Lien Khuong Airport reopens from August 19th

Phúc Khánh |

Lam Dong - After more than 5 months of suspension to repair the runway and taxiway, Lien Khuong airport will reopen from 0:00 on August 19.

On the afternoon of July 21, Lien Khuong International Airport said that it had notified airlines, operating units and relevant agencies to proactively prepare facilities, personnel and necessary conditions to serve operations when the airport reopens.

According to the planned schedule, Lien Khuong airport will officially resume operations from 0:00 on August 19th.

Đến hiện tại, đường băng cất hạ cánh sân bay Liên Khương đã cơ bản hoàn thành phần xây dựng. Ảnh: Phúc Khánh
Up to now, the runway for Lien Khuong airport has basically completed the construction part. Photo: Phuc Khanh

The project to repair the runway and taxiway of Lien Khuong International Airport was started on March 4 with a total investment of more than 1,032 billion VND.

This is a level I aviation project, including items to repair the entire runway, 3, 250m long, 45m wide, taxiway and technical infrastructure and equipment to ensure flight operation.

To ensure progress, the investor has mobilized nearly 500 officials, engineers and workers to work on duty at the construction site.

In which, more than 450 workers are working in shifts day and night, along with many machines and equipment operating continuously.

The reopening of Lien Khuong airport is expected to restore air transport operations, create favorable conditions for tourism and trade development; and connect transportation of Lam Dong province as well as the Central Highlands region.

Phúc Khánh
RELATED NEWS

Accelerate construction, determined to put Lien Khuong airport into operation on August 19

|

Lam Dong - Provincial leaders requested ACV and construction units to accelerate the repair project, ensuring Lien Khuong airport resumes operation from August 19.

After more than 5 months of repairs, Lien Khuong airport is expected to reopen from August 19

|

Lam Dong - Lien Khuong Airport is proposed to resume operations from August 19 after more than 5 months of suspension for repair.

Determination to bring the Lien Khuong airport upgrade project to completion on schedule

|

Lam Dong - After more than 3 months of construction, the Lien Khuong airport upgrade project has reached more than 50% of the volume, and units are determined to accelerate to meet the progress.

Vietnam national team starts a new day full of excitement, ready for ASEAN Cup 2026

|

The Vietnamese team started a unique and exciting morning in Chonburi (Thailand), actively improving physical strength and tactics before the ASEAN Cup 2026.

Purchased sales are 5 times higher than sold, PNJ changes payment method

|

Phu Nhuan Jewelry Joint Stock Company (PNJ) will apply a maximum daily payment limit according to actual capacity for all acquisition transactions nationwide.

Accelerate construction, determined to put Lien Khuong airport into operation on August 19

Phúc Khánh |

Lam Dong - Provincial leaders requested ACV and construction units to accelerate the repair project, ensuring Lien Khuong airport resumes operation from August 19.

After more than 5 months of repairs, Lien Khuong airport is expected to reopen from August 19

Phúc Khánh |

Lam Dong - Lien Khuong Airport is proposed to resume operations from August 19 after more than 5 months of suspension for repair.

Determination to bring the Lien Khuong airport upgrade project to completion on schedule

Phúc Khánh |

Lam Dong - After more than 3 months of construction, the Lien Khuong airport upgrade project has reached more than 50% of the volume, and units are determined to accelerate to meet the progress.