Deadline for handing over the Tuyen Quang - Ha Giang expressway site

Việt Bắc |

The Chairman of Tuyen Quang Provincial People's Committee requested localities to complete the handover of the entire Tuyen Quang - Ha Giang expressway site before April 5.

At the recent online meeting with the Government Standing Committee, Chairman of the Provincial People's Committee Nguyen Van Son requested localities and relevant agencies to hand over the entire site to the contractor for the Tuyen Quang - Ha Giang expressway construction before April 5, 2025.

Difficulties in materials such as earth, construction stone have been resolved by Tuyen Quang province to ensure meeting the needs of contractors.

By the end of March 2025, there are still some locations on the entire Tuyen Quang - Ha Giang expressway that have not been cleared in Ham Yen and Yen Son districts (about more than 500m). The progress reached 30.62% of the contract value, 4.36% behind the project progress contract.

The Chairman of Tuyen Quang Provincial People's Committee has requested Ham Yen, Yen Son districts and relevant agencies to speed up the construction of resettlement areas and issue Land Use Rights Certificates to households subject to relocation. Ensure items and conditions for people to be able to build houses.

On April 1, the People's Committee of Yen Son district reported on the project implementation progress, and the site clearance on this local route has completed the inventory of 100% of the areas that need site clearance.

Meanwhile, the site clearance at the resettlement areas has been 100% completed and handed over to the construction unit. 121 households subject to relocation have been handed over resettlement land.

Previously, Lao Dong Newspaper had many reports about the slow progress and infrastructure in disarray in the resettlement areas of Tuyen Quang - Ha Giang expressway and some related issues that have caused people to not want to move to the resettlement areas.

This has affected site clearance and the construction progress of the Tuyen Quang - Ha Giang expressway.

Việt Bắc
TIN LIÊN QUAN

Unfinished resettlement, bottleneck in the progress of Tuyen Quang expressway

|

The delay in relocating people to resettlement areas and site clearance is a bottleneck that needs to be removed to ensure the progress of the Tuyen Quang - Ha Giang expressway.

Living in the expressway resettlement area, people are worried

|

Some resettlement areas in Tuyen Quang and Ha Giang are built on unstable geology, or next to mineral mines, causing people to live in fear.

Unfinished resettlement infrastructure for Tuyen Quang Expressway

|

Tuyen Quang - Although they have moved to resettlement areas for a long time, giving up land for expressway projects, many households have not really stabilized their lives.

Securities plummeted, down 82.28 points

|

Selling pressure occurred as soon as the stock market opened after receiving information that the US was imposing tariffs on trading partners, including Vietnam.

Organizing separate test scores for independent candidates in high school graduation exams

|

HCMC - Candidates studying under the old and new programs will take the exam at different exam scores in this year's high school graduation exam.

The White House states why Russia is not subject to counterpart tariffs

|

President Donald Trump announced the imposition of countervailing tariffs on February 2 on 185 countries and territories, but Russia is not on the list.

Hanoi promotes tourism with a unique gift festival

|

Hanoi To stimulate tourism, from April 11 to 13, Hanoi will organize the 2025 Tourism gift Festival.

New developments in the case of a valedictorian becoming a high school slide in Thanh Hoa

|

C.T.H - a student of class 10A4 at Le Hong Phong High School (Bim Son, Thanh Hoa) has dropped out of school after a scandal from the valedictorian.

Unfinished resettlement, bottleneck in the progress of Tuyen Quang expressway

Việt Bắc |

The delay in relocating people to resettlement areas and site clearance is a bottleneck that needs to be removed to ensure the progress of the Tuyen Quang - Ha Giang expressway.

Living in the expressway resettlement area, people are worried

Việt Bắc |

Some resettlement areas in Tuyen Quang and Ha Giang are built on unstable geology, or next to mineral mines, causing people to live in fear.

Unfinished resettlement infrastructure for Tuyen Quang Expressway

Việt Bắc |

Tuyen Quang - Although they have moved to resettlement areas for a long time, giving up land for expressway projects, many households have not really stabilized their lives.