed up the progress of site handover.

THANH TUẤN
RELATED NEWS

Deadline for handing over the Tuyen Quang - Ha Giang expressway site

|

The Chairman of Tuyen Quang Provincial People's Committee requested localities to complete the handover of the entire Tuyen Quang - Ha Giang expressway site before April 5.

There is still 1 month left to hand over enough land to expand Tam Trinh Street

|

Hanoi - Hoang Mai District scheduled to hand over enough land to expand Tam Trinh Street on April 30. Thus, there is 1 month left for the locality to complete this target.

Dong Nai clears land for 3 roads connecting Long Thanh airport

|

Dong Nai requested 6 districts and cities to urgently clear the land for 3 projects of DT 770B road, DT 773 road, DT 769 road connecting Long Thanh airport.

Removing bottlenecks that promote energy transition

|

To promote a faster and more efficient energy transition, many bottlenecks in mechanisms, resources and markets need to be removed soon.

Gold prices plummet, buying-selling spread widens, buyers at a disadvantage

|

In the context of deep gold price drops, a series of business brands adjusted the buying - selling price difference from 3 million to 5 million VND/tael.

Promoting energy transition for double-digit growth

|

In the context of Vietnam aiming for double-digit growth, the energy transition problem is being posed more urgently than ever.

Mandatory requirements for candidates in the 2026 high school graduation exam

|

Tomorrow, June 10th, more than 1.2 million candidates nationwide will complete procedures for the 2026 high school graduation exam and enter the exam in 2 days, December 11th - 12th. 6.

Deadline for handing over the Tuyen Quang - Ha Giang expressway site

Việt Bắc |

The Chairman of Tuyen Quang Provincial People's Committee requested localities to complete the handover of the entire Tuyen Quang - Ha Giang expressway site before April 5.

There is still 1 month left to hand over enough land to expand Tam Trinh Street

HỮU CHÁNH |

Hanoi - Hoang Mai District scheduled to hand over enough land to expand Tam Trinh Street on April 30. Thus, there is 1 month left for the locality to complete this target.

Dong Nai clears land for 3 roads connecting Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai requested 6 districts and cities to urgently clear the land for 3 projects of DT 770B road, DT 773 road, DT 769 road connecting Long Thanh airport.