Accelerate construction, determined to put Lien Khuong airport into operation on August 19

Phúc Khánh |

Lam Dong - Provincial leaders requested ACV and construction units to accelerate the repair project, ensuring Lien Khuong airport resumes operation from August 19.

Progress of many items reaches over 90%

On June 16, Mr. Y Thanh Ha Nie Kdam - Member of the Party Central Committee, Secretary of the Lam Dong Provincial Party Committee and the provincial working delegation inspected the progress of the Project to repair runways and taxiways at Lien Khuong International Airport.

Quang cảnh buổi làm việc giữa lãnh đạo tỉnh Lâm Đồng với chủ đầu tư và các đơn vị thi công sân bay Liên Khương. Ảnh: Phúc Khánh
Overview of the working session between leaders of Lam Dong province with the investor and construction units. Photo: Phuc Khanh

According to Vietnam Airports Corporation (AVC), the project has a total investment of more than 1,032 billion VND, started on March 4, 2026 and is expected to be completed, bringing Lien Khuong airport back into operation on August 19, 2026.

Up to now, many important items have achieved high progress. Ground foundation for runways, rolling roads and material curbs are 100% completed; auxiliary compensation aggregate stone foundation reaches 100%; underground crushed stone layer reaches 96%, upper layer reaches 90%; cement concrete runway items are 100% completed.

Ông Y Thanh Hà Niê Kđăm - Ủy viên Trung ương Đảng, Bí thư Tỉnh ủy Lâm Đồng phát biểu tại buổi làm việc. Ảnh: Phúc Khánh
Mr. Y Thanh Ha Nie Kdam - Member of the Party Central Committee, Secretary of the Lam Dong Provincial Party Committee spoke at the working session. Photo: Phuc Khanh

Representatives of the ACV Construction Investment Project Management Board committed to completing the project on schedule, soon putting Lien Khuong airport back into operation to serve people, tourists and develop the local economy and society.

Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai requested ACV and related units to continue to focus maximum resources, take advantage of favorable weather to accelerate progress, ensure quality and safety of the project.

Bà Nguyễn Thị Hồng Phượng - Thành viên Hội đồng quản trị Tổng Công ty Cảng hàng không Việt Nam báo cáo tại buổi làm việc. Ảnh: Phúc Khánh
Ms. Nguyen Thi Hong Phuong - Member of the Board of Directors of Vietnam Airports Corporation reported at the working session. Photo: Phuc Khanh

Lien Khuong Airport plays a new driving force for development

Secretary of the Lam Dong Provincial Party Committee Y Thanh Ha Nie Kdam acknowledged the efforts of ACV, the Project Management Board and contractors in focusing manpower, equipment, and organizing continuous construction to accelerate progress.

ACV đang huy động tối đa nhân lực, phương tiện tăng tốc hoàn thành dự án theo tiến độ đã đề ra. Ảnh: Phúc Khánh
ACV is mobilizing maximum manpower and vehicles to accelerate to complete the project according to the set schedule. Photo: Phuc Khanh

The Provincial Party Secretary requested units to continue to mobilize maximum manpower and machinery, proactively respond to unfavorable weather, accelerate the construction of the remaining items to complete the project on schedule, and put Lien Khuong airport back into operation on August 19, 2026.

According to Mr. Y Thanh Ha Nie Kdam, this is not only an aviation infrastructure repair project but also a project of strategic significance for the province's development.

Công tác thi công diễn ra khẩn trương, liên tục trên đại công trường sân bay Liên Khương. Ảnh: Phúc Khánh
Construction work takes place urgently and continuously at the large construction site of Lien Khuong airport. Photo: Phuc Khanh

In the new development orientation, improving the operating capacity of Lien Khuong airport will contribute to reducing logistics costs; at the same time, shortening the transportation time of goods to international markets such as Singapore, South Korea and many other potential markets.

Bí thư Tỉnh ủy Lâm Đồng Y Thanh Hà Niê Kđăm tặng quà cho các đơn vị thi công. Ảnh: Nguyễn Luân
Secretary of the Lam Dong Provincial Party Committee Y Thanh Ha Nie Kdam presents gifts to construction units. Photo: Nguyen Luan

Lam Dong province is also orienting the development of the airport area associated with a new urban space, forming a modern service, tourism and logistics ecosystem.

At the same time, the province will coordinate with ACV and ministries and sectors to study expanding aviation infrastructure, restoring and opening more international routes.

Công nhân hăng say thi công trên công trường. Ảnh: Phúc Khánh
Workers enthusiastically work on the construction site. Photo: Phuc Khanh

Towards the 11th Da Lat Flower Festival and international cultural and tourism events, provincial leaders requested ACV to fully prepare infrastructure conditions to serve exploitation.

Phúc Khánh
RELATED NEWS

Thuy Phuong canal renovation project accelerates to finish before the 2026 rainy and flood season

|

Hanoi is accelerating the progress of the Thuy Phuong canal renovation project, contributing to improving drainage capacity and reducing flooding for the Northwest region.

Morning news 16. 6: Expected reopening time of Lien Khuong airport

|

Morning news on June 16: Preparing personnel for villages and residential groups after arrangement; After more than 5 months of repairs, Lien Khuong airport is expected to reopen from August 19;...

After more than 5 months of repairs, Lien Khuong airport is expected to reopen from August 19

|

Lam Dong - Lien Khuong Airport is proposed to resume operations from August 19 after more than 5 months of suspension for repair.

Land plots under pressure, apartments enter price adjustment phase

|

Apartment prices in some major cities have begun to adjust, but this segment is still leading in terms of interest, far exceeding land plots and villas.

Hanoi Chairman: Only relocate people when new resettlement areas are completed

|

Hanoi - Chairman of the City People's Committee said that people will only be relocated when new resettlement areas with synchronous technical and social infrastructure are completed.

Spreading the education promotion movement in Nghe An homeland

|

Nghe An - The movement to encourage learning is continuing to spread strongly from grassroots levels to key schools, contributing to building a lifelong learning spirit.

Woman lies blocking the front of a car in traffic, traffic police investigate

|

Quang Tri - Traffic police are verifying the case of a woman standing in the middle of the road, spreading her arms and then lying in front of a car on DT16 road, causing danger to traffic.

Ho Chi Minh City residents begin dismantling houses to hand over land to expand central road

|

Ho Chi Minh City - Many households on Tran Binh Trong street are dismantling houses and handing over land for the road expansion project from 5m to 23m, in order to reduce congestion.

Thuy Phuong canal renovation project accelerates to finish before the 2026 rainy and flood season

Minh Hạnh |

Hanoi is accelerating the progress of the Thuy Phuong canal renovation project, contributing to improving drainage capacity and reducing flooding for the Northwest region.

Morning news 16. 6: Expected reopening time of Lien Khuong airport

HUYỀN TRANG - DUY HƯNG |

Morning news on June 16: Preparing personnel for villages and residential groups after arrangement; After more than 5 months of repairs, Lien Khuong airport is expected to reopen from August 19;...

After more than 5 months of repairs, Lien Khuong airport is expected to reopen from August 19

Phúc Khánh |

Lam Dong - Lien Khuong Airport is proposed to resume operations from August 19 after more than 5 months of suspension for repair.