Including the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway project with a total length of about 52 km. The expressway is planned to have a scale of 6 expressway lanes, with a design speed of 100 km/h.
Phase 1, the project is invested in the form of public-private partnership (PPP), with a scale of 4 expressway lanes, continuous emergency lanes for the entire route, roadbed width of 25.5m, investment capital of about VND 17,116 billion.
Another major infrastructure project is the 47.4 km long Ho Chi Minh City Ring Road 4 (formerly the section through Binh Duong province) with an investment capital of VND 21,702 billion, the project will start construction in June 2025.

Phase 1, the project to invest in a full 4-lane expressway, including a continuous emergency lane with a roadbed width of 25.5m, designed speed of 100 km/h. Notably, the section from VSIP 2A Industrial Park to My Phuoc 3 Industrial Park is synchronized with a scale of 62 m, 10 lanes, designed speed of 80km/h...
Becamex IDC Corporation has also started construction of 4 real estate infrastructure projects.
In May 2025, the Corporation started construction of infrastructure for 2 ecological industrial parks in Bau Bang district, formerly Binh Duong province. Of which, Bau Bang Industrial Park expansion phase 2 has an area of 380 hectares with a total investment of VND 5,762 billion. The Cay Truong Industrial Park project is 700 hectares wide with a total investment of VND 5,459 billion.
Notably, this enterprise is investing in 2 large-scale social housing projects for workers. The social housing area in Dinh Hoa area 5 (Binh Duong ward) has an investment capital of 1,353 billion VND to build 2,372 apartments. The social housing project in Zone 6 Viet Sing (Thuan An Ward) has an investment capital of VND 1,590 billion, building 1,867 apartments.
Not enough land for construction
Currently, the most important are the two transport infrastructure projects. Site clearance work has been delayed, affecting the project's progress.
Of which, the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway project is 52 km long, 6.5 km preserved in its original state, and 45.6 km of the expressway was renovated. Currently, only 9.5 km has been handed over within Phuoc Hoa Rubber Joint Stock Company, 36.1 km has not been handed over.
For the Ho Chi Minh City Ring Road 4 project, the site handed over for construction has not been as committed, leading to the risk of project delays.
Currently, Becamex IDC Corporation is organizing the construction of the section with available land.