Determination to bring the Lien Khuong airport upgrade project to completion on schedule

Phúc Khánh |

Lam Dong - After more than 3 months of construction, the Lien Khuong airport upgrade project has reached more than 50% of the volume, and units are determined to accelerate to meet the progress.

Construction day and night on the large construction site

In the early days of June, the construction atmosphere at Lien Khuong airport was urgent, with the determination to bring the project to completion on schedule.

Khu vực tập kết nguyên vật liệu thi công sửa chữa, nâng cấp sân bay liên khương luôn bảo đảm phục vụ thi công. Ảnh: Phúc Khánh
The raw material gathering area for the construction, repair and upgrade of Lien Khuong airport is always guaranteed to serve construction. Photo: Phuc Khanh

On the large construction site, hundreds of workers and machinery operate continuously according to the motto "three shifts, four crews", taking advantage of favorable weather to speed up progress.

Mr. Nguyen Van Trung, a runway construction worker, said that after completing his task at the Long Thanh airport project, he and many colleagues were transferred to Lien Khuong airport to work.

“The brothers are determined to do all the work, not all the time. The goal is to complete the project on schedule so that the airport can soon resume operation, serving the travel needs of the people,” Mr. Trung shared.

Sân bay Liên Khương đang được thi công xuyên ngày đêm, với quyết tâm đưa dự án về đích đúng hạn. Ảnh: Nghĩa Nguyễn
Lien Khuong airport is under construction day and night, with the determination to bring the project to completion on schedule. Photo: Nghia Nguyen

Up to now, many important items have achieved positive results. According to the Management Board of the project to repair the runway and taxiway of Lien Khuong International Airport, the auxiliary aggregate stone foundation item for the runway has been completed 100%; the underlying crushed stone layer has reached 98%, and the upper layer has reached about 96%.

Khu vực trước nhà ga hạ cánh sân bay Liên Khương đang từng bước được hoàn thiện. Ảnh: Phúc Khánh
The area in front of the Lien Khuong airport landing terminal is being gradually completed. Photo: Phuc Khanh

The ground items of the runway, taxiway, material sidewalks and drainage system are also basically completed by over 90% of the volume. About 1.8km of runway has been completed.

Efforts to reach the finish line before August 25.

According to construction units, the most important and complex item currently is the construction of cement concrete for the runway surface. This is the structural part that directly bears the load when the aircraft takes off and lands, so the technical requirements are very high.

Đến hiện tại, 1,8 km đường cất hạ cánh đã hoàn thành. Ảnh: Phúc Khánh
Up to now, 1.8 km of runway has been completed. Photo: Phuc Khanh

While the M150/25 cement concrete layer has been completed, contractors are focusing manpower and equipment to accelerate the construction progress of the M350/45 cement concrete layer.

ACC Aviation Construction Corporation currently achieves a concrete pouring capacity of 1,000 - 1,300m3/day. VINADIC and VINACONEX units also maintain a capacity of 400 - 600m3/day to ensure the overall progress of the project.

Các đơn vị thi công đang chạy đua với thời gian để đưa dự án về đính đúng hạn. Ảnh: Phúc Khánh
Construction units are racing against time to bring the project to completion on schedule. Photo: Phuc Khanh

In parallel with infrastructure construction, technical equipment items are also deployed synchronously. All power cables serving the project have been fully gathered at the construction site.

The air traffic light system has completed ordering, and the remaining equipment is being completed procedures for installation according to plan.

The project management board said that there are currently 491 on-duty personnel at the construction site, of which 453 workers are directly involved in construction. For the contractor alone, ACC arranges about 300 workers to work continuously in shifts.

According to Mr. Nguyen Thanh Nhan, Management Board of the project to repair the runway and taxiway of Lien Khuong International Airport, the progress pressure in the remaining 2 months is very high.

Tập trung tối đa các nguồn lực, phương tiện để hoàn thành dự án trước ngày 25.8.2026. Ảnh: Phúc Khánh
Focus maximum resources and means to complete the project before August 25, 2026. Photo: Phuc Khanh

However, with the support of the locality and the determination of the construction units, the project is being maximally focused on resources to be completed before August 25, 2026.

When completed, Lien Khuong airport will have more synchronous and modern infrastructure, contributing to improving exploitation capacity, meeting the increasing demand for air transport and promoting socio-economic and tourism development of Lam Dong.

Phúc Khánh
RELATED NEWS

Ho Chi Minh City Ring Road 3 project achieves 76% progress, determined to accelerate to complete on schedule

|

Ho Chi Minh City - Ho Chi Minh City Ring Road 3 Project has reached 76% progress, contractors are focusing their efforts on construction to accelerate to the finish line by the end of this year.

Lien Khuong airport construction site urgently deploys construction

|

Lam Dong - After more than 3 weeks of construction, the construction site of the Lien Khuong airport upgrade project is being urgently implemented, ensuring the set schedule.

Lien Khuong airport must be constructed to ensure the set schedule

|

Lam Dong - Chairman of the Provincial People's Committee Ho Van Muoi requested the construction of Lien Khuong airport upgrade "calculated in days and hours", ensuring completion on schedule and ahead of schedule.

The numbers show that Elon Musk is incredibly rich

|

Elon Musk became the first person in the world to own more than 1,000 billion USD, with asset scale far exceeding what most people can imagine.

Pretty girl" Ngo Lan Huong: I studied at Foreign Trade University and once thought I would work in import and export

|

Em xinh say hi Ngo Lan Huong shared about her professional views and the past of almost not pursuing art.

Ukraine lost more than 1,460 soldiers last week

|

The Russian Ministry of Defense said on June 12 that Ukrainian forces lost more than 1,460 soldiers in the operating area of the Western Combat Group in the past week.

The moon's words "Binh Xuan Truong" and the journey to find the martyr's grave for 50 years

|

Thanh Hoa - For more than 50 years, Mr. Do Dinh Ninh's family has been deeply concerned about the journey to find the martyr's grave. Taking DNA samples from relatives of martyrs has ignited hope.

Ho Chi Minh City Ring Road 3 project achieves 76% progress, determined to accelerate to complete on schedule

Bảo Tú |

Ho Chi Minh City - Ho Chi Minh City Ring Road 3 Project has reached 76% progress, contractors are focusing their efforts on construction to accelerate to the finish line by the end of this year.

Lien Khuong airport construction site urgently deploys construction

Phúc Khánh |

Lam Dong - After more than 3 weeks of construction, the construction site of the Lien Khuong airport upgrade project is being urgently implemented, ensuring the set schedule.

Lien Khuong airport must be constructed to ensure the set schedule

Phúc Khánh |

Lam Dong - Chairman of the Provincial People's Committee Ho Van Muoi requested the construction of Lien Khuong airport upgrade "calculated in days and hours", ensuring completion on schedule and ahead of schedule.